Martin County v. Polivka Paving, Inc.

44 So. 3d 126, 2010 Fla. App. LEXIS 6566, 2010 WL 1881089
CourtDistrict Court of Appeal of Florida
DecidedMay 12, 2010
Docket4D08-3701
StatusPublished
Cited by7 cases

This text of 44 So. 3d 126 (Martin County v. Polivka Paving, Inc.) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Martin County v. Polivka Paving, Inc., 44 So. 3d 126, 2010 Fla. App. LEXIS 6566, 2010 WL 1881089 (Fla. Ct. App. 2010).

Opinions

GERBER, J.

In this appeal, we maintain our previous holdings that a contractor seeking entitlement to recover home office overhead damages from the government must prove that a government-imposed delay required the contractor to indefinitely stand by to the point that the contractor was effective[128]*128ly suspended and unable to take on additional work. Here, because the contractor’s evidence at trial showed that it could not meet the entitlement prerequisites, we reverse the award of home office overhead damages to the contractor.

To provide better context for our holding, this opinion first will review the seminal case on home office overhead damages, Appeal of Eichleay Corp., ASBCA No. 5183, 60-2 B.C.A. (CCH) ¶ 2688, 1960 WL 538 (ASBCA 1960). Then we will review our three prior cases which developed the law in Florida regarding home office overhead damages. After that, we will examine this case, our holding, and our rationale. Finally, we will address preservation and remand issues requiring our resolution.

Eichleay and, its Progeny

In Eichleay, the Armed Services Board of Contract Appeals (the “board”) confronted a dispute between the government and a contractor over how to allocate the contractor’s home office expenses incurred during a suspension of work, where it was not practical for the contractor to undertake other work which might absorb those expenses. Id,. The board recognized that “[t]here is no exact method to determine the amount of such expenses to be allocated to any particular contract or part of a contract.” Id. Therefore, the board accepted a formula based on:

an allocation of the total recorded main office expense to the contract in the ratio of contract billings to total billings for the period of performance. The resulting determination of a contract allocation is divided into a daily rate, which is multiplied by the number of days of delay to arrive at the amount of the claim.

Id.

We first examined home office overhead damages and the Eichleay formula in Broward County v. Russell, Inc., 589 So.2d 983 (Fla. 4th DCA 1991), where we described the formula using the following diagram:

[[Image here]]

Id. at 984 n. 1. We held that “use of the Eichleay formula for the calculation of home office overhead damages is proper as long as there is competent evidence of actual damages of this variety having been sustained by the party seeking relief.” Id. at 984. However, we did not set forth the elements to prove entitlement to home office overhead damages.

Next, in Triple R Paving, Inc. v. Broward County, 774 So.2d 50 (Fla. 4th DCA 2000), we set forth the elements to prove entitlement to home office overhead damages:

Entitlement to [home office overhead] damages depends on proof of three elements:
(1) a government-imposed delay occurred; (2) the government required the contractor to “standby” during the delay; and (3) while “standing by,” [129]*129the contractor was unable to take on additional work.
Once the contractor proves the first two elements, a prima facie case of entitlement to [home office overhead] damages is established, [and] the burden of production then shifts to the government “to show either (1) that it was not impractical for the contractor to obtain ‘replacement work’ during the delay, or (2) that the contractor’s inability to obtain such work, or to perform it, was not caused by the government’s suspension.”

Id. at 57 (internal citations omitted).

Finally, in Broward County v. Brooks Builders, Inc., 908 So.2d 536 (Fla. 4th DCA 2005), we clarified Triple R’s “standby” element as follows: “The contractor must show effective suspension of much, if not all, of the work on the contract.” Id. at 540 (citation omitted).

The question presented in this case is whether we should maintain our previous holdings from Triple R and Brooks Builders that a contractor seeking entitlement to recover home office overhead damages from the government must prove that a government-imposed delay required the contractor to indefinitely stand by to the point that the contractor was effectively suspended and unable to take on additional work. Thus, we turn to this case.

The Instant Case

Martin County (the “county”) and Poliv-ka Paving, Inc. (the “contractor”) entered into an agreement whereby the contractor would construct soccer fields and related improvements at a county park for payment of $1,662,835.71. After clearing the site, the contractor realized that the county’s representations regarding the site’s conditions were different from the site’s actual conditions. Ultimately, the contractor added more fill than the county estimated to raise the elevation. The contractor also required several months beyond the contract’s completion date to finish the project. As work progressed, the county and the contractor agreed on change orders for some work which increased the price and extended the time of the contract. However, when the contractor finished the project, the county did not pay the contract balance. The county also did not pay for additional fill and repairs which the contractor performed.

The contractor sued the county for breach of contract. The contractor sought damages for the contract balance, the additional fill, and the repairs. The contractor also sought to recover “field office” overhead and “home office” overhead which it incurred from the original completion date to the actual completion date. At trial, the contractor’s expert testified that “field office” overhead means costs directly attributable to the project, such as the work trailer, sanitation, utilities, tools, and fuel. The expert testified that “home office” overhead means “costs associated with the home office that [are] funded by the projects ... which the company is performing.”

The contractor’s expert then turned to his method of calculating the contractor’s home office overhead damages, which method he later described as an “extended performance analysis.” The expert testified that this project represented about fifty percent of the work which the contractor intended to perform that year, and should have contributed that percentage of money to the contractor’s home office overhead during that time. The expert used that percentage to calculate the amount of money which the contractor’s additional work should have contributed to the contractor’s home office overhead during the extension period. The expert calculated that amount to be $550,501.93.

[130]*130The contractor’s expert testified that he was familiar with the Eichleay formula, but did not utilize it in this case. The expert explained that “Eichleay would be for a suspension ... and this job was never specifically suspended.” The expert added that the contractor, during this job, had other ongoing jobs which contributed to paying the contractor’s home office overhead. Despite those factors, the expert argued that the contractor still should be entitled to recover home office overhead damages because the county’s nonpayment caused the contractor to consume cash from its own accounts and, in turn, caused the contractor’s bonding company to refuse to provide bonds for new projects.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mohammad Salauddin v. Bank of America, N.A.
150 So. 3d 1189 (District Court of Appeal of Florida, 2014)
Young v. Becker & Poliakoff, P.A.
88 So. 3d 1002 (District Court of Appeal of Florida, 2012)
Henry v. Hoelke
82 So. 3d 962 (District Court of Appeal of Florida, 2011)
Miami-Dade County v. Eghbal
54 So. 3d 525 (District Court of Appeal of Florida, 2011)
Martin County v. Polivka Paving, Inc.
44 So. 3d 126 (District Court of Appeal of Florida, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
44 So. 3d 126, 2010 Fla. App. LEXIS 6566, 2010 WL 1881089, Counsel Stack Legal Research, https://law.counselstack.com/opinion/martin-county-v-polivka-paving-inc-fladistctapp-2010.