Meridian Engineering Company v. United States

130 Fed. Cl. 147, 2016 U.S. Claims LEXIS 1956, 2016 WL 7496175
CourtUnited States Court of Federal Claims
DecidedDecember 30, 2016
Docket11-492 C
StatusPublished
Cited by3 cases

This text of 130 Fed. Cl. 147 (Meridian Engineering Company v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Meridian Engineering Company v. United States, 130 Fed. Cl. 147, 2016 U.S. Claims LEXIS 1956, 2016 WL 7496175 (uscfc 2016).

Opinion

41 U.S.C. §§ 601-613 (2006); 41 U.S.C. §§ 7101-7109 (2011) (Contract Disputes Act); 48 C.F.R. 31.105, 31.202, 31.203, 52.242-14, 52.243-4; Breach of Contract; Equitable Adjustment; Federal Rule of Evidence 702, 703 (Experts); Federal Rule of Evidence 802 (Hearsay); Show Cause Order.

POST TRIAL MEMORANDUM OPINION AND FINAL ORDER ON EQUITABLE ADJUSTMENT

BRADEN, Judge.

This post trial decision resolves the equitable adjustment that Meridian Engineering *151 Company (“Meridian”) is due for costs that it incurred when the Government suspended performance of a September 21, 2007 contract and for work that Meridian completed after the suspension was lifted. To facilitate review of this Post Trial Memorandum Opinion And Final Order, the court has provided the following outline:

I. Relevant Background.

II. Discussion.

A. Jurisdiction.

B. Standing.

C. Whether The Government Breached The September 21,2007 Contract.

1. Counts 7, 8 And 9 Of The May 19, 2014 Second Amended Complaint.

2. The Government’s Argument.
3. Meridian’s Response.
4. The Government’s Reply.
5. The Court’s Resolution.

D. The Measure Of Equitablé Adjustment That Meridian Is Entitled To Receive.

1. Fact Witnesses.

a. Ted Haworth, Former President Of Meridian.

b. Mark Sutton, Current President And Former Executive Vice-President Of Meridian.

2. Expert Testimony On Equitable Adjustment.

a. Meridian’s Expert In Construction Cost Accounting: Timothy Van Noy, C.P.A., C.F.E.

b. The Government’s Expert In Federal Government Contract Accounting: Sam Hadley, C.P.A., C.F.E., C.F.M.

3. The Court’s Resolution.

a. The Relevant Legal Standard.

b. “Claim Elements” Alleged In Counts 7, 8 And 9 Of The May 19, 2014 Second Amended Complaint.

i.Regarding Meridian’s Small Tools Costs.

ii. Regarding Meridian’s Payroll Burden Costs.

iii. Regarding Meridian’s Field Support Overhead Costs.

iv. Regarding Home Office Overhead Costs.

v. Regarding Meridian’s Use Of The USACE Manual.

vi. Regarding The Water Diversion System.

vii. Regarding Standby Equipment Costs.

viii. Regarding The Amount Of Time That Meridian Took To Perform The Backfill And Interim Protection Work Orders.

c. The Total Equitable Adjustment That Meridian Is Due For Count 7, 8 And 9 Of The May 19, 2014 Second Amended Complaint.

d. Under The September 21, 2007 Contract And The Contract Disputes Act, Meridian Also Is Entitled To Recover Interest On The Equitable Adjustment That It Is Due.

III.CONCLUSION.

* * *

I. RELEVANT BACKGROUND. 1

Meridian is an engineering and construction firm located in Tucson, Arizona, that specializes in heavy civil, structural, and industrial construction. PX 1000-5. On September 21, 2007, the Army Corps of Engineers (“USACE”) awarded Meridian a $5.8 million contract to complete a flood control project in Nogales, Arizona (“Chula Vista Project”). JX193-1.

After commencing work on the Chula Vista Project, Meridian encountered a series of problems. On July 29, 2011, due to disagreements over how these issues should be resolved, Meridian filed a Complaint in the United States Court of Federal Claims alleging that the Government breached the September 21, 2007 Contract and seeking *152 damages of $7.6 million. Compl. at ¶324. Subsequently, Meridian filed two amended complaints. ECF Nos. 83, 108. The Second Amended Complaint (“Sec. Am. Compl.”) contained fourteen counts. Sec. Am. Compl. at ¶¶ 31-387.

On January 27-30 and March 27-30, 2014, the court conducted a liability trial in this case. On July 22, 2015, the court determined that USACE did not breach the September 21, 2007 Contract, as alleged in Counts 1-6 and 10-13 of the Second Amended Complaint. See Meridian Engineering Company v. United States, 122 Fed.Cl. 381, 402-13, 415-22 (2015). In addition, the court decided that the USACE did not violate the implied duty of good faith and fail' dealing, as alleged in Count 14. Id. at 426. The court, however, reserved judgment on Counts 7, 8 and 9, that alleged the USACE owed Meridian payment for completed work. Id. at 414. With regard to these Counts, the Government was ordered to show cause why it did not breach the September 21, 2007 Contract, by failure to make timely payment for completed work. Id.

On October 23, 2015, the Government filed a Response (“Gov’t SC Br.”), admitting that it owed Meridian payment for completed work, but arguing that Meridian could not recover damages under breach of contract theory, because the appropriate remedy is an equitable adjustment. Gov’t SC Br. at 1-14. On December 7, 2015, Meridian filed a Response (“PL Resp.”), arguing that the Government’s October 23, 2015 Response to the Show Cause Order was hyper-technical and without merit. PL Resp. at 1-23. On February 29, 2016, the Government filed a Reply (“Gov’t Reply”). Gov’t Reply at 1-8.

On June 14, 2016, the parties filed a Joint Stipulation Of Fact (“Jt. Stip.”). Jt, Stip. at ¶¶ 1-12. Therein, the Government “acknowledge[d] that Meridian is entitled to compensation for costs incurred in connection with Counts 7, 8 and 9.” Jt. Stip. at ¶ 6. The Government also stipulated that it did not challenge $964,355.73 of the $1,391,210.73 that Meridian claims. Jt. Stip. at ¶ 10.

On June 16, 2016, the court held an eviden-tiary hearing on the quantum of damages that remained in dispute, ie., $426,855. 6/16/2016 TR at 2436-671. On June, 24, 2016, the Government filed a Supplemental Brief. ECF No. 144. On June 28, 2016, Meridian filed a Responsive Supplemental Brief. ECF No. 145.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rustler Construction, Inc. v. District of Columbia
211 A.3d 187 (District of Columbia Court of Appeals, 2019)
Meridian Engineering Company v. United States
885 F.3d 1351 (Federal Circuit, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
130 Fed. Cl. 147, 2016 U.S. Claims LEXIS 1956, 2016 WL 7496175, Counsel Stack Legal Research, https://law.counselstack.com/opinion/meridian-engineering-company-v-united-states-uscfc-2016.