Bockman Printing & Services, Inc. v. Baldwin-Gregg, Inc.

572 N.E.2d 1094, 213 Ill. App. 3d 516, 157 Ill. Dec. 630, 15 U.C.C. Rep. Serv. 2d (West) 490, 1991 Ill. App. LEXIS 723
CourtAppellate Court of Illinois
DecidedMay 3, 1991
Docket1-89-3021
StatusPublished
Cited by11 cases

This text of 572 N.E.2d 1094 (Bockman Printing & Services, Inc. v. Baldwin-Gregg, Inc.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bockman Printing & Services, Inc. v. Baldwin-Gregg, Inc., 572 N.E.2d 1094, 213 Ill. App. 3d 516, 157 Ill. Dec. 630, 15 U.C.C. Rep. Serv. 2d (West) 490, 1991 Ill. App. LEXIS 723 (Ill. Ct. App. 1991).

Opinion

JUSTICE McNAMARA

delivered the opinion of the court:

Defendants, Baldwin-Gregg, Inc., and Baldwin Technology Corp., appeal from the trial court’s order granting summary judgment on liability in favor of plaintiff. After a bench trial as to damages only, the trial court awarded damages to plaintiff in the amount of $181,338.16. Defendants also appeal the award of damages. Plaintiff cross-appeals, alleging that the trial court applied the wrong period for damages and erred in denying its claim for outside bindery charges.

Plaintiff, Bookman Printing and Services, Inc., is a company which prints and mails advertising for its customers. In the late 1970’s and early 1980’s, Anthony and Robert Perrone, plaintiff’s executive vice-president and president, respectively, attempted to purchase a folding machine that would attach to its Didde Glaser Webb press (Didde press) and fold printed material at the same rate as the press. At the time, the Didde press printed material which was transported to another area where other machines folded it. The Perrones believed that an in-line attached folder would increase plaintiff’s production capacity, reduce cost, time and labor and result in substantial savings to its customers.

Beginning in about 1978, plaintiff attempted to purchase such an in-line folder. Custom-Bilt, a New York company, built and installed a folder in 1981, which ran only at one-third the rate of the Didde press. A subsequent attempt by Custom-Bilt to rebuild the folder also failed. In 1984, plaintiff consulted with the Vijuk Company, which, in 1985, installed an in-line folder which was also unsatisfactory.

Plaintiff contacted defendants in 1982. Defendants’ engineering manager, engineers and salesman visited plaintiff’s plant, viewed and took measurements of the Didde press. Plaintiff explained the type of folds it sought to make, and defendants’ agents assured plaintiff that they could produce and guarantee the folder.

Based upon these preliminary meetings, defendants prepared a proposal, dated July 13, 1982, which provided that defendants would design a “double chopper folder” according to plaintiff’s specifications. It further provided that: “[T]he folder, after being built, but before delivery, would be ‘tested at the [defendants’] factory prior to shipment and you will be invited to witness tests.’ ” A guarantee clause provided that if the folder did not perform the folds according to specifications, defendants would refund to plaintiff all monies paid. On a separate page, defendants indicated: “In no event shall we be liable for any contingent or consequential charges or damages.” The proposal’s “estimated delivery” was six months after defendants received the order, down payment and necessary engineering information. Defendants’ August 11, 1982, letter to plaintiff repeated the payment terms. In a letter dated August 23, 1982, Anthony Perrone accepted defendants’ offer to build the double chopper folder. His letter provided: “We also would expect all of our money back if at any time or for whatever reason the folder does not do an acceptable job,” defining “acceptable” as operating at the same speed as the Didde press. On September 8, 1982, defendants sent plaintiff a letter which stated: “[Defendants] will do everything possible to make this a successful installation, but will not be liable for any contingent or consequential charges or damages.” The trial court found that the July proposal and the two August letters comprised the contract.

Defendants thereafter stated that design work was proceeding and projected February 1983 as the completion date and April 1983 as the shipping date. The folder, however, was not delivered in April 1983. Defendants’ July 6, 1983, letter assured plaintiff that defendants could make the folder and promised delivery by September 1, 1983. In September 1983, defendants telephoned plaintiff, asking what color to make the folder.

In October 1983, the Perrones viewed a demonstration of the then-existing folder at defendants’ place of business. The folder failed to operate at a high enough speed and failed to meet the fold accuracy requirements. Plaintiff informed defendants that the folder was not acceptable.

On December 15, 1983, defendants advised plaintiff that they had been unsuccessful in constructing a folder to meet plaintiff’s requirements and had “exhausted all technical approaches known to [them],” spending more than $70,000 in their efforts. Defendants also issued a check to return plaintiff’s down payment.

Plaintiff filed suit against defendants on May 16, 1984. The complaint, as amended, consisted of six counts: wrongful repudiation of the agreement; breach of the agreement; faüure to act in good faith; improper attempt to limit consequential damages; breach of implied warranties of merchantability; and breach of fitness for a particular purpose.

After a hearing on the parties’ cross-motions for summary judgment, the trial court granted summary judgment in favor of plaintiff on the issue of liability. Subsequently, a trial proceeded solely on the issue of damages.

At the trial on damages, plaintiff sought recovery for cover under section 2 — 711 of the Uniform Commercial Code (UCC) (Ill. Rev. Stat. 1989, ch. 26, par. 2 — 711) for the purchase of two Baum folders and a Vijuk folder. Plaintiff also sought consequential and incidental damages under section 2 — 715 of the UCC, consisting of outside folding costs, payroll overtime charges, and the cost of an extra employee. Finally, plaintiff sought recovery of its down payment.

The trial judge determined that the applicable period of damages was February 1983 through December 1983, and awarded the following damages: (1) $34,000 for the two Baum folders; (2) $56,275 for the Vijuk folder; (3) $67,485.66 for overtime; (4) $8,640 for an additional employee; and (5) $14,937.50 for return of plaintiff’s down payment.

PLAINTIFF’S DAMAGES

We summarize below the most relevant evidence adduced at the damages trial.

Anthony Perrone and William Marshall each testified that plaintiff’s equipment folded off-line at a cost of $3 per thousand and that the double chopper folder would reduce the cost and enable plaintiff to charge customers $1 per thousand for folding. According to Perrone, plaintiff instructed its sales staff to use this as a price advantage and commit itself based upon this rate for work coming in as of February 1983.

Anthony Perrone estimated that plaintiff’s business increased by 300% during this period. Marshall testified that business began to increase in February 1983, but he did not know the dollar volume. Although no records existed to document this increase, his conclusion was “based upon [his] knowledge of being in there and fighting the battle.” He said that things became more manageable and began to return to normal in March 1985.

Morris Elstein, plaintiff’s vice-president of sales, testified that he and his sales staff started making quotes to customers based upon the new rate soon after the parties contracted for in-line equipment.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Worldcom, Inc.
492 B.R. 696 (S.D. New York, 2013)
Shoop v. DaimlerChrysler Corp.
864 N.E.2d 785 (Appellate Court of Illinois, 2007)
Shoop v. DaimlerChrysler Corporation
Appellate Court of Illinois, 2007
Valenti v. Mitsubishi Motor Sales of America, Inc.
773 N.E.2d 1199 (Appellate Court of Illinois, 2002)
Meade v. Kubinski
661 N.E.2d 1178 (Appellate Court of Illinois, 1996)
McCarthy Brothers Co. v. State
47 Ill. Ct. Cl. 15 (Court of Claims of Illinois, 1995)
McGill v. Trooper Publications, Inc. (In re Holler)
187 B.R. 622 (C.D. Illinois, 1994)
Beasley v. Pelmore
631 N.E.2d 749 (Appellate Court of Illinois, 1994)
Ohline Corp. v. Granite Mill
849 P.2d 602 (Court of Appeals of Utah, 1993)
Ouwenga v. Nu-Way Ag, Inc.
604 N.E.2d 1085 (Appellate Court of Illinois, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
572 N.E.2d 1094, 213 Ill. App. 3d 516, 157 Ill. Dec. 630, 15 U.C.C. Rep. Serv. 2d (West) 490, 1991 Ill. App. LEXIS 723, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bockman-printing-services-inc-v-baldwin-gregg-inc-illappct-1991.