Bcpeabody Construction Services, Inc. v. United States

117 Fed. Cl. 408, 2014 U.S. Claims LEXIS 678, 2014 WL 3640776
CourtUnited States Court of Federal Claims
DecidedJuly 23, 2014
Docket1:13-cv-00378
StatusPublished
Cited by2 cases

This text of 117 Fed. Cl. 408 (Bcpeabody Construction Services, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bcpeabody Construction Services, Inc. v. United States, 117 Fed. Cl. 408, 2014 U.S. Claims LEXIS 678, 2014 WL 3640776 (uscfc 2014).

Opinion

Application by a prevailing plaintiff for an award of attorneys’ fees and expenses pursuant to the Equal Access to Justice Act, 28 U.S.C. § 2412; no substantial justification for the government’s position; hourly rates; expenses; bond premiums as expenses

OPINION AND ORDER

LETTOW, Judge.

A judgment on the administrative record was issued in plaintiffs favor in this post-award bid protest contesting a construction contract awarded by the Department of the Army, United States Army Corps of Engineers, Jacksonville District (“the Corps” or “the government”) for work in Okeechobee County, Florida. Now before the court is an application by plaintiff, BCPeabody Construction Services, Inc. (“BCPeabody”), for an award of attorneys’ fees and expenses pursuant to the Equal Access to Justice Act (“EAJA”), 28 U.S.C. § 2412, and a Bill of Costs submitted pursuant to Rule 54(d) of the Rules of the Court of Federal Claims (“RCFC”).

BACKGROUND

The Corps issued a solicitation seeking proposals to construct a cutoff wall, repave a dike crown, and perform ancillary work in Okeechobee County, Florida. BCPeabody Constr. Servs., Inc. v. United States, 112 Fed.Cl. 502, 505 (2013). The solicitation was issued pursuant to 48 C.F.R. (“FAR”) § 15.101-2, invoking a lowest-price technically acceptable source selection process. Id. The solicitation also stated that the “government intended] to evaluate proposals and award a contract without discussions with offerors (except clarifications as described in FAR § 15.306(a)).” Id. To be considered technically acceptable, offerors were required to submit project information sheets “to demonstrate that the offeror and its subcontractors had experience performing the type of work requested in the solicitation,” ie., cutoff wall experience and earthen embankment experience. Id. Regarding the cutoff wall experience, one project information sheet had to specifically demonstrate prior experience “penetrating, excavating, and backfilling through an obstruction that could not be removed by a typical backhoe or excavator during cutoff wall construction.” Id. In its proposal, BCPeabody identified Bauer Foundation Corporation (“Bauer”) as its major subcontractor for the cutoff wall work and submitted two project information sheets to demonstrate Bauer’s cutoff wall experience. Id. BCPeabody, however, mistakenly submitted two copies of the same project information sheet, and the submitted project information sheet failed to make the specific showing related to prior experience “penetrating, excavating, and backfilling through an obstruction that could not be removed by a typical backhoe or excavator during cutoff wall construction.” Id. Accordingly, BCPea-body’s proposal was found to be technically unacceptable, and it was excluded from the competition. Id. at 505-06. BCPeabody’s proposal was the lowest-priced proposal and it was technically acceptable in all other respects. Id. at 506. Notably, the awardee, Edens Construction Co., Inc. (“Edens”), also proposed to use Bauer as a major subcontractor and submitted the requisite details regarding Bauer’s past experience with cutoff wall construction. Id. As a result, the contracting officer was well aware that Bauer possessed the necessary prior experience to successfully’ perform the work. Id. But for the duplication of one project information sheet and the omission of a second project information sheet, BCPeabody would have received the contract. Id.

*412 After learning that another offeror received the contract, BCPeabody requested a debriefing from the contracting officer. BCPeabody, 112 Fed.Cl. at 506. BCPeabody first learned of its copying error at this debriefing. Id. It submitted an agency-level protest which was denied and then filed a protest with the Government Accountability Office (“GAO”). Id. at 507. The GAO agreed with BCPeabody that the contracting officer had abused her discretion in failing to clarify the clerical mistake, given her knowledge that Bauer was well-qualified to perform the subcontracted work. Id. The GAO nonetheless denied relief, finding that BCPeabody’s protest was deficient because BCPeabody had proffered to GAO a project information sheet from Bauer Foundations Canada, a separate legal entity from Bauer, but it only had a letter of commitment from Bauer to perform the work. Id. BCPeabody thereafter filed suit in this court on June 6, 2013, seeking a preliminary injunction to bar the Corps from proceeding with the contract awarded to Edens. BCPeabody, 112 Fed.Cl. at 507. The court granted the preliminary injunction, id. and ultimately granted BCPeabody’s Motion for Judgment on the Administrative Record, setting aside the Corps’ contract award, id. at 514. The Corps was directed to restore BCPeabody to the competition and reevaluate the proposals that were submitted. Id.

The court’s decision rested upon a finding that the copying mistake was a “minor or clerical error” within the terms of FAR § 15.306(a), which meant that the contracting officer could have allowed BCPeabody to clarify its proposal without having to engage in discussions. BCPeabody, 112 Fed.Cl. at 512-13. In making this determination, the court noted that the missing project information sheet did not “bear on price or involve information that the contracting officer did not already know. Inclusion of a second project information sheet would not have materially altered the terms of BCPeabody’s offer.... [T]he contracting officer was well aware that Bauer was a qualified subcontractor.” Id. at 511. The court further held that, while the contracting officer had discretion under FAR § 15.306(a) to clarify the mistake, it was unreasonable and an abuse of discretion for her to fail to do so in the circumstances. Id. at 512 (“Once the contracting officer became aware of the suitability of Bauer’s past experience with cutoff wall construction, she could not reasonably rate Bauer differently for BCPeabody as contrasted to Edens[, the awardee].”).

BCPeabody now seeks an award of attorneys’ fees and expenses in the amount of $47,716.06, pursuant to the EAJA, see Pl.’s Mot. & Application for Award of Att’ys’ Fees and Related Nontaxable Expenses (“Pl.’s Mot. for Fees”) at 4, ECF No. 71. It has also submitted a Bill of Costs totaling $19,176.85, pursuant to RCFC 54(d). Pl.’s Bill of Costs and Mem. in Support (“Pl.’s Bill of Costs”) at 1, ECF No. 72.

ANALYSIS

I. Attorneys’ Fees and Other Expenses

Congress enacted EAJA “ ‘to eliminate the barriers that prohibit small businesses and individuals from securing vindication of their lights in civil actions and administrative proceedings brought by or against the Federal Government.’ ” Scarborough v. Principi, 541 U.S. 401, 406, 124 S.Ct.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hyperion, Inc. v. United States
118 Fed. Cl. 540 (Federal Claims, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
117 Fed. Cl. 408, 2014 U.S. Claims LEXIS 678, 2014 WL 3640776, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bcpeabody-construction-services-inc-v-united-states-uscfc-2014.