Korte-Fusco Joint Venture

CourtArmed Services Board of Contract Appeals
DecidedNovember 5, 2015
DocketASBCA No. 59767
StatusPublished

This text of Korte-Fusco Joint Venture (Korte-Fusco Joint Venture) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Korte-Fusco Joint Venture, (asbca 2015).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) Korte-Fusco Joint Venture ) ASBCA No. 59767 ) Under Contract No. W912QR-11-C-0037 )

APPEARANCE FOR THE APPELLANT: Kirk J. McCormick, Esq. Hinckley, Allen & Snyder LLP Boston, MA

APPEARANCES FOR THE GOVERNMENT: Thomas H. Gourlay, Jr., Esq. Engineer Chief Trial Attorney Jennifer M. Payton, Esq. Engineer Trial Attorney U.S. Army Engineer District, Louisville

OPINION BY ADMINISTRATIVE JUDGE O'CONNELL ON THE GOVERNMENT'S MOTION FOR SUMMARY JUDGMENT

This appeal involves a delay claim on a U.S. Army Corps of Engineers (Corps) construction project. The Corps has filed a motion for summary judgment in which it contends that a bilateral modification executed after the alleged delays shields the government from any liability. Because this modification does not clearly release the claim at issue, the government is not entitled to judgment as a matter of law and we deny the motion.

STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION

The following facts are undisputed, unless otherwise noted. 1

1. On 31 August 2011, a contracting officer with the Louisville District of the Corps executed a contract with appellant, Korte-Fusco Joint Venture (KFJV), for the design and construction of a project that included a new 400 member Armed Forces training building and two segmental retaining walls (R4, tab 3 ). Due to a bid protest, the contracting officer waited until 29 November 2011 to issue the notice to proceed (R4, tab 4; B. Korte aff. ii 8).

1 Both parties have submitted a statement of undisputed material facts. While appellant has submitted a detailed response to the government's statement, the government has not responded to appellant's submission. Under Board Rule 7(c)(2), the Board may accept as true a fact properly proposed and supported by one party unless the other party properly responds and establishes that it is in dispute. 2. On 16 May 2012, KFJV entered into a subcontract with NCI-CT, Inc. (NCI), for work that included construction of the retaining walls (R4, tab 9). According to appellant, "NCI is prosecuting this Appeal in the name of KFJV with the consent, cooperation, and authorization of KF JV" ( app. br. at 1 n. l ).

3. NCI first submitted the retaining walls as a construction submittal to KFJV on 31May2012 (R4, tab 6). The government provides a long history of the approval process in its statement of undisputed facts but for present purposes it suffices to say that after a series of disapprovals and re-submittals, the Corps did not approve the retaining walls until more than 13 months after the initial submittal, on 9 July 2013 (R4, tab 64).

4. On 21 August 2013, the parties attended a "Red Zone" meeting, a meeting contemplated by the contract to occur 60 days before the beneficial occupancy date to discuss the closeout process (R4, tab 3 at GR4-277, ~ 1.52). The minutes of this meeting quote a Corps employee as stating that "a pending weather mod and time extension will be executed" (B. Korte aff., ex. 4 at 2 of 8, ~ 19).

5. Attached to the Red Zone meeting minutes is a "Change Request Register." This register lists 17 change requests, including request no. 5, which is also identified as "Ref No R00004" and is listed as a negotiated change of 72 days. Under the heading "Necessity for Change" it states: "l. Contractor is due an increase in the performance time due to bid protest of over 3 months delaying the contract start, and several adverse weather days during the construction period." (B. Korte aff., ex. 4)

6. On 13 September 2013, KFJV and the contracting officer executed bilateral Modification No. A00004, which extended the time for contract completion by 72 days but left the contract price unchanged (R4, tab 67). In block 14, Description of Amendment/Modification. the modification states as follows:

Reference No: R00004 Case 005 - Time Extension

(Id. at 1) In a continuation of block 14, the second page of the modification contains the following relevant language:

A. SCOPE OF WORK

Case 005 -Time Extension

Performance time is increased 72 calendar days to 702 calendar days. Time extension includes all delays incurred by the contract up to the date of issuance of this modification.

2 D. CHANGE IN CONTRACT PRICE

Total contract price is unchanged.

E. CHANGE IN CONTRACT TIME

... [I]t is understood and agreed that the contract performance time is hereby extended 72 calendar days to and including 8 November 2013, at no additional cost to the Government.

F. CLOSING STATEMENT

It is understood and agreed that pursuant to the above, the contract time is extended the number of calendar days stated, and the contract price is unchanged as indicated above, which reflects all credits due to the Government and all debits due the Contractor.

It is further understood and agreed that this adjustment constitutes compensation in full on behalf of the Contractor and its Subcontractors and Suppliers for all costs and markups directly or indirectly attributable for the change ordered, for all delays related thereto, for all extended overhead costs, and for performance of the change within the time frame stated.

7. On 12 May 2014, KFJV submitted the certified claim at issue in this appeal (R4, tab 73). KFJV sought $1,971,209.19, including $1,753,424.96 for NCI, and a 389-day time extension as a result of Corps delays in approving the retaining wall submittals (id. at GR4-2533).

8. Prior to execution of Modification No. A00004, NCI informed KFJV on three occasions that it wanted additional money (R4, tabs 16, 26, 66). KFJV agrees that one of these documents, an email from NCI dated 27 November 2012 (R4, tab 26), relates to the retaining wall approval process but points out that this email ended with NCI stating that it could not "calculate the magnitude of the delay value" until it had a confirmed start date and experienced the severity of the winter. KFJV disputes any suggestion that the issues raised in the emails contained at Rule 4, tabs 16 and 66, have any relationship to approval of the submittals (app. statement of genuine issues~~ 14, 62).

3 DECISION

Standard ofReview for Summary Judgment Motions

Pursuant to Board Rule 7(c)(2), the Board looks to Rule 56 of the Federal Rules of Civil Procedure for guidance in deciding motions for summary judgment. Under FED. R. C1v. P. 56(a), the Board may grant summary judgment ifthere is no genuine dispute as to any material fact. In considering such a motion, the evidence of the nonmovant is to be believed, and all justifiable inferences are to be drawn in its favor. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 255 (1986).

Standards Governing Accord and Satisfaction and Releases

Accord and satisfaction occur "when some performance different from that which was claimed as due is rendered and such substituted performance is accepted by the claimant as full satisfaction of his claim." Bell BC! Co. v. United States, 570 F.3d 1337, 1340-41 (Fed. Cir. 2009) (quoting Cmty. Heating & Plumbing Co. v. Kelso, 987 F.2d 1575, 1581 (Fed. Cir. 1993)).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Korte-Fusco Joint Venture, Counsel Stack Legal Research, https://law.counselstack.com/opinion/korte-fusco-joint-venture-asbca-2015.