Toxco Inc. v. Chu

724 F. Supp. 2d 16, 2010 U.S. Dist. LEXIS 72567, 2010 WL 2814323
District Court, District of Columbia·Decided July 20, 2010·No. Civil Action No.: 09-1925·Published·Cited by 20 cases

Opinion

MEMORANDUM OPINION

Denying the Defendant’s Motion to Dismiss for Failure to State a Claim for Which Relief Can be Granted; Denying the Plaintiff’s Motion for a Preliminary Injunction; Denying as Moot the Plaintiff’s Motion for Leave to File Supplemental Information

RICARDO M. URBINA, District Judge.

I. INTRODUCTION

The plaintiff, Toxco Inc., operates a waste disposal facility in Tennessee. It has brought this action pursuant to the Administrative Procedure Act (“APA”), 5 U.S.C. §§ 553 et seq., and the due process clause of the Fifth Amendment, challenging the Department of Energy’s (“DOE”) withdrawal of its consent to a subcontract entered into by the plaintiff. This matter is now before the court on the plaintiffs motion for a preliminary injunction and the defendant’s motion to dismiss for failure to state a claim. The plaintiff seeks a preliminary injunction requiring the DOE to reinstate its consent to the plaintiff serving as a subcontractor on a DOE environmental clean-up project in Niskayuna, New York. The defendant opposes the entry of a preliminary injunction and has filed a Rule 12(b)(6) motion to dismiss. Because the plaintiff has failed to demonstrate that it will suffer irreparable harm *19 absent injunctive relief and has not shown a likelihood of success on the merits, the court denies the plaintiffs motion for a preliminary injunction. Because, however, the court cannot conclude at this stage of the litigation that the plaintiff has no entitlement to relief under the APA or the due process clause of the Fifth Amendment, the court denies the defendant’s motion to dismiss. 1

II. BACKGROUND

A. Factual Background

Until 2000, the DOE operated a research facility known as the Separation Process Research Unit (“SPRU”) in Niskayuna, New York, which was used for research on the separation of atomic isotopes. Pl.’s Mot. for a Prelim. Inj. (“Pl.’s Mot.”) at 3. Although the SPRU facility has been largely unused since 2000, the research performed there resulted in radioactive contamination of the facilities and the surrounding soil. Id. In October 2004, the DOE engaged Accelerated Remediation Company (“ARC”) to return the site to a usable condition. Id.; Def.’s Consolidated Opp’n to Pl.’s Prelim. Inj. Mot. & Mot. to Dismiss for Failure to State a Claim (“Def.’s Mot.”) at 3. The work performed by ARC was to include the removal of contaminated soils, building debris and other waste materials containing low levels of radioactive contamination and disposing of these materials at qualified locations. Pl.’s Mot. at 3.

In September 2007, the DOE issued a task order to ARC for the rehabilitation of the lower level railbed area and the lower level parking lot of the SPRU facility (“the SP-15 Task Order”). Def.’s Mot. at 3. The SP-15 Task Order made ARC responsible for disposing of any waste generated by the remediation project and authorized ARC to use “existing contractual instruments between the Federal Government and waste disposal facilities ... when disposing of waste unless [ARC could] obtain more favorable cost arrangements.” Id., Decl. of Marilyn Long (“Long Decl.”), Ex. 1 at C-12.

In February 2009, the American Recovery and Reinvestment Act provided $37 million of funding to DOE to accelerate the rehabilitation of the SPRU site. Pl.’s Mot. at 4. As a result, in May 2009, ARC issued a request for subcontractors to submit proposals for the disposal of waste generated through work on the SP-15 Task Order containing low levels of radioactive contamination. Id. The plaintiff submitted a proposal in June 2009, and ARC determined that the plaintiff was the lowest-cost, qualifying bidder. Id.

The federal acquisition regulations in force at the time required agency consent for certain subcontracts entered into by a contractor without an approved purchasing system. Def.’s Mot. at 12-13. Furthermore, DOE Order 435.1 required a contractor to obtain an exemption from the DOE before disposing of radioactive waste *20 at a non-DOE facility. Id. at 13. Both provisions applied to the plaintiffs proposed subcontract with ARC. Id. at 12-13. Accordingly, in July 2009, ARC requested DOE’s consent to a subcontract between itself and the plaintiff. Pl.’s Mot. at 5-6.

On August 11, 2009, the DOE provided its formal consent to the subcontract in a letter from Marilyn Long, a DOE contracting officer. See id., Aff. of David Eaker (“Eaker Aff.”), Ex. 9. The same day, the plaintiff and ARC executed a subcontract for the disposal of low-level radioactive material pursuant to the SP-15 Task Order. See generally Eaker Aff., Ex. 10 (“Toxco Purchase Order”). The subcontract expressly incorporated several contractual provisions set forth in federal acquisition regulations, including Federal Acquisition Regulation (“FAR”) § 52.249-2. See id. at 3. That regulation contained a contractual provision entitled “Termination for Convenience of the Government,” which provided, in relevant part, that “[t]he Government may terminate performance of work under this contract in whole or, from time to time, in part if the Contracting Officer determines that a termination is in the Government’s interest.” 48 C.F.R. § 52.249-2(a). The provision further specified that upon the delivery of the government’s notice of termination to the prime contractor, the prime contractor shall, “[w]ith approval or ratification to the extent required by the Contracting Officer, settle all outstanding liabilities and termination settlement proposals arising from the termination of subcontracts; the approval or ratification will be final for purposes of this clause.” Id. § 52.249-2(b)(5).

After executing the subcontract, the plaintiff began to undertake its processing and disposal duties as set forth in the agreement. Pl.’s Mot. at 6. Yet on August 19, 2009, eight days after providing written consent to the plaintiffs subcontract, the DOE issued a notice to ARC that it had rescinded its consent to the plaintiffs subcontract. Eaker Aff., Ex. 13 at 1. The notice contained no explanation for the DOE’s withdrawal of consent. See id. The withdrawal forced ARC to terminate its subcontract with the plaintiff. Pl.’s Mot. at 6-7.

B. Procedural History

The plaintiff commenced this action in October 2009, asserting that the DOE’s withdrawal of consent constituted an arbitrary and capricious agency action in violation of the APA, and deprived it of property without due process of law in violation of the Fifth Amendment. See generally Compl. The plaintiff also moved for a preliminary injunction requiring the DOE to rescind its withdrawal and reinstate its consent to the plaintiffs subcontract with ARC. See generally Pl.’s Mot.

Free access — add to your briefcase to read the full text and ask questions with AI

Toxco Inc. v. Chu, 724 F. Supp. 2d 16, 2010 U.S. Dist. LEXIS 72567, 2010 WL 2814323 (D.D.C. 2010).

724 F. Supp. 2d 16 (Toxco Inc. v. Chu) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

George v. George Washington University
District of Columbia, 2022
Hall v. Barr
District of Columbia, 2020
Yankton Sioux Tribe v. Kempthorne
District of Columbia, 2019
Benoit v. District of Columbia
District of Columbia, 2018
Beacon Assocs., Inc. v. Apprio, Inc.
308 F. Supp. 3d 277 (D.C. Circuit, 2018)
Beacon Associates, Inc. v. Apprio, Inc.
District of Columbia, 2018
Converdyn v. Moniz
68 F. Supp. 3d 34 (District of Columbia, 2014)
TOXCO, INC. v. Chu
801 F. Supp. 2d 1 (District of Columbia, 2011)
Sterling Commercial Credit-Michigan, LLC v. Phoenix Industries I, LLC
762 F. Supp. 2d 8 (District of Columbia, 2011)
Allina Health Services v. Sebelius
District of Columbia, 2010