United Partition Systems, Inc. v. United States

95 Fed. Cl. 42, 2010 U.S. Claims LEXIS 786, 2010 WL 4005182
CourtUnited States Court of Federal Claims
DecidedOctober 12, 2010
DocketNo. 03-1242C
StatusPublished
Cited by19 cases

This text of 95 Fed. Cl. 42 (United Partition Systems, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United Partition Systems, Inc. v. United States, 95 Fed. Cl. 42, 2010 U.S. Claims LEXIS 786, 2010 WL 4005182 (uscfc 2010).

Opinion

[47]*47OPINION AND ORDER

LETTOW, Judge.

In this contract case, a post-trial judgment was issued in favor of plaintiff, United Partition Systems, Inc. (“United Partition”). See United Partition Sys., Inc. v. United States, 90 Fed.Cl. 74 (2009) (“United Partition II ”).1 That judgment became final when the government dismissed an appeal it had taken from the judgment. United Partition Sys., Inc. v. United States, No.2010-5068 (Fed. Cir. June 21, 2010) (order dismissing appeal under Fed. R.App. P. 42(b)). Now, United Partition has filed a motion for an award of attorneys’ fees and expenses pursuant to the Equal Access to Justice Act (“EAJA”), 28 U.S.C. § 2412(d). It seeks an award of $112,562.01 in attorneys’ fees and expenses, $14,512.50 in fees for paralegals and law clerks, and $8,559.21 in other expenses.2 The government resists such an award, maintaining that its position in the underlying litigation was substantially justified and questioning the bases for, and reasonableness of, United Partition’s attorneys’ fee request.

BACKGROUND3

United Partition is a manufacturer of prefabricated modular buildings, primarily but not exclusively for indoor use. Having obtained a Multiple Award Schedule contract from the General Services Administration (“GSA”), United Partition’s product consequently was included on the Federal Supply Schedule (“FSS”) by GSA. On June 5, 2000, the Air Force issued a delivery order to United Partition for the construction and installation of a modular building inside a warehouse at Luke Air Force Base (“AFB”), coupled with the removal of three existing modular buildings. United Partition II, 90 Fed.Cl. at 79-80. Prior to the issuance of the delivery order, United Partition’s representatives and Air Force personnel held a meeting at Luke AFB during which they agreed upon the use of particular materials for the construction of the modular building. Id. at 78-79.

United Partition substantially performed under the delivery order and nearly completed construction of the building. United Partition II, 90 Fed.Cl. at 81-83. However, the Air Force expressed concerns whether construction of the modular building met the terms of the contract. Id. at 80-81. Among other things, Air Force personnel questioned (1) United Partition’s placement of data and electrical wiring in the same raceways, (2) its use of hardboard substrate wall panels covered in a vinyl-clad finish because those panels might not meet the contract’s requirement that the modular building walls be “Class-A fire rated and UL [Underwriters Laboratory] approved,” (3) its use of UL-listed electric conduit wrap for the installation of the building’s wiring system in place of a purported contractual requirement that such wiring be installed in “UL approved raceway channels,” and (4) its planned placement of HVAC condensing units outside the warehouse walls rather than on top of the modular’ building. Id. at 79-83.4 On approx[48]*48imately August 18, 2000, the Air Force demanded that United Partition cease work on the project and vacate Luke AFB. Id. at 81. Following numerous inconclusive exchanges between United Partition and Air Force personnel regarding whether the building materials and placement of components were satisfactory, the Air Force’s contracting officer terminated the contract for default on August 20, 2001. Id. at 82-85. United Partition was not allowed to return to Luke AFB to correct deficiencies and complete construction. Id. at 90. United Partition’s building was dismantled, and another contractor constructed a replacement building using some of the materials United Partition had provided. United Partition was then assessed excess reprocurement costs. Id. at 86.

Subsequent to the termination of the contract, United Partition filed a claim with the Air Force’s contracting officer. See United Partition I, 59 Fed.Cl. at 631. After that claim was denied by the Air Force’s contracting officer, United Partition took an appeal to the Armed Services Board of Contract Appeals (“ASBCA” or “Board”), where the key issue was whether the Air Force’s contracting officer had authority to act on the claim. Id. The Board ruled that the Air Force’s contracting officer did not have such power and that United Partition’s claim should have been transferred to GSA’s contracting officer because the disputed issues regarding the default related to materials subject to the FSS schedule contract and concerned whether United Partition’s performance was “excusable” within the meaning of 48 C.F.R. [“FAR”] 8.405-5 and Clause I-FSS-249-B of the schedule contract. See United Partition I, 59 Fed.Cl. at 633-36 (quoting In re Appeals of United Partition Sys., Inc. ASBCA Nos. 53915, 53916, 03-2 BCA ¶ 32,264, 2003 WL 2012838 (May 02, 2003)). The Board consequently dismissed United Partition’s appeal for lack of jurisdiction. United Partition then filed a jurisdietionally protective complaint in this court on May 20, 2003, alleging a breach of contract, a breach of the duty to cooperate, and a flawed termination for default resulting in a termination for convenience by the Air Force. United Partition I, 59 Fed.Cl. at 633. Five days later, the Air Force’s contracting officer referred United Partition’s claim to GSA’s contracting officer, who within five months issued a decision consistent with that of the Air Force’s contracting officer, rejecting United Partition’s claim and upholding the Air Force’s demand for excess reprocurement costs. Id.

In this court, the government moved to dismiss United Partition’s complaint for lack of subject matter jurisdiction, relying on the fact that the Air Force contracting officer did not have jurisdiction to act on United Partition’s claim and arguing that the court was accordingly lacking authority under the Contract Disputes Act, 41 U.S.C. § 605, at the time United Partition filed its complaint. See United Partition I, 59 Fed.Cl. at 633. In denying that motion, the court held that the Air Force’s contracting officer had jurisdiction over some aspects of United Partition’s performance of the delivery order, but he also had responsibility to forward the submission to GSA’s contracting officer for resolution of United Partition’s exeusability claim, which had not been done. Id. at 639-40. Consequently, “United Partition could properly treat its claim as denied pursuant to 41 U.S.C. § 605(c)(5) and bring its claim within the jurisdiction of this [c]ourt by filing a timely complaint,” which had been accomplished. Id. at 640. In doing so, the court commented that “[although the Ah* Force’s contracting officer did not retain authority to evaluate United Partition’s exeusability defense, that is precisely what he did in issuing his final decision denying United Partition’s claim and demanding reprocurement costs.” Id. at 636; see also id. at 643 (noting the “exeusability aspect of United Partition’s claim”).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brass v. United States
127 Fed. Cl. 505 (Federal Claims, 2016)
Wollman v. United States
Federal Claims, 2015
Whr Group, Inc. v. United States
121 Fed. Cl. 673 (Federal Claims, 2015)
Sufi Network Services, Inc. v. United States
785 F.3d 585 (Federal Circuit, 2015)
Hyperion, Inc. v. United States
118 Fed. Cl. 540 (Federal Claims, 2014)
Ulysses, Inc. v. United States
117 Fed. Cl. 772 (Federal Claims, 2014)
Bcpeabody Construction Services, Inc. v. United States
117 Fed. Cl. 408 (Federal Claims, 2014)
Prochazka v. United States
116 Fed. Cl. 444 (Federal Claims, 2014)
Miles Construction, LLC v. United States
113 Fed. Cl. 174 (Federal Claims, 2013)
Sufi Network Services, Inc. v. United States
113 Fed. Cl. 140 (Federal Claims, 2013)
Metropolitan Van & Storage, Inc. v. United States
101 Fed. Cl. 173 (Federal Claims, 2011)
DGR Associates, Inc. v. United States
97 Fed. Cl. 214 (Federal Claims, 2011)
Greenhill v. United States
96 Fed. Cl. 771 (Federal Claims, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
95 Fed. Cl. 42, 2010 U.S. Claims LEXIS 786, 2010 WL 4005182, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-partition-systems-inc-v-united-states-uscfc-2010.