Yul Lim Construction Co., Ltd.

CourtArmed Services Board of Contract Appeals
DecidedJuly 15, 2025
Docket63483
StatusPublished

This text of Yul Lim Construction Co., Ltd. (Yul Lim Construction Co., Ltd.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Yul Lim Construction Co., Ltd., (asbca 2025).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of - ) ) Yul Lim Construction Co., Ltd. ) ASBCA No. 63483 ) Under Contract No. W912UM-19-C-0002 )

APPEARANCE FOR THE APPELLANT: Yong Eui Song, Esq. Central IP & Law Seoul, Korea

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney SoCheung Lee, Esq. Engineer Trial Attorney U.S. Army Engineer District, Far East Seoul, Korea

OPINION BY ADMINISTRATIVE JUDGE THRASHER ON THE GOVERNMENT’S MOTION TO DISMISS

This claim arises from a dispute regarding repair work at two buildings at Daegu Air Base in Korea. The parties had elected to have the appeal heard on the written record pursuant to Board Rule 11. After the briefing on the merits was completed, the government filed a motion to dismiss for lack of jurisdiction based on the bilateral execution of a settlement agreement. Appellant contends that the settlement agreement was only a partial settlement and that it did not cover all items raised in its previously-filed claim. The Board notified the parties that it would consider the motion to dismiss as a motion for summary judgment because there is evidence referred to outside of the pleadings. For the reasons stated below, we grant the government’s motion and deny the appeal.

STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION

1. The United States Army Corps of Engineers (government or USACE) awarded contract W912UM-19-C-0002 to Yul Lim Construction Co., Ltd. (Yul Lim or appellant) for the repair of two buildings at Daegu Air Base, Korea (R4, tab 2 at 4-6). The contract was awarded on December 31, 2018 (id. at 6). 2. On September 6, 2022, Yul Lim submitted a certified claim for a 740-day extension and ₩11,725,043,090 (approximately $1,454,628) 1 plus interest (R4, tab 9 at 2). The claim was based on seven major delay factors: (1) late site release, (2) roof reinforcement on B3605, (3) DOAS and WAF design changes on B3571, (4) domestic water supply, (5) paint spray booth design change on B3571, (6) COVID-19 delays, and (7) severe weather conditions (id. at 11-12).

3. On December 19, 2022, Yul Lim appealed the deemed denial of its claim to the Board, which was docketed as ASBCA No. 63483.

4. On March 24, 2023, the contracting officer issued a final decision (COFD) determining that the project was delayed 700 days, granting a 661-day extension, with 127 compensable days (R4, tab 1 at 36-37). The COFD stated that “[t]he [g]overnment intends to issue a unilateral modification effecting the days and amount owed to Yul Lim” (id. at 23). However, the COFD did not include a specific monetary amount owed to Yul Lim (see id.).

5. On January 18, 2024, the parties filed a Joint Stipulation to Partially Dismiss, with prejudice, four of the six delay issues 2 raised by Yul Lim (stip. to partially dismiss dtd. January 18, 2024). In the Joint Stipulation, the parties stated that they had resolved the issues pertaining to “four of the six major delay periods through the [COFD] . . . in which the Government provided a time extension and compensable delay damages” (id. at 2). However, the joint stipulation did not include a specific monetary amount owed to Yul Lim (see id.). The Board granted this request, leaving only the issues of two delay events and direct costs (Bd. Order dtd. January 25, 2024).

6. The two remaining delay issues were 1) the late site release and 2) roof reinforcement on building B3605. On the late site release, the contracting officer had denied Yul Lim’s claim for a 42-day delay (R4, tab 1 at 35). On the roof reinforcement, Yul Lin sought 322 days of delay. The contracting officer found that there were 347 days of delay, of which the government was responsible for 315. However, he also found that Yul Lim was responsible for 288 days of concurrent delay, leaving a net of 27 compensable days. (Id. at 35-36)

7. The January 18, 2024, Joint Stipulation to Partially Dismiss framed the unresolved issue with respect to the roof reinforcement delay as “whether Yul Lim’s

1 The contract uses an exchange rate of Korean Won ₩1,128.1127/$1.00 (R4, tab 2 at 5). 2 Yul Lim did not seek compensation for the domestic water supply delay as it overlapped the delay pertaining to the DOAS and WAF design change on B3571 (R4, tab 9 at 12).

2 delay on B3571 was concurrent with the Government’s delay of its roof repair on B3605 (jt. stip. at 2).

8. On January 26, 2024 (the same day as the Board’s order granting the partial dismissal), the parties filed opening briefs pursuant to Board Rule 11. On February 15, 2024, the parties filed Rule 11 response briefs.

9. Neither party has filed any communications or other extrinsic evidence dated between January 26 and March 5, 2024, that shed light on the parties’ efforts to resolve their dispute.

10. On March 5, 2024, the parties bilaterally executed Modification No. P00002 (Mod. 2) for “settlement of contractor’s claim dated 6 September 2022 and based on the Contracting Officer’s final determination dated, 24 March 2023” (R4, tab 63 at 1, 4). The Scope of Work in Mod. 2 further specified that:

[i]t also includes all fees and time for the following works as equitable adjustments:

1. Building 3571

a. Architectural Work

(1) Removal of existing metal lath/insulation on above ceiling in around arms room area, RFI-0019.

(2) Install hardware in the existing door (Approved by the user, 607th)

b. Mechanical Work

(1) Change capacity for DOAS system

c. Electrical Work

(1) LED display for fire alarm system, RFI0035

(2) Added control part material per QAB comments

2. Building 3605

3 (1) Change materials from capillary water barrier (CWB) to NFSM or light weight concrete, RFI-0011.

(1) Revise equipment type (HV-1 & HV-2)

(2) No water supplies

(1) Change Paint Spray Booth to explosionproof type, RFI-0064

(2) Roll-Up Door Power Connection, RFI-0060

(3) Add offshore/local material per QAB comments

(Id. at 4)

11. With respect to delay, Mod. 2 granted 661 days of government delay, of which 534 were concurrent to delays by Yul Lim (and, thus, non-compensable), leaving 127 days of compensable delay, which is what the contracting officer had granted in the final decision (compare R4, at 1 at 36, tab 63 at 6). The modification specifically listed each component of the 661 days granted, including 315 days for the roof reinforcement delay (R4, tab 63 at 6).

12. Mod. 2 provided Yul Lim with ₩283,851,949 as a settlement amount and ₩19,560,511 as interest (id.). The modification also contained the following release language:

It is further understood and agreed by all parties that this adjustment constitutes compensation in full on behalf of the contractor . . . for all cost and markups attributable to the circumstances giving rise to this modification for all delays related thereto, and for the performance of the change within the time frame stated.

(Id. at 6) In fulfillment of Mod. 2, USACE paid Yul Lim a total of ₩303,412,460 on June 6, 2024 (R4, tab 64).

13. On July 1, 2024, the President of Yul Lim signed a statement, admitting that “[w]hen one of my employees brought me [Mod. 2] for my signature, I signed it

4 after asking him whether the amount was correctly stated without actually reviewing [Mod. 2] because of my busy schedule” (app. resp. at enc. K). There are no documents in the record to indicate Yul Lim involuntarily signed Mod. 2 or had any objections to the signing of Mod. 2.

14. While the Rule 11 merits briefs were still pending before the Board, on June 17, 2024, the government filed a motion to dismiss for lack of jurisdiction, citing what it contended was a full settlement of the dispute in Mod. 2.

DECISION

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Bell Bci Co. v. United States
570 F.3d 1337 (Federal Circuit, 2009)
Pure Gold, Inc. v. Syntex (u.s.a.), Inc.
739 F.2d 624 (Federal Circuit, 1984)
Mingus Constructors, Inc. v. The United States
812 F.2d 1387 (Federal Circuit, 1987)
C. Sanchez and Son, Incorporated v. United States
6 F.3d 1539 (Federal Circuit, 1993)
McAbee Construction, Inc. v. United States
97 F.3d 1431 (Federal Circuit, 1996)
Metric Constructors v. United States
314 F.3d 578 (Federal Circuit, 2002)
Metcalf Construction Company v. United States
742 F.3d 984 (Federal Circuit, 2014)
T.L. Roof & Associates Construction Co. v. United States
38 Cont. Cas. Fed. 76,534 (Federal Claims, 1993)
C & H Commercial Contractors, Inc. v. United States
35 Fed. Cl. 246 (Federal Claims, 1996)
Axion Corp. v. United States
68 Fed. Cl. 468 (Federal Claims, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
Yul Lim Construction Co., Ltd., Counsel Stack Legal Research, https://law.counselstack.com/opinion/yul-lim-construction-co-ltd-asbca-2025.