Toxco Inc. v. Chu

CourtDistrict Court, District of Columbia
DecidedJuly 20, 2010
DocketCivil Action No. 2009-1925
StatusPublished

This text of Toxco Inc. v. Chu (Toxco Inc. v. Chu) is published on Counsel Stack Legal Research, covering District Court, District of Columbia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Toxco Inc. v. Chu, (D.D.C. 2010).

Opinion

UNITED STATES DISTRICT COURT FOR THE DISTRICT OF COLUMBIA

TOXCO INC., : : Plaintiff, : Civil Action No.: 09-1925 : v. : Re Document Nos.: 3, 7, 15 : STEVEN CHU, : in his official capacity as Secretary of : the U.S. Department of Energy, : : Defendant. :

MEMORANDUM OPINION

DENYING THE DEFENDANT’S MOTION TO DISMISS FOR FAILURE TO STATE A CLAIM FOR WHICH RELIEF CAN BE GRANTED; DENYING THE PLAINTIFF’S MOTION FOR A PRELIMINARY INJUNCTION; DENYING AS MOOT THE PLAINTIFF’S MOTION FOR LEAVE TO FILE SUPPLEMENTAL INFORMATION

I. INTRODUCTION

The plaintiff, Toxco Inc., operates a waste disposal facility in Tennessee. It has brought

this action pursuant to the Administrative Procedure Act (“APA”), 5 U.S.C. §§ 553 et seq., and

the due process clause of the Fifth Amendment, challenging the Department of Energy’s

(“DOE”) withdrawal of its consent to a subcontract entered into by the plaintiff. This matter is

now before the court on the plaintiff’s motion for a preliminary injunction and the defendant’s

motion to dismiss for failure to state a claim. The plaintiff seeks a preliminary injunction

requiring the DOE to reinstate its consent to the plaintiff serving as a subcontractor on a DOE

environmental clean-up project in Niskayuna, New York. The defendant opposes the entry of a

preliminary injunction and has filed a Rule 12(b)(6) motion to dismiss. Because the plaintiff has

failed to demonstrate that it will suffer irreparable harm absent injunctive relief and has not

shown a likelihood of success on the merits, the court denies the plaintiff’s motion for a preliminary injunction. Because, however, the court cannot conclude at this stage of the

litigation that the plaintiff has no entitlement to relief under the APA or the due process clause of

the Fifth Amendment, the court denies the defendant’s motion to dismiss.1

II. BACKGROUND

A. Factual Background

Until 2000, the DOE operated a research facility known as the Separation Process

Research Unit (“SPRU”) in Niskayuna, New York, which was used for research on the

separation of atomic isotopes. Pl.’s Mot. for a Prelim. Inj. (“Pl.’s Mot.”) at 3. Although the

SPRU facility has been largely unused since 2000, the research performed there resulted in

radioactive contamination of the facilities and the surrounding soil. Id. In October 2004, the

DOE engaged Accelerated Remediation Company (“ARC”) to return the site to a usable

condition. Id.; Def.’s Consolidated Opp’n to Pl.’s Prelim. Inj. Mot. & Mot. to Dismiss for

Failure to State a Claim (“Def.’s Mot.”) at 3. The work performed by ARC was to include the

removal of contaminated soils, building debris and other waste materials containing low levels of

radioactive contamination and disposing of these materials at qualified locations. Pl.’s Mot. at 3.

In September 2007, the DOE issued a task order to ARC for the rehabilitation of the

lower level railbed area and the lower level parking lot of the SPRU facility (“the SP-15 Task

1 The plaintiff has also filed a motion for leave to file supplemental information in opposition to the defendant’s motion to dismiss. Because, as discussed below, the court denies the defendant’s motion to dismiss without consideration of this supplemental information, the court denies as moot the plaintiff’s motion for leave to file. See Nat’l Credit Counseling Servs., Inc. v. United States, 2008 WL 5413163, at *2 (D.D.C. Oct. 15, 2008) (denying without prejudice the plaintiff’s motion for partial summary judgment and, consequently, denying as moot the plaintiff’s motion for leave to file a supplemental memorandum of law in support of its motion for summary judgment); see also Banks v. Office of Senate Sergeant-at-Arms, 233 F.R.D. 1, 11 (D.D.C. 2005) (denying as moot the plaintiff’s motion for leave to file a supplemental filing because the court had already ruled on the motion to which the supplemental filing was related).

2 Order”). Def.’s Mot. at 3. The SP-15 Task Order made ARC responsible for disposing of any

waste generated by the remediation project and authorized ARC to use “existing contractual

instruments between the Federal Government and waste disposal facilities . . . when disposing of

waste unless [ARC could] obtain more favorable cost arrangements.” Id., Decl. of Marilyn Long

(“Long Decl.”), Ex. 1 at C-12.

In February 2009, the American Recovery and Reinvestment Act provided $37 million of

funding to DOE to accelerate the rehabilitation of the SPRU site. Pl.’s Mot. at 4. As a result, in

May 2009, ARC issued a request for subcontractors to submit proposals for the disposal of waste

generated through work on the SP-15 Task Order containing low levels of radioactive

contamination. Id. The plaintiff submitted a proposal in June 2009, and ARC determined that

the plaintiff was the lowest-cost, qualifying bidder. Id.

The federal acquisition regulations in force at the time required agency consent for

certain subcontracts entered into by a contractor without an approved purchasing system. Def.’s

Mot. at 12-13. Furthermore, DOE Order 435.1 required a contractor to obtain an exemption

from the DOE before disposing of radioactive waste at a non-DOE facility. Id. at 13. Both

provisions applied to the plaintiff’s proposed subcontract with ARC. Id. at 12-13. Accordingly,

in July 2009, ARC requested DOE’s consent to a subcontract between itself and the plaintiff.

Pl.’s Mot. at 5-6.

On August 11, 2009, the DOE provided its formal consent to the subcontract in a letter

from Marilyn Long, a DOE contracting officer. See id., Aff. of David Eaker (“Eaker Aff.”), Ex.

9. The same day, the plaintiff and ARC executed a subcontract for the disposal of low-level

radioactive material pursuant to the SP-15 Task Order. See generally Eaker Aff., Ex. 10 (“Toxco

Purchase Order”). The subcontract expressly incorporated several contractual provisions set

3 forth in federal acquisition regulations, including Federal Acquisition Regulation (“FAR”) §

52.249-2. See id. at 3. That regulation contained a contractual provision entitled “Termination

for Convenience of the Government,” which provided, in relevant part, that “[t]he Government

may terminate performance of work under this contract in whole or, from time to time, in part if

the Contracting Officer determines that a termination is in the Government’s interest.” 48 C.F.R.

§ 52.249-2(a). The provision further specified that upon the delivery of the government’s notice

of termination to the prime contractor, the prime contractor shall, “[w]ith approval or ratification

to the extent required by the Contracting Officer, settle all outstanding liabilities and termination

settlement proposals arising from the termination of subcontracts; the approval or ratification

will be final for purposes of this clause.” Id. § 52.249-2(b)(5).

After executing the subcontract, the plaintiff began to undertake its processing and

disposal duties as set forth in the agreement. Pl.’s Mot. at 6. Yet on August 19, 2009, eight days

after providing written consent to the plaintiff’s subcontract, the DOE issued a notice to ARC

that it had rescinded its consent to the plaintiff’s subcontract. Eaker Aff., Ex. 13 at 1. The notice

contained no explanation for the DOE’s withdrawal of consent. See id. The withdrawal forced

ARC to terminate its subcontract with the plaintiff. Pl.’s Mot. at 6-7.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Conley v. Gibson
355 U.S. 41 (Supreme Court, 1957)
Greene v. McElroy
360 U.S. 474 (Supreme Court, 1959)
Abbott Laboratories v. Gardner
387 U.S. 136 (Supreme Court, 1967)
Barlow v. Collins
397 U.S. 159 (Supreme Court, 1970)
Citizens to Preserve Overton Park, Inc. v. Volpe
401 U.S. 402 (Supreme Court, 1971)
Board of Regents of State Colleges v. Roth
408 U.S. 564 (Supreme Court, 1972)
Weinberger v. Romero-Barcelo
456 U.S. 305 (Supreme Court, 1982)
City of Los Angeles v. Lyons
461 U.S. 95 (Supreme Court, 1983)
Heckler v. Chaney
470 U.S. 821 (Supreme Court, 1985)
Amoco Production Co. v. Village of Gambell
480 U.S. 531 (Supreme Court, 1987)
Brock v. Roadway Express, Inc.
481 U.S. 252 (Supreme Court, 1987)
Federal Deposit Insurance v. Mallen
486 U.S. 230 (Supreme Court, 1988)
Webster v. Doe
486 U.S. 592 (Supreme Court, 1988)
Bowen v. Massachusetts
487 U.S. 879 (Supreme Court, 1988)
Kentucky Department of Corrections v. Thompson
490 U.S. 454 (Supreme Court, 1989)
Lincoln v. Vigil
508 U.S. 182 (Supreme Court, 1993)
Lujan v. G & G Fire Sprinklers, Inc.
532 U.S. 189 (Supreme Court, 2001)
Swierkiewicz v. Sorema N. A.
534 U.S. 506 (Supreme Court, 2002)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Munaf v. Geren
553 U.S. 674 (Supreme Court, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
Toxco Inc. v. Chu, Counsel Stack Legal Research, https://law.counselstack.com/opinion/toxco-inc-v-chu-dcd-2010.