Airport Industrial Park, Inc. v. United States

59 Fed. Cl. 332, 2004 U.S. Claims LEXIS 8, 2004 WL 86186
CourtUnited States Court of Federal Claims
DecidedJanuary 16, 2004
DocketNo. 02-1077 C
StatusPublished
Cited by17 cases

This text of 59 Fed. Cl. 332 (Airport Industrial Park, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Airport Industrial Park, Inc. v. United States, 59 Fed. Cl. 332, 2004 U.S. Claims LEXIS 8, 2004 WL 86186 (uscfc 2004).

Opinion

OPINION

HEWITT, Judge.

Plaintiff filed this suit on August 28, 2002 alleging that defendant United States wrongfully terminated plaintiffs contract for work in Pittsburgh, Pennsylvania. Complaint (Compl.) UH 5, 7, ll.1 Defendant moved for [333]*333summary judgment on September 11, 2003, stating that plaintiffs “failure to obtain necessary bonding justifie[d] a termination for default.” Defendant’s Motion for Summary Judgment (defendant’s motion or MSJ) at 6. Defendant’s motion has been fully briefed by both parties. For the reasons discussed below, the court GRANTS defendant’s motion.

I. Background

The United States Army Corps of Engineers (the Corps) solicited bids on December 1, 1998 for construction and other work in Pittsburgh, Pennsylvania. Affidavit of Paul Chambers in Opposition to Motion for Summary Judgment (Chambers Aff.) 113; Compl. 112.2 Contract Number DACW59-99-C-0002 “New Dock Front, Pittsburgh Engineer Warehouse and Repair Shops, Neville Island, Pennsylvania” (the contract) was awarded to Airport Industrial Park, Inc., d/b/a P.E.C. Contracting Engineers (plaintiff) on March 25,1999. Declaration of Michael S. DeStefa-no in Support of Defendant’s Motion for Summary Judgment (DeStefano Deel.) H2, Ex. A. The contract stated that “[t]he Contractor shall begin performance within 10 calendar days and complete it within 365 calendar days after receiving notice to proceed.” 3 DeStefano Decl. Ex. A. The original amount of the contract was $4,646,931. Id.

The contract referenced regulations related to bonding required of the contract awar-dee.4 MSJ at 2-3 (citing Fed. Acquisition Reg. (FAR) §§ 52.228-1, -2, -15 at 48 C.F.R. §§ 52.228-1, -2, -15 (1998)). On March 25, 1999, plaintiff obtained a performance bond with a penal sum of $4,646,931.00 and a payment bond with a penal sum of $1,858,772.40, both from Amwest Surety Insurance Company (Amwest).5 DeStefano Deel. Exs. B, C. These bonds were approved by the Corps on April 14, 1999. MSJ at 3. Plaintiff also obtained on March 25, 1999 a reinsurance agreement for the performance bond in the amount of $2,646,831.00 provided by Swiss Reinsurance America Corporation (Swiss Re). Chambers Aff. H 9. The reinsurance agreement was accepted by the Corps on April 14,1999. DeStefano Decl. 115.

The original completion date was extended several times by contract modifications signed by plaintiff and the Corps. Defendant’s Reply to Plaintiffs Response to Defendant’s Motion for Summary Judgment, with Appendix (Def.’s Reply), Reply Declaration of Michael S. DeStefano (DeStefano Reply Decl.) 116. Modification P00004/Change “AE” extended the contract completion date until August 15, 2001. Id. Amwest became insolvent on June 7, 2001 and notified the Corps that its bonding of plaintiff for the contract was cancelled. DeStefano Decl. 115, Ex. E. The work on the contract was not complete. See Chambers Aff. 1110 (“The work was approximately 50% complete ... on August 17, 2001.”). The Corps notified plaintiff that plaintiff no longer had valid bonds for the contract and directed plaintiff to deliver “acceptable performance and payment bonds” to the Corps within ten days or a stop work order would issue. DeStefano Decl. Ex. F.

Plaintiffs counsel responded on July 20, 2001 by letter to the Corps stating that plaintiffs reinsurance agreement “clearly contemplates and covers both the performance bond and the payment bond.” DeStefano Deel. Ex. G. The Corps replied with a cure notice on July 31, 2001 stating that, among other conditions, “we have not received an acceptable Payment Bond in accordance with contract clause FAR 52.228-15.” DeStefano Decl. Ex. H. The cure notice stated that if the conditions were not cured “within 10 days after receipt of this notice, the Government may terminate for default under the terms and conditions of contract clause FAR [334]*33452.249-10, Default (Fixed-Price Construction).” Id. Plaintiff did not respond to the cure notice and did not obtain and provide a replacement payment bond. See DeStefano Decl. Ex. I (terminating plaintiffs contract for these reasons, among others); Chambers Aff. 1112 (mentioning various factors that “prevented P.E.C. Contracting Engineers from securing alternative payment bonds from new sources after Amwest Surety Insurance Company went insolvent”). The Corps terminated plaintiffs contract for default on August 17, 2001. DeStefano Decl. K11, Ex. I.

The government has had to defend against claims from subcontractors of plaintiff who seek payment for what they allege is unpaid work performed under the contract. Def.’s Reply at 2 n. 2. The contract work was finished by Swiss Re, but there has been no showing that the government filed claims against the reinsurance of the performance bond for any excess costs created by the need to complete plaintiffs work. Response to Defendant’s Motion for Summary Judgment (PL’s Resp.) at 2.

II. Discussion

A. Standard of Review

“Summary judgment shall be rendered if there is no genuine issue as to any material fact and the moving party is entitled to a judgment as a matter of law.” Coast Fed. Bank, FSB v. United States, 323 F.3d 1035, 1037 (Fed.Cir.2003); see also Rules of the United States Court of Federal Claims 56(c) (setting out the standard for summary judgment). Material facts are those “that might affect the outcome of the suit under the governing law.” Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986). A dispute over a material fact is “genuine” only if “a reasonable jury could return a verdict for the nonmoving party.” Id.

“Where a movant has supported its motion with affidavits or other evidence which, unopposed, would establish its right to judgment, the non-movant may not rest upon general denials in its pleadings or otherwise, but must proffer countering evidence sufficient to create a genuine factual dispute.” Sweats Fashions, Inc. v. Pannill Knitting Co., 833 F.2d 1560, 1562 (Fed.Cir.1987). “A nonmoving party’s failure of proof concerning the existence of an element essential to its case on which the nonmoving party will bear the burden of proof at trial necessarily renders all other facts immaterial and entitles the moving party to summary judgment as a matter of law.” Dairyland Power Coop. v. United States, 16 F.3d 1197, 1202 (Fed.Cir.1994).

B. Analysis

As many decisions of boards of contract appeals have held, failure to furnish adequate bonding required by a government procurement contract is a material breach that justifies termination for default. See, e.g., Dieleman Constr. Co., ENG BCA No. 6213, 96-2 B.C.A. (CCH) ¶ 28,430, 1996 WL 419850, 1996 Eng.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kostas Greek Food - Zorbas
Armed Services Board of Contract Appeals, 2021
Bowles v. United States
Federal Claims, 2019
State Corps v. United States
Federal Claims, 2019
Emiabata v. United States
Federal Claims, 2018
Quality Trust Inc.
Armed Services Board of Contract Appeals, 2016
Securiforce International America, LLC v. United States
125 Fed. Cl. 749 (Federal Claims, 2016)
Allen Engineering Contractor Inc. v. United States
611 F. App'x 701 (Federal Circuit, 2015)
Allen Engineering Contractor, Inc. v. United States
115 Fed. Cl. 457 (Federal Claims, 2014)
Pinckney v. United States
88 Fed. Cl. 490 (Federal Claims, 2009)
Keeter Trading Co. v. United States
79 Fed. Cl. 243 (Federal Claims, 2007)
Lanterman v. United States
75 Fed. Cl. 731 (Federal Claims, 2007)
Precision Pine & Timber, Inc. v. United States
62 Fed. Cl. 635 (Federal Claims, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
59 Fed. Cl. 332, 2004 U.S. Claims LEXIS 8, 2004 WL 86186, Counsel Stack Legal Research, https://law.counselstack.com/opinion/airport-industrial-park-inc-v-united-states-uscfc-2004.