Hubbard v. United States

480 F.3d 1327, 75 Fed. Cl. 1327, 2007 U.S. App. LEXIS 6414, 2007 WL 817647
CourtCourt of Appeals for the Federal Circuit
DecidedMarch 20, 2007
Docket2003-5076, 2003-5080, 2005-5167
StatusPublished
Cited by56 cases

This text of 480 F.3d 1327 (Hubbard v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hubbard v. United States, 480 F.3d 1327, 75 Fed. Cl. 1327, 2007 U.S. App. LEXIS 6414, 2007 WL 817647 (Fed. Cir. 2007).

Opinion

FRIEDMAN, Senior Circuit Judge.

In this government contract case, in which the Court of Federal Claims held that the government had breached the contract, the contractor’s cross-appeal challenges the court’s ruling that he had not proven that the government’s breach had resulted in lost profits for him. The government’s appeal challenges the district court’s award to the contractor, under the Equal Access to Justice Act, 28 U.S.C. § 2412, of attorneys fees of $110,000 in a case in which the contractor recovered damages of $400.

We affirm the denial of lost profits damages, vacate the attorney fees award, and remand the case to the trial court to reconsider an attorney fees award under the standard we have described.

I

This case stems from a 1984 contract under which the cross-appellant Bill Hubbard (“Hubbard”) agreed to build and operate a mini-storage facility at a naval air station. The Navy agreed to provide the personnel to operate the facility and a rental office known as the Rent All Center. The financial arrangements were that Hubbard would give the Navy 17.5% of the business’ gross revenue and retain the rest.

Tensions arose between the parties in 1993 when Captain A1 Gorthy, Jr. became the new commander of the base. Despite Hubbard’s objection, Captain Gorthy moved the Rent All Center to a new location about two miles from the facility. Captain Gorthy also took other actions relating to the facility, described below, to which Hubbard objected.

In 1995, Hubbard filed suit in the Court of Federal Claims seeking damages for breach of contract. He contended that moving the Rent All Center violated the Navy’s contractual obligation to provide an on-site rental office. Hubbard v. United States, 52 Fed.Cl. 192, 194 (2002). Hubbard also contended that the Navy breached the contract by ending phone service to the rental facility before it was moved; reducing the hours of the Rent All Center; failing to post signs notifying customers of the new office’s location; allowing firefighters to conduct a training exercise at the storage facility site; and allowing other contractors to park at the storage facility, which damaged a concrete slab on which Hubbard planned to build another storage building. Id.

After a trial, the court held that Captain Gorthy’s decision to move “the Rent All Center breached both the implied duty to make reasonable decisions and the implied covenant of good faith and fair dealing,” id. at 196—a ruling not challenged in this *1330 appeal. The court found that Captain Gorthy’s “stated reasons for the move were pretextual, and that the move was engineered in bad faith, without regard, indeed, with deliberate and bad faith disregard, for the legitimate business interests of Mr. Hubbard.” Id. The court also found that the Navy’s permitting a fire drill at the storage facility and parking by other contractors on the slab breached the contract. Id. at 198. Lastly, the court found that the termination of telephone service, the reduction in office hours, and the delay in posting signs providing notice of the Rent All Center’s move did not breach the contract. Id. at 197-98.

At trial, Hubbard sought damages of $627,000—most of which represented profits he allegedly lost as a result of the contract breaches. The court rejected most of his claim because Hubbard had not shown that the breaches had caused his alleged lost profits. Id. at 199-200. It awarded damages of only $400, covering the cost of repaving the concrete slab.

Finally, the court concluded that

Because of the clear bad faith shown by the Navy in dealing with Mr. Hubbard, Mr. Hubbard has been forced to appeal to this court, after numerous attempts to resolve the case without resort to litigation, because it was impossible to deal reasonably with a business partner that had acted in bad faith. Accordingly, plaintiff is entitled to recover all its attorney costs, fees and expenses related to this litigation, including expert expenses, from the preparation for the filing of this suit until the current date.

Id. at 200.

The court wrote an additional opinion dealing with the attorney fees issue under the Equal Access to Justice Act. Hubbard v. United States, No. 95-396C, slip op. at 2-3 (Fed.Cl. Aug.26, 2003) (“Fees Op. 1 ”). The court first determined that the statutory conditions for awarding a fee were satisfied. The court ruled that the $400 damages it had awarded made Hubbard a “prevailing party” under the Act. It stated that although the Navy’s “conduct during the litigation phase of the dispute was generally justified,” its pre-litigation bad faith, which “seriously abused Plaintiffs contract rights, and amounted to harassment” and “needlessly forced this matter before the Court,” meant that the government’s position was not substantially justified. Id. at 4.

In determining the attorney fees, the court multiplied the number of attorney and paralegal hours billed by the rate specified in the Act, adjusted upward to reflect cost-of-living increases based on the Consumer Price Index. Hubbard v. United States, No. 95-396C, slip op. at 2-3 (Fed.Cl. July 14, 2005) (“Fees Op. 2”); Fees Op. 1 at 4. This came to $110,920.59. To this the court added total costs of $14,266.33, for a total attorney fees and costs award of $125,185.92.

II

Hubbard’s claim of lost profits damages was based upon two items of evidence. First, he presented a study by his expert, Mr. O’Keefe, that purported to show what the business’ profits would have been had there been no breach. Second, Hubbard himself testified about the profits he had expected to earn.

The Court of Federal Claims rejected this evidence because it did not establish that the breach of the contract (primarily the moving of the Rent All Center) caused the decrease in earnings that Hubbard attributed to the breach.

The court found that O’Keefe’s analysis did “not relate to the actual breach actions,” and that based on a review at Hubbard’s business records, the “rental *1331 revenue on a month-to-month basis varied considerably both before and after the breach, and that no reduction or fall-off in rental revenue can be attributable to the move based on the information before the court.” Hubbard, 52 Fed.Cl. at 199-200. The court rejected Hubbard’s own analysis for substantially the same reason.

Although a trier of fact perhaps could have concluded that Hubbard’s lost profits evidence showed the necessary causal connection between the breach and the losses, it did not compel that conclusion. We have no reason to reject, as contrary to the evidence, the trial court’s determination that the necessary causal connection had not been shown.

Ill

The Equal Access to Justice Act provides that “in any civil action brought by or against the United States ... a court shall award to a prevailing party other than the United States fees and other expenses ...

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mostafa v. United States
Federal Claims, 2026
NICHOLSON v. United States
Federal Claims, 2025
HYATT v. United States
Federal Claims, 2025
Haggart v. United States
Federal Claims, 2020
Fastship, LLC v. United States
Federal Claims, 2019
Hitkansut LLC v. United States
Federal Claims, 2019
Assessment and Training Solutions Consulting Corporation
Armed Services Board of Contract Appeals, 2018
Andrus v. United States
Federal Claims, 2017
Q Integrated Companies, LLC v. United States
133 Fed. Cl. 479 (Federal Claims, 2017)
Small v. United States
130 Fed. Cl. 88 (Federal Claims, 2016)
Sufi Network Services, Inc. v. United States
128 Fed. Cl. 683 (Federal Claims, 2016)
Brass v. United States
127 Fed. Cl. 505 (Federal Claims, 2016)
Shafer v. United States
Federal Claims, 2015
Military Aircraft Parts
Armed Services Board of Contract Appeals, 2015

Cite This Page — Counsel Stack

Bluebook (online)
480 F.3d 1327, 75 Fed. Cl. 1327, 2007 U.S. App. LEXIS 6414, 2007 WL 817647, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hubbard-v-united-states-cafc-2007.