Speedway Orion JV

CourtArmed Services Board of Contract Appeals
DecidedMay 18, 2023
Docket63457
StatusPublished

This text of Speedway Orion JV (Speedway Orion JV) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Speedway Orion JV, (asbca 2023).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of - ) ) Speedway Orion JV ) ASBCA No. 63457 ) Under Contract No. N62473-19-D-1221 )

APPEARANCE FOR THE APPELLANT: Luke E. Thompson, Esq. Thompson Law & Consultation Lakeside, CA

APPEARANCES FOR THE GOVERNMENT: Craig D. Jensen, Esq. Navy Chief Trial Attorney Lynn A. Long, Esq. David M. Ruddy, Esq. Trial Attorneys

OPINION BY ADMINISTRATIVE JUDGE STINSON

Appellant Speedway Orion JV (Speedway), appeals a contracting officer’s denial of its June 30, 2022, claim in the amount of $19,099 (R4, tabs 13-14). Appellant elected to proceed under the Board's Small Claims (Expedited) procedures, Board Rule 12.2, and the parties agreed to submit this appeal for a decision on the record without a hearing pursuant to Board Rule 11. The Contract Disputes Act (CDA), 41 U.S.C. § 7106(b)(4)-(5), as implemented by Board Rule 12.2, provides that this decision shall have no precedential value and in the absence of fraud, shall be final, and conclusive, and may not be appealed or set aside. For the reasons stated below, Speedway’s appeal is denied.

FINDINGS OF FACT

1. On June 6, 2019, the Naval Facilities Engineering Systems Command (NAVFAC) Southwest awarded Speedway Contract No. N62473-19-D-1221 (the Contract) a multiple award, Indefinite Delivery, Indefinite Quantity (IDIQ) construction contract 8(a) set-aside for new construction, renovation, and repair of general building construction at various government installations located in California and other western states (R4, tab 1 at GOV0000001).

2. The Contract stated that “[t]he actual amount of work to be performed and the time of such performance will be determined by the Contracting Officer (CO) or his/her properly authorized representative, who will issue written task orders to the Contractor” (R4, tab 1 at GOV0000006). 3. The contract incorporated Defense Federal Acquisition Regulation Supplement (DFARS) 252.216-7006 ORDERING (MAY 2011), which provides, in part, that “[a]ny supplies and services to be furnished under this contract shall be ordered by issuance of delivery orders or task orders by the individuals or activities designated in the contract schedule” (R4, tab 1 at GOV0000070).

4. The Contract incorporated by reference Federal Acquisition Regulation (FAR) 52.236-15 Schedules for Construction Contracts, which required Speedway to submit a schedule in the form of a progress chart “showing the order in which the Contractor proposes to perform the work, and the dates on which the Contractor contemplates starting and completing the several salient features of the work . . . .” 48 C.F.R. § 52.236-15(a). FAR 52.236-15(b) provides that “[t]he Contractor shall enter the actual progress on the chart as directed by the Contracting Officer.”

5. The Contract included Navy Facilities Acquisitions Standard (NFAS) 5252.211- PHASED CONSTRUCTION SCHEDULE (SEP 1996), which provides that “[w]ithin the overall project schedule, commence and complete the work in phases” (R4, tab 1 at GOV0000075).

6. The Contract incorporated by reference FAR 52.242-14 Suspension of Work (R4, tab 1 at GOV0000028). Neither the Contract nor the Task Order incorporated, either in full or by reference, FAR 52.242-17 Government Delay of Work (R4, tabs 1, 10).

7. On September 13, 2021, NAVFAC issued Speedway Delivery Order No. N62473-21-F-5336 (the Task Order), 1 for multiple office renovation of ten buildings, B20, B76, B77, B91, B123, B3116, B3278, B3338, B3418, and B3602, at the Naval Base, San Diego, California, through the Southwest Regional Maintenance Center (SWRMC) (the Task Order). The Task Order provided that “[a]ll work will be in accordance with REV SOW 06/23/2021, 57 Request for Information (RFI) Government Responses and Latest Davis Bacon Wages CA20210001 Mod 13 dated 09/03/2021.” (R4, tab 10 at GOV0000121) The Task Order contained “no preestablished fixed contract prices,” with a set maximum amount of $947,777 (id.). The contract completion date (CCD) was June 13, 2022 (R4, tab 10 at GOV0000166).

1 The document is identified in block no. 2 as a “delivery order” (R4, tab 10 at GOV0000120), which is defined as “an order for supplies placed against an established contract or with Government sources.” 48 C.F.R. § 2.101, Definitions. Both parties refer to the document as a task order, which is defined as “an order for services placed against an established contract or with Government sources.” Id. Like the parties, we refer to the document herein as a task order. 2 8. RFI Question one inquired, “[w]ill the work on these buildings be performed in phases or simultaneously? In which order will the buildings be made available to perform the work? Are we to assume multiple mobilizations and if so, how many?” The government responded, “work will be done in phases. We do not have an overflow area large enough to support that many groups of personnel relocating at once. SWRMC facilities will coordinate relocating personnel to ensure the contractor doesn’t experience a pause in work.” (R4, tab 10 at GOV0000123)

9. The Task Order contained language similar to that set forth in the Contract, stating that “[t]he actual amount of work to be performed and the time of such performance will be determined by the CO or his/her properly authorized representative, who will issue written task orders to the Contractor” (id. at GOV0000121).

10. The Task Order Statement of Work, section 1.2, stated, in part, “contractor shall furnish all labor, management, supervision, tools, materials, equipment, incidental engineering, and transportation necessary to perform all ordered work in this task order,” and that “[c]onstruction of this project will require coordination with NAVFAC’s Construction Manager (CM) and Facilities Management Specialist (FMS) as the facility will remain operational during construction” (R4, tab 10 at GOV0000127-28).

11. The Task Order Statement of Work, section 1.2.1, Work Requirements, General Requirements, provided that “[c]onstruction shall be phased so that the KTR shall not work on more than one building at a time. KTR to coordinate phasing with FMS and customer.” (R4, tab 10 at GOV0000128)

12. The Task Order Statement of Work, section 1.4, OCCUPIED BUILDINGS, stated that “[t]he Contractor is advised that the building will be occupied and in use during the Contract period. It is necessary that the scheduling and performance of work be done in such a manner as to cause the least possible interference to the occupants. All life, fire safety requirements shall be operational at areas occupied during the work being performed.” (R4, tab 10 at GOV0000132)

13. The Task Order Statement of Work, section 1.5, PERIOD OF PERFORMANCE stated that “[t]he period of performance starts at contract/task order award and runs thru Final Inspection/BOD date. Many submittal requirements and benchmark dates will run concurrently. Allow for 60-day acquisition period. . . . Estimated period of performance for this task order: 221 days.” (R4, tab 10 at GOV0000133)

14. The Task Order Statement of Work, section 1.11, PRECONSTRUCTION SUBMITTALS, set forth requirements for submission of certain submittals prior to the

3 start of work (R4, tab 10 at GOV0000134). One of the required submittals specified in section 1.11 was the Planning/Construction Schedule, which Speedway was required to submit within 15 days after award of the Task Order (id.).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Speedway Orion JV, Counsel Stack Legal Research, https://law.counselstack.com/opinion/speedway-orion-jv-asbca-2023.