Octagon Process Inc. v. United States

141 Ct. Cl. 599, 1958 U.S. Ct. Cl. LEXIS 97, 1958 WL 7368
CourtUnited States Court of Claims
DecidedMarch 5, 1958
DocketNo. 389-56
StatusPublished
Cited by6 cases

This text of 141 Ct. Cl. 599 (Octagon Process Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Octagon Process Inc. v. United States, 141 Ct. Cl. 599, 1958 U.S. Ct. Cl. LEXIS 97, 1958 WL 7368 (cc 1958).

Opinion

Jones, Chief Judge,

delivered the opinion of the court:

Plaintiff contractor brings this suit to recover the difference between the cost of steel drums which it alleges it was authorized to use under the terms of its supplies contract and the cost of more expensive drums which the plaintiff used when advised by the Air Force that the less expensive drums did not comply with the contract specifications. In support of their motions for summary judgment, the parties have submitted affidavits and exhibits. These documents, along with the pleadings and briefs, provide the basis for our decision.

On May 14, 1954, the Topeka Air Force Depot, United States Air Force, awarded plaintiff a fixed price contract, calling for the delivery, inter alia, of stated quantities of aircraft cleaning compound. Deliveries of the product were made under the contract during the months of August and September, 1954, in reconditioned drums which were embossed with an ICC stamp.

However, on September 13, 1954, plaintiff wrote the contracting officer requesting permission to use so-called “Rule 40” drums, i. e., reconditioned drums acceptable to the railroads under Rule 40 of Consolidated Freight Classification No. 20. By way of explanation plaintiff stated that a shortage of reconditioned ICC drums had developed in the Kansas City area where the subcontracting work was being performed, and as a result delivery of the cleaning compound was being hampered. This difficulty could be avoided, according to plaintiff, if it were permitted to use “Rule 40” drums, which were readily available, in completing the balance of its contract. It was plaintiff’s interpretation of the contract that “Rule '40” drums were acceptable since they conformed to the drum reconditioning requirements (MIL-R-3567A) of the contract.

[601]*601In a letter dated September 22, 1954, the contracting officer informed plaintiff that “Rule 40” drums would not be acceptable, even though they might have complied with Specification MIL-R-3567A, inasmuch as they did not meet the basic drum specification (JAN-P-110) of the contract, as did the ICC drums. Plaintiff replied on October 15, 1954, by reiterating its position that any drum may be furnished provided it meets the requirements of MIL-R-3567A, and asserted that the cleaning compound was non-hazardous and therefore need not be delivered in ICC drums.

By letter dated October 25, 1954, the contracting officer again stated his position that all drums must conform to the requirements of JAN-P-110 and that “Rule 40” drums did not so conform and were unacceptable. The contracting officer was thereafter advised by letter on November 15,1954, that .plaintiff would complete the contract using reconditioned ICC drums but would claim the difference in cost between the reconditioned ICC drum and the reconditioned “Rule 40” drum.

On November 22,1954, the contracting officer in a written communication entered formal findings and made a decision disallowing plaintiff’s requested use of “Rule 40” drums. Plaintiff appealed and a hearing was conducted before the Armed Services Board of Contract Appeals. On September 16,1955, an opinion was delivered in which plaintiff’s appeal was denied. A motion by plaintiff for rehearing and reconsideration was also denied. In seeking the difference between the price of the ICC drums actually used and the price of “Rule 4Ó” drums it was not allowed to use, plaintiff alleges arbitrary and capricious action in the ruling by the contracting officer.

Initially, it should.be indicated that the product giving rise to this dispute is described in Item No. 2 of the supply contract as:

7300-190100 Compound cleaning aircraft Spec 20015E dtd 23 Feb 49 — 55 gal drum.

Item No. 8 of the contract, relating to packing and marking requirements, provides in part as follows:

[602]*602PACKING AND MARKING:
The requirements set forth below shall apply to any contract issued hereon, and supersede any conditions inconsistent herewith. All specifications referenced below shall be of the issue in effect on the date of this Invitation For Bids.
a. Unit containers shall be of the following type:
m * * *
(2) Fifty-five (55) gallon metal drums 18 Gage conforming to the requirements of Specification JAN-P-110, applicable to Item 2.
(3) Others as follows: Reconditioned drums are acceptable, if they meet all requirements of MIL-R-3567A.

It is plaintiff’s contention that item 8 a (3) of the contract is not an adjunct nor part of item 8 a (2). Consequently, plaintiff argues, reconditioned drums are acceptable under the contract if they conform to the requirements of MIL-R-3567A. Whether the drums would qualify under Specification JAN-P-110 is immaterial, according to this interpretation. Absent other provisions in the contract and the interpretative acts of the parties under the agreement prior to the time this dispute materialized, we would be inclined to favor plaintiff’s argument. However, careful examination of other related provisions of the contract, and consideration of the practical interpretation attached to it by the parties, demonstrate the unreasonableness of plaintiff’s position.

Section 5.2 of Specification 20015E, which is incorporated into the contract under item 2 provides:

Packaging. — The compound shall be furnished in containers of the size specified by the Procuring Agency. The containers shall be steel and shall conform to Specifications JAN-P-110 or JAN-P-124 and the applicable Interstate Commerce Commission Regulations.

Specification JAN-P-110, incorporated into the contract by item 8 a (2) of the contract and Specification 20015E, provides the Joint Army-Navy specifications for 55-gallon metal drums for packaging and packing for overseas shipment. These specifications set forth requirements as to the type of steel; the enamel coating; the acceptable type of gaskets; the [603]*603capacity; the weight and thickness of the sheets of steel; the requirements concerning seams, heads, rolling hoops, closures, and linings; and the provisions for sampling, inspection, and tests. Item E5 Specification JAN-P-110 also provides as follows:

E-5. 7. O. O. regulations. — In addition to the requirements of this specification, drums shall conform to the requirements of the Interstate Commerce Commission Regulations.1

On the other hand, “Rule 40” drums need only be of 18-gauge steel and have welded seams. Rule 40 does not set forth specifications for the materials, finish, dimensions, hoops, gaskets, closures or any of the other requirements or tests prescribed in JAN-P-110. Furthermore, “Rule 40” drums do not have the “ICC” stamp embossed on them, thereby eliminating a convenient quality control factor which is important in the final acceptance of the drums and thus impeding the Government contracting officer in determining whether the contract specifications have been complied with. And by its very terms, Specification MIL-R-3567A would also seem to indicate that only JAN-P-110 drums will be acceptable if they have been reconditioned under the specification. For section 6 provides in pertinent part:

6.1 Ordering data. — Procurement documents should specify the following:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Elastomeric Roofing Associates, Inc. v. United States
26 Cl. Ct. 1106 (Court of Claims, 1992)
Utley-James, Inc. v. United States
34 Cont. Cas. Fed. 75,478 (Court of Claims, 1988)
American Electric Contracting Corp. v. United States
579 F.2d 602 (Court of Claims, 1978)
Consolidated Diesel Electric Co. v. United States
533 F.2d 556 (Court of Claims, 1976)
The Jack Stone Company, Inc. v. The United States
344 F.2d 370 (Court of Claims, 1965)

Cite This Page — Counsel Stack

Bluebook (online)
141 Ct. Cl. 599, 1958 U.S. Ct. Cl. LEXIS 97, 1958 WL 7368, Counsel Stack Legal Research, https://law.counselstack.com/opinion/octagon-process-inc-v-united-states-cc-1958.