Ralph Construction, Inc. v. United States
Opinion
OPINION
Plaintiff Ralph Construction, Inc., brought this case under the Contract Disputes Act of 1978, 41 U.S.C. § 609(a)(1) (Supp. IV 1980), for breach of an asserted maintenance service requirements contract. The main breach alleged is that the government allocated work orders between in-house personnel and plaintiff on the basis of economic feasibility not permitted by the contract. The case is now here on defendant’s motion for summary judgment and plaintiff’s cross-motion for partial summary judgment.
FACTS
Plaintiff is a Texas corporation specializing in disaster relief services for state and federal agencies and maintenance services for governmental entities. In the spring of 1980, the Directorate of Facilities and Engineering (DFAE) at Fort Rucker, Alabama, sought bids for a contract to perform routine maintenance services at housing facilities at Fort Rucker. These services had previously been performed in-house by government personnel. The contract to be let here was the first one for services to be performed by a private contractor.
The government calculated its “best estimates” of the work tasks to be required of the successful bidder based on completed service orders and work orders performed by government personnel during the 12-month period preceding the issuance of the solicitation. Separate line items specified the government’s estimate of the quantities of supplies and services the contractor could be required to provide. Bidders were required to insert a unit price for each line item.
Plaintiff was the low bidder and was awarded the contract on a bid of $411,-619.21. The estimates were incorporated in the contract awarded plaintiff in a “unit price schedule.” The contract also contained the following provision:
(a) This is a requirements contract for the supplies or service specified in the schedule, and for the period set forth therein. Delivery of supplies or performance of services shall be made only as authorized by orders issued in accordance with the clause entitled “Ordering”. The quantities of supplies or services specified herein are estimates only, and are not purchased hereby. These quantities are not the total requirements of the activity named in the Schedule; they are estimates of requirements in excess of the quantities which such activity may itself furnish within its own capabilities. Except as may be otherwise provided herein, in the event the Government’s requirements for supplies or services set forth in the Schedule do not result in orders in the amounts or quantities described as “estimated” or “maximum” in the Schedule, such event shall not constitute the basis for an equitable price adjustment under this contract.
(b) Except as otherwise provided in this contract, the Government shall order from the Contractor all the supplies or services of the Government activity named in the Schedule in excess of the quantities which the activity may itself furnish within its own capabilities.
Plaintiff began performance of the contract in August of 1980, a time when there was a backlog of maintenance work. The government initially adopted a policy of assigning plaintiff all backlog work covered by the contract not already assigned to [730] government employees and, after August 25, 1980, of assigning plaintiff all service orders called into DFAE,
Footnotes
32 Cont. Cas. Fed. 72,430 (Ralph Construction, Inc. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.