Biener GmbH v. United States

35 Cont. Cas. Fed. 75,701, 17 Cl. Ct. 802, 1989 U.S. Claims LEXIS 149, 1989 WL 87937
CourtUnited States Court of Claims
DecidedAugust 8, 1989
DocketNo. 418-85C
StatusPublished

This text of 35 Cont. Cas. Fed. 75,701 (Biener GmbH v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Biener GmbH v. United States, 35 Cont. Cas. Fed. 75,701, 17 Cl. Ct. 802, 1989 U.S. Claims LEXIS 149, 1989 WL 87937 (cc 1989).

Opinion

OPINION

RADER, Judge.

Plaintiff, Biener GmbH (Biener), entered a contract with the United States Department of Defense (DOD) in 1980. In the contract, DOD promised to order from plaintiff all of its Direct Procurement Method (DPM) packing and containerization requirements for the Hanua/Aschaf-fenburg area of West Germany. The contract excluded items shipped by the Through Government Bill of Lading (TGBL) method.

Plaintiff alleges that DOD diverted business to the TGBL method of shipment and thereby breached the requirements contract. Plaintiff also asks this court to determine whether DOD negligently prepared the Best Estimated Quantities (BEQs) and whether DOD constructively terminated the contract for the convenience of the Government.

Defendant contends the contract did not cover TGBL shipping. Defendant also maintains that the cancellation clause limits plaintiff’s damages for DOD’s failure to order the quantities estimated by the contract.

The case at bar was assigned to this court for resolution on October 18, 1988. Both parties have moved for summary judgment. After oral argument, this court grants defendant’s motion for summary judgment and denies plaintiff’s cross-motion.

FACTS

On January 28, 1980, plaintiff won a Direct Procurement Method contract to pack the personal property1 of military personnel in the Hanua/Aschaffenburg area of the Federal Republic of Germany (Germany). In addition to conveying some property to nearby air bases, plaintiff agreed to place household goods and unaccompanied baggage such as furniture, linens, and clothing in suitable overseas shipment containers. This requirements contract originally ran from February 1, 1980 to September 30, 1982. On September 20, 1982, the DOD extended the contract to December 31, 1982.

Under the contract, plaintiff agreed to supply all of DOD’s requirements for DPM shipping services. DOD agreed to obtain DPM services only from plaintiff. Section L, Clause L-3 stated:

(b) Except as otherwise provided in this contract, the Government shall order from the Contractor all the supplies or services set forth in the Schedule which are required to be purchases by the Government activity identified in the “Ordering” clause.

DOD used DPM contracts for small local moves within Germany. Of most importance to the case at bar, however, the DOD also used DPM contracts for segments of trans-Atlantic moves. For example, one DPM contractor might pack the goods Germany, another might convey the packages to port, another might load the packages on the ship, and so on, until the shipment reached its destination in the United States.

As early as May 1979, DOD began to consider an alternative method of contracting for movement of personal property across the Atlantic. Under this alternative, the TGBL method, a single contractor is responsible for the entire move from initial packing to post-transit delivery. International Through Government Bill of Lading (ITGBL) refers to international movements by the TGBL procurement method.

[805]*805From May 1979 until April 30, 1980, DOD tested and evaluated the TGBL method for trans-Atlantic shipment of unaccompanied baggage. The test program became an optional recommended shipment method on May 1, 1980. DOD gave code designations to various classes of goods moved by the ITGBL method. DOD designated unaccompanied baggage as Code J. Code T referred to household goods moved under ITGBL procurements. In 1979, DOD began testing Code J ITGBL shipments. Although it had used ITGBL for at least 20 years in other parts of the world, DOD had not used ITGBL in Germany.

On November 1,1980, DOD implemented Code J ITGBL service for Germany.2 Consequently, a large portion of the unaccompanied baggage covered by plaintiffs contract, was shipped via TGBL carriers. This affected line items in Section E, Clause E-2, items 4b(l), 4b(2) and 13 (line items) of plaintiffs contract as follows:3

Best Estimated Quantity

ITEM 4b(l) ITEM 4b(2) ITEM 13

1st program year 20,000 40 13,600

2nd program year 25,000 50 17.000

3rd program year 25,000 50 17.000

Ext. period (3 mo.) 420 4 430

TOTAL ESTIMATE = 70,420 GCWT 114 GCWT 48,030 GCWT

Total Services Actually Ordered

From Biener 14,139 GCWT -0- GCWT 14,139 GCWT

From CONUS 35,885 " 104 " 20,291 *

On this chart, CONUS denotes continental United States shippers used to procure ITGBL services. Line items 4(b)l, 4(b)2, [806]*806and 13 denote DPM classes of unaccompanied baggage which also fell under Code J ITGBL. The chart shows that the total of shipment services ordered both under DPM from plaintiff and under ITGBL from CO-NUS did not reach the BEQs. In each category of unaccompanied baggage, DOD ordered more ITGBL services than DPM services. DOD continued to place orders for DPM services throughout the duration of plaintiffs extended contract.

Plaintiff’s contract contained a provision, Section E, Clause E-l (Scope of Contract), governing procurement of “like services or materials” via the TGBL method:

Excluded from the scope of this Contract is the furnishing of like services or materials which are provided incident to complete movement of personal property when purchased by the Through Government Bill of Lading method.

In the event that DOD failed to order the amount mentioned in the “Best Estimated Quantity” section of the contract, the document contained a cancellation clause. The cancellation clause guaranteed that plaintiff would receive compensation for start-up and other non-recurring costs if the Government failed to order as much as anticipated. For example, Section C, Clause C-15 d(f)(iv) of the contract provides:

The Contractor is entitled to reimbursement for preproduction and other non-recurring costs in accordance with the Clause “Cancellation Ceiling” in the event the Government orders lesser quantities than the aggregate BEQ or cancels any subsequent program year, by cancellation notice. (See L-14) For this purpose a cancellation ceiling rate has been estimated and established as shown in the clause J-7.

The parties agreed to freely negotiate the cancellation ceiling rate prior to contract award.4

This cancellation clause operated under three sets of circumstances. First, DOD could notify plaintiff that funds were not available for any subsequent program year. Second, DOD could fail to notify plaintiff that funds were available for the succeeding year. And finally, under Section L, Clause L-14b, DOD could fail to order the specified items in quantities up to the aggregate BEQs set forth in the contract.

The total value of the contract, based on the BEQs, was DM 5,791,338.50. The total value of the services covered under line items 4b(l), 4b(2) and 13, based on the BEQs, was DM 3,082,940. DOD ordered services covered by line items 4b(l), 4b(2), and 13 from an ITGBL contractor after full implementation of this alternative procurement method in November 1980. Plaintiff does not contest transactions under the contract other than those involving unaccompanied baggage.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Diebold, Inc.
369 U.S. 654 (Supreme Court, 1962)
First Nat. Bank of Ariz. v. Cities Service Co.
391 U.S. 253 (Supreme Court, 1968)
Hol-Gar Manufacturing Corp. v. The United States
351 F.2d 972 (Court of Claims, 1965)
Unicon Management Corporation v. The United States
375 F.2d 804 (Court of Claims, 1967)
Fortec Constructors v. The United States
760 F.2d 1288 (Federal Circuit, 1985)
Mingus Constructors, Inc. v. The United States
812 F.2d 1387 (Federal Circuit, 1987)
Government Systems Advisors, Inc. v. The United States
847 F.2d 811 (Federal Circuit, 1988)
Ralph Construction, Inc. v. United States
32 Cont. Cas. Fed. 72,430 (Court of Claims, 1984)
Universal Restoration, Inc. v. United States
35 Cont. Cas. Fed. 75,612 (Court of Claims, 1989)
Chemical Technology, Inc. v. United States
645 F.2d 934 (Court of Claims, 1981)
Clearwater Forest Industries, Inc. v. United States
650 F.2d 233 (Court of Claims, 1981)
Torncello v. United States
681 F.2d 756 (Court of Claims, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
35 Cont. Cas. Fed. 75,701, 17 Cl. Ct. 802, 1989 U.S. Claims LEXIS 149, 1989 WL 87937, Counsel Stack Legal Research, https://law.counselstack.com/opinion/biener-gmbh-v-united-states-cc-1989.