AAB Joint Venture v. United States

68 Fed. Cl. 363, 2005 U.S. Claims LEXIS 322, 2005 WL 2864701
United States Court of Federal Claims·Decided November 1, 2005·No. No. 04-1792 C·Published·Cited by 4 cases

Opinion

OPINION

DAMICH, Chief Judge.

This case is before the Court on Defendant’s Motion to Dismiss for Lack of Subject Matter Jurisdiction pursuant to Rule 12(b)(1) of the Rules of the United States Court of Federal Claims (“RCFC”). Plaintiff seeks to recover increased costs on behalf of its two subcontractors, Rolider, Ltd. (“Rolider”) and Biri Barashi, Land Works, Development Infrastructure and Road, Ltd. (“Barashi”), under a construction contract with the U.S. Army Engineer Corps-Europe. In its motion, Defendant requests the Court to dismiss for lack of jurisdiction Plaintiffs claim on behalf of Barashi because it was not certified and presented to the contracting officer [364] for final decision as required by the Contract Disputes Act for claims exceeding $100,000. See 41 U.S.C. § 605(e)(1). Plaintiff asserts that the Barashi claim arises from the same set of operative facts as its certified claim to the contracting officer on behalf of Rolider on December 17, 2003, and hence does not constitute a new claim that needs to be separately certified. For the reasons set forth below, Defendant’s Motion to Dismiss is hereby GRANTED.

I. Background

AAB entered into a contract with the U.S. Army Engineer Corps-Europe (“USACE”) on June 5, 2001, to design and construct a storage and logistics base in Elad, Israel for use by the Israeli Defense Force. Compl. ¶4, 6. AAB was to complete the project in three years, and was to receive $124,089,176 in compensation. Id. ¶ 6. Barashi and Rolider subcontracted with AAB to perform the earthwork operations. Id. ¶ 7.

The contract provided technical directions for compaction of controlled fill on subsurface areas and road. Id. ¶ 8. In particular, the contract specified that a maximum stone size of 15 cm (approximately 6 inches) should be used, and that fill in the top 1.5 meters should be laid in layers of 20 cm compacted to 98% of the maximum density according to the modified American Association of State Highway and Transportation Officials (“A.A.S.H.T.O.”) compaction test. Id. ¶ 8-9. Barashi and Rolider based their bids on the assumption that they would be able to use 6 inch stone in the top 1.5 meters of the sub-grade. Id. ¶ 10. The modified A.AS.H.T.O. compaction test required for the top 1.5 meters, however, can only be performed with a stone size of 3 inches or less. Id. ¶ 11. Therefore, the contract specifications were defective. Id. ¶ 12.

On June 25, 2002, AAB submitted RFI No. DC-0011 to the contracting officer, proposing that 6 inch stone be used in the upper 1.5 to 1.7 meters in three areas: (1) open fill area in sector 78; (2) under logistics area building and nontrack vehicle parking areas; and (c) under sheds 8 to 13 in sector 123 and associated nontraek vehicle parking/loading areas. Id. ¶ 13. AAB also proposed that the minimum required density would be increased from 98% to 100% based on nuclear density test results. Id. ¶ 13. For all other fill areas, 3 inch stone would be used in the upper 1.5 to 1.7 meters. Id. ¶ 13. USACE accepted AAB’s proposal on July 30, 2002, and Rolider and Barashi performed earthwork operations in accordance with RFI No. DC-0011. Id. ¶ 14-15.

On December 17, 2003, AAB submitted a certified claim to the contracting officer for an equitable adjustment of $916,895 (which it later revised to $910,873) to cover the additional costs incurred by Rolider as a result of the requirement to use 3 inch fill, rather than the 6 inch fill specified in the contract. Id. ¶ 17. The contracting officer failed to issue a final decision within 60 days of receipt of the certified claim. Id. ¶ 19.

In its December 21, 2004, complaint, AAB requested compensation in the amount of $1,897,320, pursuant to FAR 52.243-4 (Changes) for the increased costs incurred by its subcontractors as a result of the defective specifications and resulting directive by USACE in response to RFI No. DC-0011. Id. ¶23. In addition to the previously requested $910,873 on behalf of Rolider, AAB also requested $986,447 to compensate subcontractor Barashi for increased costs to place and compact 3 inch fill in the upper 1.5 meters in all areas except the three designated areas. Id. ¶ 21. It is this claim on behalf of Barashi that is the subject of Defendant’s motion, as this claim was never submitted to the contracting officer.

II. Standard of Review

In considering Defendant’s Motion to Dismiss pursuant to RCFC 12(b)(1), the Court must accept as true all of Plaintiffs well-pleaded facts alleged in the complaint, and draw all reasonable inferences in the Plaintiffs favor. Godwin v. United States, 338 F.3d 1374, 1377 (Fed.Cir.2003); Boyle v. United States, 200 F.3d 1369, 1372 (Fed.Cir.2000); Perez v. United States, 156 F.3d 1366, 1370 (Fed.Cir.1998). Plaintiff, however, bears the burden of establishing subject matter jurisdiction by a preponderance of the evidence. Taylor v. United States, 303 F.3d 1357, 1359 (Fed.Cir.2002); Reynolds v. Army [365] & Air Force Exch. Serv., 846 F.2d 746, 748 (Fed.Cir.1988).

The jurisdiction of the Court of Federal Claims is “prescribed by the metes and bounds of the United States’ consent to be sued in its waiver of immunity.” RHI Holdings, Inc. v. United States, 142 F.3d 1459, 1461 (Fed.Cir.1998) (citing United States v. Sherwood, 312 U.S. 584, 586, 61 S.Ct. 767, 85 L.Ed. 1058 (1941)). Waiver of sovereign immunity “cannot be implied but must be unequivocally expressed.” Fed. Nat’l Mortgage Assoc. v. United States, 379 F.3d 1303, 1311 (Fed.Cir.2004) (citing United States v. King, 395 U.S. 1, 4, 89 S.Ct. 1501, 23 L.Ed.2d 52 (1969)). The Tucker Act provides:

The Court of Federal Claims shall have jurisdiction to render judgment upon any claim by or against, or dispute with, a contractor arising under section 10(a)(1) of the Contract Disputes Act of 1978, including a dispute concerning termination of a contract, rights in tangible or intangible property, compliance with cost accounting standards, and other nonmonetary disputes on which a decision of the contracting officer has been issued under section 6 of that Act.

Free access — add to your briefcase to read the full text and ask questions with AI

AAB Joint Venture v. United States, 68 Fed. Cl. 363, 2005 U.S. Claims LEXIS 322, 2005 WL 2864701 (uscfc 2005).

68 Fed. Cl. 363 (AAB Joint Venture v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

AAB Joint Venture v. United States
75 Fed. Cl. 414 (Federal Claims, 2007)
Lockheed Martin Corp. v. United States
70 Fed. Cl. 745 (Federal Claims, 2006)