Willamette Crushing Co. v. State

932 P.2d 1350, 188 Ariz. 79, 235 Ariz. Adv. Rep. 3, 1997 Ariz. App. LEXIS 9
CourtCourt of Appeals of Arizona
DecidedJanuary 28, 1997
Docket1 CA-CV 95-0491
StatusPublished
Cited by3 cases

This text of 932 P.2d 1350 (Willamette Crushing Co. v. State) is published on Counsel Stack Legal Research, covering Court of Appeals of Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Willamette Crushing Co. v. State, 932 P.2d 1350, 188 Ariz. 79, 235 Ariz. Adv. Rep. 3, 1997 Ariz. App. LEXIS 9 (Ark. Ct. App. 1997).

Opinion

OPINION

NOYES, Acting Presiding Judge.

Appellant Wildish made the low bid on an Arizona highway construction project which was to be completed within 360 working days and was to be staged according to a specified Traffic Control Pattern (“TCP”). After being awarded the contract, Wildish decided that it could not meet the due date using the State’s TCP. Wildish asked for more time and the State refused. Wildish asked to use its own TCP and the State agreed. Using its own TCP, Wildish met the due date — with a cost overrun it now seeks to recover from the State and the engineers who drafted the State’s TCP.

Wildish argues that the contract due date was a warranty by the State that a contractor could meet the due date using the State’s TCP. Wildish also argues that the State’s TCP was defective because no contractor could use it and meet the due date. The defendants argue that the State’s TCP was not defective and that any due-date warranty was by Wildish because a contractor’s bid is a warranty by the contractor that it can meet the due date if awarded the contract. The trial court granted summary judgment to defendants and we affirm. To do otherwise on the undisputed material facts presented would erroneously suggest that the law might imply a warranty of profitability in public contracts.

I.

In April 1990 the Arizona Department of Transportation (“the State”) invited bids on a project to expand “the Broadway Curve,” a three-mile section of Interstate 10 in the Phoenix-Tempe area. The contract contained a TCP which specified the stages of construction and was intended to permit maximum traffic flow while ensuring the safety of motorists and construction workers. The contract specified completion of the project in 360 working days. Section 108.08 of the contract provided that “the contractor’s plea that insufficient time was specified is not a valid reason for extension of time.”

Wildish had nine and a half weeks to study the bid package. After one of its employees spent four weeks preparing its bid, Wildish submitted a bid of $22.1 million. This bid was $2.6 to $3.1 million lower than the State’s cost estimate ($24.7 million) and the bids of all Arizona-based competitors: FNF Construction, Inc. ($24.8 million), The Tanner Companies ($25 million), and Pulice Construction ($25.2 million). There were also bids from two out-of-state companies: one was $15,000 higher than the Wildish bid and the other was $3.8 million higher.

After being awarded the contract, Wildish performed a critical path method (“CPM”) analysis, which organizes and schedules a complex project such as this one. A CPM analysis is time-consuming and expensive and is not normally done prior to bidding on a contract. Based on its CPM analysis, *81 Wildish calculated it would need 542 working days to complete the project using the State’s TCP. Wildish asked for an extension of the due date and the State refused, but the State did approve a TCP devised by Wildish.

Using its own TCP, Wildish completed the project in 357 days, but at a cost which exceeded its bid by $2.9 million. Wildish blamed the cost overrun on inefficiencies inherent in the TCP it had to devisé in order to meet the due date. Wildish filed a claim with the State for the cost overrun and the claim was rejected. Wildish filed this lawsuit and the defendants were granted summary judgment. Wildish appealed. We have jurisdiction pursuant to A.R.S. sections 12-2101(B) (1994) and 12-120.21(A)(1) (1992).

II.

Summary judgment is appropriate when there are no genuine issues of material fact. Orme School v. Reeves, 166 Ariz. 301, 310, 802 P.2d 1000, 1009 (1990). If the undisputed facts are such that no reasonable jury could grant relief, summary judgment is warranted. See id. Contract interpretation is a question of law which we review de novo. Arizona Biltmore Estates Assoc. v. Tezak, 177 Ariz. 447, 448, 868 P.2d 1030, 1031 (App. 1993).

This appeal involves a public contract and issues on which there are no Arizona cases. For guidance, we look to the federal court of claims and the federal boards of contract appeals, for those specialty courts have expertise with public contracts. New Pueblo Constructors, Inc. v. State, 144 Ariz. 95, 101, 696 P.2d 185, 191 (1985).

III.

The contract entitles Wildish to a price adjustment if the State expressly or impliedly ordered modifications which “significantly changed the character of the work.” Wildish argues that the State impliedly ordered modification of the TCP when it refused to extend the due date to enable Wildish to complete the contract using the State’s TCP.

Change provisions compensate contractors for burdens not contemplated by the contract. Wunderlich Contracting Co. v. United States, 173 Ct.Cl. 180, 351 F.2d 956, 965-66 (1965). To qualify for adjustment under a change provision, a contractor must prove, first, that “any increased costs arose from conditions differing materially from those indicated in the bid documents;” and, second, that the changes “were reasonably unforeseeable in the light of all the information available to the contractor.” Sterling Millwrights, Inc. v. United States, 26 Cl.Ct. 49, 72 (1992).

Wildish claims that the State’s TCP had a hidden defect because only after being awarded the contract and performing its CPM did Wildish discover that it could not meet the due date using the State’s TCP. Wildish’s opening brief advises that, “Wildish calculated its bid assuming that the State’s [TCP sequences] were appropriate for the job and, if followed, would allow the work to be completed within the time allowed.” We conclude that the contractor bears the risk of basing a bid on such assumptions.

Wildish relies on a line of eases beginning with United States v. Spearin, 248 U.S. 132, 136, 39 S.Ct. 59, 61, 63 L.Ed. 166 (1918), which hold that, when the government specifies how the work is to be done, it impliedly warrants that adherence to the specifications will result in “satisfactory completion of the work.” John McShain, Inc. v. United States, 188 Ct.Cl. 830, 412 F.2d 1281, 1283 (1969); see also Chaney Bldg. Co. v. City of Tucson, 148 Ariz. 571, 574, 716 P.2d 28, 31 (1986).

The Spearin rule applies to design specifications only; it does not apply to performance specifications. Haehn Management Co. v. United States, 15 Cl.Ct. 50, 56 (1988). Design specifications precisely detail the manner in which the work is to be done. J.L. Simmons Co. v. United States, 188 Ct.Cl. 684, 412 F.2d 1360

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ry-Tan Construction, Inc. v. Washington Elementary School District No. 6
93 P.3d 1095 (Court of Appeals of Arizona, 2004)
Andrews v. Blake
69 P.3d 7 (Arizona Supreme Court, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
932 P.2d 1350, 188 Ariz. 79, 235 Ariz. Adv. Rep. 3, 1997 Ariz. App. LEXIS 9, Counsel Stack Legal Research, https://law.counselstack.com/opinion/willamette-crushing-co-v-state-arizctapp-1997.