Rumley v. United States

169 Ct. Cl. 100, 1965 U.S. Ct. Cl. LEXIS 46, 1965 WL 8335
CourtUnited States Court of Claims
DecidedJanuary 22, 1965
DocketCong. No. 4-61
StatusPublished
Cited by12 cases

This text of 169 Ct. Cl. 100 (Rumley v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rumley v. United States, 169 Ct. Cl. 100, 1965 U.S. Ct. Cl. LEXIS 46, 1965 WL 8335 (cc 1965).

Opinion

Collins, Judge,

delivered the opinion of the court:

This congressional reference case1 was filed pursuant to H. Ees. 249, 87th Cong., 1st Sess., passed by the House of Eep-resentatives on July 10,1961. That resolution directed this court to report to Congress regarding the nature of a claim presented by the estate of George S. Eumley, and the amount, [102]*102if any, legally or equitably due from the United States.2 The word “plaintiff” hereinafter refers to George S. Bumley.3

The plaintiff and the defendant were parties to three separate contracts. Plaintiff asserts a valid claim founded upon one contract and the defendant admits the amount involved in this claim was withheld from the payment due plaintiff under that contract. Defendant refused to pay plaintiff its money because of counterclaims arising from the other two contracts. Previously, in an action brought under 28 U.S.C. § 1491, this court determined that neither plaintiff nor defendant was entitled to a net judgment. Rumley v. United States, 152 Ct. Cl. 166, 285 F. 2d 773 (1961). In the present case, plaintiff seeks to establish an equitable claim “in a broad non-juridical sense.” The court is now requested to determine and to advise the Congress, in light of this broad concept of “equity,” whether the counterclaims of the Government should prevent recovery by plaintiff.

The findings of fact by Commissioner Paul H. McMurray have been adopted, with modifications, by the court and are incorporated within this opinion. A brief statement of the facts follows:

Plaintiff herein claims he is entitled to $12,840, which is admittedly due for work on contract DA-30-280-QM-12130 (hereinafter referred to as QM-12130). The defendant has withheld and has refused payment under said contract because of its counterclaims arising under contract DA-30-280-QM-3833 (hereinafter referred to as QM-3833) and contract DA-30-352-TAP-1904 (hereinafter referred to as TAP-1904). This court, in its prior decision, established plaintiff’s claim in the amount of $12,840 under QM-12130 and the counterclaim of the defendant, under QM-3833, in the amount of $27,930. Begarding defendant’s counterclaim [103]*103based upon TAP-1904, in the amount of $1,143.19, plaintiff had admitted his liability. In view of the insolvency of the plaintiff at that time and his inability to satisfy any judgment, the defendant requested judgment on its counterclaims only to the extent required to offset plaintiff’s judgment in the amount of $12,840. The court, believing this to be reasonable and that such would “result in substantial justice to both parties,” ordered such an offset.

It was apparent at that time, as it is now, that the plaintiff had “no legal or equitable claim against the United States, in the sense of a claim enforceable in a court, under applicable legal standards.” Palmer-Bee Co. v. United States, 142 Ct. Cl. 485, 488 (1958).

Contract QM-3833 related to the manufacture of dufflebags. Plaintiff’s bid of 47 cents per unit was the lowest of 62 bids submitted. On June 12,1950, in response to an addendum to the invitation for bids, requiring packaging for overseas shipment instead of for domestic shipment, plaintiff failed to enclose a suggested alteration of his bid. On June 16,1950, defendant determined to award the contract to plaintiff. On June 17, 1950, prior to receiving notice of the award, plaintiff wrote to defendant advising that plaintiff’s bid had been based on errors in calculating costs and, at that time, plaintiff requested a necessary change upward in its bid price. Plaintiff’s letter expressed various notions regarding acceptance of the contract. First, plaintiff stated that he would take the contract, except for deliveries to four of the locations, if the price were increased by three-fourths of a cent. The plaintiff added that if the unit price were raised by 1 y2 cents, he would accept the entire contract although, because of expected losses confronting him, he suggested that part or all of the contract go to the Brown Manufacturing Company.

In June and July 1950, during conferences between the plaintiff and the contracting officer, plaintiff explained the various errors he had made in his calculations and requested that the unit price be raised to 54 cents per unit.4 On [104]*104August 11, 1950, plaintiff asked to be relieved from the contract on the ground of his inability to perform except at a substantial loss to himself and to his business.

On September 7,1950, the successor contracting officer recommended that the plaintiff be relieved of his obligations.5 His report recognized that plaintiff’s bid was “unusually low” and stated that the more normal range of bid prices would be 58 cents per unit and up. The report pointed out that the Philadelphia Quartermaster Depot’s Manufacturing Division had estimated, in June 1950, that “the labor and material costs for this item [would] be $.7033,” not including transportation and overhead costs, but the contracting officer added that “Government manufacturing costs may be as much as 25% or 30% higher than costs incurred by commercial firms.”6

On November 8, 1950, the Comptroller General ruled that he had no legal basis for increasing the price of contract QM-3833 and no legal basis for relieving plaintiff from his liability under the terms of the contract.7 In the face of increasing prices, due to the Korean situation, plaintiff finally wrote the contracting officer on December 28, 1950, requesting the Government to cancel the contract. The contracting officer replied that unless the plaintiff, by January 15, 1951, could give assurance of his performance, the contract would be terminated for default. By letter of January 17, 1951, plaintiff was notified that the contract was terminated and that the Government reserved its rights, including the right of repurchase. Plaintiff appealed the termination to the Armed Services Board of Contract Appeals.8

The defendant did not enter into new contracts for the purchase of the dufflebags until June 1,1951. In September 1951, the contracting officer submitted to plaintiff a claim for $66,121.60, based on the difference between the contract price under QM-3833 and the actual cost under the new contracts for purchase. Plaintiff also appealed from this determination to the ASBCA. Subsequently, the Government’s claim [105]*105was amended to $29,670.07, an amount which, in the opinion of the contracting officer, represented the excess which would have resulted had defendant made the new contracts for purchase and manufacture of the dufflebags within a reasonable time. By its opinion of September 12, 1952, the Armed Services Board of Contract Appeals (1) sustained the termination of the contract, but (2) rejected the assessment of excess costs since (a) the actual repurchase was made too late and (b) the amended claim was not made pursuant to the contract.9

Contract TAP-1904 was awarded to plaintiff on May 26, 1953. Pursuant to its terms, the Government shipped certain material to plaintiff on June 17, 1953. At the time of both the award and the shipment, plaintiff was ill and hospitalized.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Paul v. United States
20 Cl. Ct. 236 (Court of Claims, 1990)
California Canners & Growers Ass'n v. United States
7 Cl. Ct. 69 (Court of Claims, 1984)
Amick v. United States
5 Cl. Ct. 426 (Court of Claims, 1984)
Merchants National Bank v. United States
32 Cont. Cas. Fed. 72,455 (Court of Claims, 1984)
Rawlins v. United States
686 F.2d 903 (Court of Claims, 1982)
Eriez Magnetics Corp. v. United States
209 Ct. Cl. 673 (Court of Claims, 1976)
Phillips v. United States
207 Ct. Cl. 924 (Court of Claims, 1975)
O'Brien Dieselectric Corp. v. United States
207 Ct. Cl. 903 (Court of Claims, 1975)
H & H Manufacturing Co. v. United States
201 Ct. Cl. 799 (Court of Claims, 1973)
Burt v. United States
199 Ct. Cl. 897 (Court of Claims, 1972)
North Counties Hydro-Electric Co. v. United States
170 Ct. Cl. 241 (Court of Claims, 1965)

Cite This Page — Counsel Stack

Bluebook (online)
169 Ct. Cl. 100, 1965 U.S. Ct. Cl. LEXIS 46, 1965 WL 8335, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rumley-v-united-states-cc-1965.