P. Sanford Ross, Inc. v. United States

50 Ct. Cl. 168, 1915 U.S. Ct. Cl. LEXIS 119, 1915 WL 270
CourtUnited States Court of Claims
DecidedFebruary 23, 1915
DocketNo. 30808
StatusPublished
Cited by3 cases

This text of 50 Ct. Cl. 168 (P. Sanford Ross, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
P. Sanford Ross, Inc. v. United States, 50 Ct. Cl. 168, 1915 U.S. Ct. Cl. LEXIS 119, 1915 WL 270 (cc 1915).

Opinion

Atkinson, Judge,

reviewing the facts found to be established, delivered the opinion of the court:

The claimant entered into a contract with the United States for dredging earth and rock and constructing jetties in James Eiver, Ya. A copy of the contract and specifications forming part thereof are attached to the petition as Exhibit A.

The description of the work to be done was stated in paragraphs 18, 19, and 20 of the specifications as follows:

“ 18. Work to be done: The work to be done under these specifications consists in excavating and removing material from portions of the channel of the James Eiver; towing the material and disposing of it by casting it overboard, conveying it ashore, or dumping it; constructing pile jetties; revetting dikes and jetties with excavated material; and removing old wharf piles.

[169]*169“CHANNEL excavation.

“ 19. Localities: Channel excavation is to be carried on in the three following divisions of the river, in which it is proposed to secure a depth of 18 feet below mean low water:

“ Division 1, extending from Jetty B, about 800 feet below the lower city line of Eichmond, Va., to Jetty 28, about 8,300 feet below that line.

“ Division 2, extending from Jetty 41 to Jetty 49, about 2-| miles below the city line of Eichmond.

“ Division 3, situated in Kingsland Eeach, about 10 miles below Eichmond.

“20. Nature of work: In division 1 the work will consist in widening the channel 50 feet or more over a length of about 7,500 feet to the full projected width of 200 feet. In division 2 lumps in the channel are to be removed over a distance of about 1,600 feet so as to obtain the channel width of 200 feet. In division 3 the work will consist in excavating a channel 200 feet wide over a distance of about 2,600 feet.”

By paragraph 31 it was declared that material excavated from a greater depth than 1 foot below the prescribed depth of 18 feet or from outside the limits of the channel as marked by stakes and ranges will not be paid for, due allowance, however, being made for slide slopes.

The disposition of excavated material was to be made under instructions of the engineer, and no question is raised on that feature. The provisions of the specifications relative to conveying material ashore, dumping material, and transporting material appear in paragraphs 34, 35, and 36. as follows:

“ 34. Conveying material ashore: The price paid for conveying material, as described under subhead (2) of the preceding paragraph, will cover the cost of all plant and appliances used-for and incidental to said conveying, and all labor and other expense incurred in placing and disposing of the excavated material by this method. It is estimated that the quantity of material to be conveyed will be about 31,000 cubic yards, and that it will have to be conveyed an average distance of about 180 feet. It is not expected that the above quantity will be increased or diminished more than 50 per cent.

“ 35. Dumping material: It is estimated that about 35,000 cubic yards of material will be transported about 30 miles on dump scows to the vicinity of Jordans Point and dumped. This quantity may be increased or diminished as the exigencies of the work may require, although it is not expected that [170]*170the variation from the estimated quantity will be more than 50 per cent.

“ 36. Transporting excavated material: The prices bid for both earth and hard rock excavation will include the cost of transporting on scows the material between the extreme head of the work at Jetty B and Jetty No. 134, 6| miles below. An additional price to be named in the bid will be paid the contractor for transporting this material (which does not include that to be dumped near Jordans Point) below Jetty No. 134. It is estimated that the quantity of material to be so transported will be about 22,000 cubic yards (subject to a variation of 30 per cent) and that it will have to be carried on deck scows an average distance of 4 miles below Jetty 134.”

By the contract between the parties the specifications are made a part of it, and it is agreed—

“(a) The said party of the second part shall furnish all necessary material, labor, machinery, and appliances, and dredge earth and rock, construct jetties, and remove piles in James Biver at the following prices:

“For earth excavation, 133,400 cubic yards, more or less, at 37-^¶ cents per cubic yard.

“For hard rock excavation, 5,750 cubic yards, more or less, at $11.10 per cubic yard.

“For conveying excavated material from scows to points of deposit, as specified in paragraph 34 of the specifications, 31,000 cubic yards, more or less, at 27 cents per cubic yard.

“For transporting excavated material on deck scows below Jetty No. 134, as specified in paragraph 36 of the specifications, 22,000 cubic yards, more or less, at 15 cents per cubic yard.

“For dumping excavated material in vicinity of Jordans Point, as specified in paragraph 35 of the specifications, 35,000 cubic yards, more or less, at 22^ cents per cubic yard.”

The claimant proceeded with his work under the said contract, which required its completion within two years; that is, by November 14,1909. Finding that the work would not be completed by said date, the claimant, on October 21, 1909, made an application in writing for an extension of time to January 14,1910, stating some reasons for the application, and saying:

“And for the reasons above stated would respectfully request that this extension be granted without charges against us for superintendence and inspection.”

[171]*171The reply to said application stated that the extension was “ granted by the Chief of Engineers, United States Army, under provisions of paragraph 5 of the contract,” and added:

“ These provisions provide that all expenses for superintendence and inspection and all other actual losses and damages to the United States due to the delay will be deducted from any payments due or to become due to you.”

The claimant acknowledged receipt of said communication.

Again, on December 15, claimant applied for a further extension of two months from January 14 to March 14, 1910, which application was replied to by Maj. Morrow, of the Corps of Engineers, on December 21, stating that he was authorized by the Chief of Engineers, United States Army, “ to grant you an extension of time for a reasonable period, you to bear the necessary costs of inspection and superintendence.” The receipt of this reply to his application was at once acknowledged by claimant.

Paragraph 5 of the contract provided that an extension of time could be granted by the Chief of Engineers, and—

“ Should the original time limit be thus waived, all expenses for inspection and superintendence and all other actual losses and damages to the United States due to the delay beyond the time originally set for completion shall be determined by the party of the first part and deducted from any payments due or to become due the party of the second part.”

The cost of superintendence and inspection incurred by the United States during the periods of the two extensions was deducted from time to time from the payments made to the claimant and aggregated $1,616.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hol-Gar Manufacturing Corp. v. The United States
351 F.2d 972 (Court of Claims, 1965)
Loftis v. United States
76 F. Supp. 816 (Court of Claims, 1948)

Cite This Page — Counsel Stack

Bluebook (online)
50 Ct. Cl. 168, 1915 U.S. Ct. Cl. LEXIS 119, 1915 WL 270, Counsel Stack Legal Research, https://law.counselstack.com/opinion/p-sanford-ross-inc-v-united-states-cc-1915.