Kenbridge Construction Co. v. United States

39 Cont. Cas. Fed. 76,549, 28 Fed. Cl. 762, 1993 U.S. Claims LEXIS 110, 1993 WL 298696
CourtUnited States Court of Federal Claims
DecidedAugust 5, 1993
DocketNo. 91-1581C
StatusPublished
Cited by9 cases

This text of 39 Cont. Cas. Fed. 76,549 (Kenbridge Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kenbridge Construction Co. v. United States, 39 Cont. Cas. Fed. 76,549, 28 Fed. Cl. 762, 1993 U.S. Claims LEXIS 110, 1993 WL 298696 (uscfc 1993).

Opinion

OPINION AND ORDER

FUTEY, Judge.

This contract case is before the court on defendant’s motion for summary judgment. Defendant argues that plaintiff waived its right to file its complaint when, upon receiving final payment under the contract, it executed a release of claims. Plaintiff counters that the release should not bar plaintiff’s instant claim because the parties intended to reserve this claim, even though the release does not so state.

Factual Background

On April 19, 1988, plaintiff and the government entered into contract No. DACA65-88-C-0042 for construction of a Troop Support Agency Headquarters Building at Fort Lee, Virginia. On May 18, 1988, plaintiff entered into a subcontract with Dwight Snead Landscaping & Paving Co. (Snead) to furnish labor, materials, and equipment necessary for much of the work. [764]*764The subcontract was subject to all of the terms and conditions of the prime contract between plaintiff and the government.

The sections of the contract relevant to the complaint deal primarily with storage of surplus materials generated during excavation and grading at the construction site. The contract required Snead to stockpile certain surplus and unsatisfactory material in on-site berms, and to dispose of other specified material off-site.

By letter dated June 20, 1988, plaintiff, on Snead’s behalf, notified the area engineer that it was concerned with the fact that there was a purported excess of 18,000 to 20,000 cubic yards of material on the building site, and Snead was not certain where to store this material. Plaintiff and Snead believed that the excess material needed to be transported and unloaded off-site. In a written response dated August 3, 1988, the area engineer informed plaintiff that it was to put the material in the on-site berms as specified by the contract. The area engineer also stated that Army personnel would remove any material in excess of that required for the berms.

Snead continued working on the site for approximately 2 years. On January 23, 1990, Snead notified plaintiff that it was unable to store approximately 22,900 cubic yards of material into the areas provided by the contract for such storage. On April 10, 1990, on Snead’s behalf, plaintiff requested that the government increase the contract amount by $196,485.71, for stockpiling the extra material. On April 16, 1991, the government denied plaintiff’s request for additional compensation because, in its opinion, the location of the stockpiled material was neither off-site, nor an inconvenience to the contractor.

On May 2, 1991, plaintiff submitted a certified claim to the contracting officer, which the contracting officer denied on August 15, 1991. On or about October 1, 1991,1 plaintiff executed the Payment Estimate. The Payment Estimate included a release, which stated that—

Unless otherwise indicated in the space provided at the end of this Release, the Contractor by executing Block 12 of this Payment Estimate hereby releases the United States and its officers and agents from all claims and demands arising under or by virtue of this contract.

Plaintiff executed Block 12 of the Payment Estimate without reserving its right to bring additional claims.

On November 12, 1991, plaintiff filed a complaint with this court. As in its claim before the contracting officer, plaintiff here alleges that it is entitled to an equitable adjustment of $196,485.71 for the transfer of surplus materials to an off-site location. On September 24, 1992, defendant filed a motion for summary judgment, arguing that plaintiff’s release precludes it from bringing the instant claim. The parties have filed all appropriate responses to this motion. Oral argument was held on July 7, 1993.

Discussion

I. Summary Judgment

Summary judgment is appropriate when there are no genuine issues of material fact and the moving party is entitled to judgment as a matter of law. RCFC 56(c); Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 247, 106 S.Ct. 2505, 2509, 91 L.Ed.2d 202 (1986); Jay v. Secretary, DHHS, 998 F.2d 979, 982 (Fed.Cir.1993). A fact is material if it might significantly affect the outcome of the suit under the governing law. Anderson, 477 U.S. at 248, 106 S.Ct. at 2510.

The party moving for summary judgment bears the initial burden of demonstrating either the absence of any genuine issue of material fact or the absence of evidence to support the non-moving party’s case. Celotex Corp. v. Catrett, 477 U.S. 317, 325, 106 S.Ct. 2548, 2553, 91 L.Ed.2d [765]*765265 (1986); Jay, 998 F.2d at 982. If the moving party demonstrates an absence of genuine issues of material fact, then the burden shifts to the non-moving party to show that a genuine factual dispute does exist. Sweats Fashions, Inc. v. Pannill Knitting Co., 833 F.2d 1560, 1563 (Fed.Cir.1987). Alternatively, if the moving party can show that there is an absence of evidence to support the non-moving party’s case, then the burden shifts to the non-moving party to proffer such evidence. Celotex, 477 U.S. at 325, 106 S.Ct. at 2553.

The court must resolve any doubts about factual issues in favor of the non-moving party, Matsushita Elec. Indus. Co. v. Zenith Radio Corp., 475 U.S. 574, 587, 106 S.Ct. 1348, 1356, 89 L.Ed.2d 538 (1986); Litton Indus. Prods., Inc. v. Solid State Sys. Corp., 755 F.2d 158, 163 (Fed.Cir.1985), to whom the benefit of all presumptions and inferences run. Jay, 998 F.2d at 982; H.F. Allen Orchards v. United States, 749 F.2d 1571, 1574 (Fed.Cir.1984), cert. denied, 474 U.S. 818, 106 S.Ct. 64, 88 L.Ed.2d 52 (1985).

II. Release as Claim Waiver

In the instant case, plaintiff executed a release without reserving its right to bring additional claims. The release is a contractual provision, and its interpretation is a matter of law. P.J. Maffei Bldg. Wrecking Corp. v. United States, 732 F.2d 913, 916 (Fed.Cir.1984). The plain and unambiguous language of this release indicates that, unless plaintiff reserves its right to bring additional claims, it discharges the government from all claims arising under the contract. See George Hyman Constr. Co. v. United States, 832 F.2d 574, 579 (Fed.Cir.1987).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ingham Regional Medical Center v. United States
126 Fed. Cl. 1 (Federal Claims, 2016)
IMS Engineers-Architects, P.C. v. United States
92 Fed. Cl. 52 (Federal Claims, 2010)
Imprimis Investors LLC v. United States
83 Fed. Cl. 46 (Federal Claims, 2008)
Information Systems & Networks Corp. v. United States
68 Fed. Cl. 336 (Federal Claims, 2005)
City of Gettysburg v. United States
64 Fed. Cl. 429 (Federal Claims, 2005)
Jackson Construction Co. v. United States
62 Fed. Cl. 84 (Federal Claims, 2004)
Perry-McCall Construction, Inc. v. United States
46 Fed. Cl. 664 (Federal Claims, 2000)
Air-Sea Forwarders, Inc. v. United States
39 Fed. Cl. 434 (Federal Claims, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
39 Cont. Cas. Fed. 76,549, 28 Fed. Cl. 762, 1993 U.S. Claims LEXIS 110, 1993 WL 298696, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kenbridge-construction-co-v-united-states-uscfc-1993.