Metric Constructors v. United States

314 F.3d 578, 60 Fed. R. Serv. 260, 2002 U.S. App. LEXIS 26093, 2002 WL 31828862
CourtCourt of Appeals for the Federal Circuit
DecidedDecember 18, 2002
Docket02-5086
StatusPublished
Cited by17 cases

This text of 314 F.3d 578 (Metric Constructors v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Metric Constructors v. United States, 314 F.3d 578, 60 Fed. R. Serv. 260, 2002 U.S. App. LEXIS 26093, 2002 WL 31828862 (Fed. Cir. 2002).

Opinion

BRYSON, Circuit Judge.

Metric Constructors, Inc., entered into a contract with the National Aeronautics and Space Administration (“NASA”) to build the Space Station Processing Facility (“SSPF”) at the Kennedy Space Center in Florida. Meisner Electric, Inc., performed electrical work on the project under a subcontract from Metric. After its work on the contract was completed, Meis-ner filed claims through Metric against the government, requesting an equitable adjustment in the contract price. The contracting officer denied the request, and Metric filed this action in the United States Court of Federal Claims.

The government argued that a July 1996 document executed by Meisner had the effect of releasing Metric and the government from all further liability on the contract, and that Metric’s action in the Court of Federal Claims therefore had to be dismissed. The court agreed and held that the July 1996 document constituted a full release of Metric and the government and therefore foreclosed any further claims on the contract by Metric on Meis-ner’s behalf. Metric appealed.

This case, like many contract disputes, turns on the interpretation of a document — the “July 1996 release” — that was poorly drafted and thus left the parties in a state of legitimate disagreement as to its meaning. While we sympathize with the trial court’s effort to make sense of a document that is difficult to interpret, we conclude that the document did not have the legal effect of releasing the government from any further claims asserted by Meisner through the prime contractor, Metric. We therefore reverse the summary judgment in favor of the government *580 and remand the case for farther proceedings before the Court of Federal Claims.

I

The pivotal question in this case is whether the July 1996 release that Meis-ner issued to Metric released Metric from any further liability on its subcontract with Meisner and thus extinguished Metric’s right to pursue a claim against the government on Meisner’s behalf. To resolve that question requires a review of the background of the release as well as an examination of the precise language used in the disputed document.

NASA entered into the contract with Metric to build the SSPF in early 1991. Shortly thereafter, Metric entered into a subcontract with Meisner to do the electrical work in the facility, for a price of $8,635,000.

Work under the electrical subcontract did not proceed smoothly. There were many changes to the contract, which increased the subcontract price to more than $11,500,000. When the work was completed, Meisner contended that a total of $106,519 remained to be paid on the subcontract, not counting requests for equitable adjustment. However, in part because of a dispute between Meisner and another subcontractor, Metric advised Meisner that it could not make any further payments to Meisner at that time. Metric added that it would be making settlement offers to Meisner on all the extra work orders and would adjust Meisner’s subcontract accordingly.

In March 1995, Metric forwarded a subcontract change order to Meisner that increased the revised amount of the subcontract and, according to Metric, resolved “all of Meisner’s extra work over invoices on this project” with the exception of one small invoice. Several months later, Meis-ner sought Metric’s aid in requesting an equitable adjustment from NASA relating to “costs and schedule impacts” throughout the performance of the subcontract.

On April 17, 1996, Metric and NASA reached a settlement on an equitable adjustment claim related to Meisner’s work on the contract for the SSPF substation 1 transformer. NASA agreed to pay $39,000 to resolve the claim, and Metric agreed to pay $36,000 of that amount to Meisner. Nine days later, Metric and Meisner entered into an agreement, termed the “Liquidation Agreement,” which referred to Meisner’s claims for additional compensation under its subcontract based on “actions and inactions by NASA.” The agreement sought to “establish the procedure for adjudication of [Meisner’s claims] and for establishing and releasing [Metric’s and Meisner’s] respective liabilities” as to those claims. Metric agreed to pay Meisner $74,751 that Metric had withheld based on the dispute between Meisner and another subcontractor. In addition, Metric agreed to present Meis-ner’s claims to NASA and assist in prosecuting those claims, subject to Metric being permitted to retain an agreed-upon portion of any recovery for itself, as general contractor.

On the same day that the Liquidation Agreement was signed, Meisner issued to Metric a form document entitled “Affidavit and Release” and subtitled “Partial Payment.” The document invoiced the payment of the $74,751 by Metric to Meisner and granted Metric a release. The release recited that Meisner warranted that all labor, materials, and other expenses related to the subcontract had been paid for, and that Meisner released Metric “and the owners of the project from all claims whatsoever arising out of or relating to the subcontract or purchase order to the extent of payments actually received.” The *581 release also waived any lien rights with respect to the project “to the extent of payments actually received” and agreed to indemnify Metric against “any claim or lien asserted through or under [Meisner] with respect to the project.”

In May of 1996, NASA issued a formal change order to Metric in the amount of $39,000 for the substation 1 transformer claim settlement. Consistent with its agreement with Meisner, Metric then passed on $36,000 of that amount to Meis-ner. In connection with the receipt of that sum, Meisner on July 15, 1996, issued another document similar to the April 1996 release. The July release was identical to the April release in several respects: it was entitled “Affidavit and Release” and subtitled “Partial Payment”; it contained language releasing Metric and the project owner (the government) from “all claims whatsoever arising out of or relating to the subcontract or purchase order to the extent of payments actually received”; it waived any lien rights with respect to the project “to the extent of payments actually received”; and it promised to indemnify Metric against “any claim or lien asserted through or under [Meisner] with respect to the project.”

A year and a half later, Metric submitted a request for equitable adjustment to NASA on Meisner’s behalf, seeking compensation for a variety of direct costs and disruptions to Meisner’s performance. The contracting officer denied the request in most respects. Metric then converted the request to a claim, and when the claim was denied Metric filed its complaint as a “pass-through” suit in the Court of Federal Claims. In a pass-through suit, a prime contractor that is liable for damages sustained by its subcontractor may bring claims against the government on behalf of the subcontractor. See E.R. Mitchell Constr. Co. v. Danzig, 175 F.3d 1369, 1370 (Fed.Cir.1999). A pass-through suit is necessary because subcontractors in a government contract are not in privity with the government and may not sue the government directly.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Yul Lim Construction Co., Ltd.
Armed Services Board of Contract Appeals, 2025
Logistics and Rental Car SARL
Armed Services Board of Contract Appeals, 2024
Odyssey International, Inc.
Armed Services Board of Contract Appeals, 2021
JAAAT Technical Services, LLC
Armed Services Board of Contract Appeals, 2021
Cubic Defense Applications, Inc.
Armed Services Board of Contract Appeals, 2018
Hanover Insurance Company (The) v. United States
134 Fed. Cl. 51 (Federal Claims, 2017)
Korte-Fusco Joint Venture
Armed Services Board of Contract Appeals, 2015
United States v. Travelers Casualty & Surety Co. of America
55 F. Supp. 3d 852 (N.D. West Virginia, 2014)
Toxco Inc. v. Chu
District of Columbia, 2010
Bell BCI Co. v. United States
91 Fed. Cl. 664 (Federal Claims, 2010)
Bell Bci Co. v. United States
570 F.3d 1337 (Federal Circuit, 2009)
International Technology Corp. v. Winter
523 F.3d 1341 (Federal Circuit, 2008)
AAB Joint Venture v. United States
68 Fed. Cl. 363 (Federal Claims, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
314 F.3d 578, 60 Fed. R. Serv. 260, 2002 U.S. App. LEXIS 26093, 2002 WL 31828862, Counsel Stack Legal Research, https://law.counselstack.com/opinion/metric-constructors-v-united-states-cafc-2002.