Boyd Bros. v. State

52 Ill. Ct. Cl. 191
CourtCourt of Claims of Illinois
DecidedNovember 30, 1998
DocketNo. 93-CC-2145
StatusPublished

This text of 52 Ill. Ct. Cl. 191 (Boyd Bros. v. State) is published on Counsel Stack Legal Research, covering Court of Claims of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Boyd Bros. v. State, 52 Ill. Ct. Cl. 191 (Ill. Super. Ct. 1998).

Opinion

ORDER

Frederick, J.

This cause comes before the Court on Claimants renewed motion for summary judgment and Respondents motion for summary judgment on all claims for extras in area other than the northeast quadrant, and on the issue of Claimants claim for compensation for idle equipment, and the Court having reviewed the pleadings, affidavits, depositions, exhibits and arguments, and the Court being fully advised in the premises, wherefore, the Court finds:

1. That the Abandoned Mines Lands Reclamation Council, “AML,” designed the reclamation plans for the St. Ellen Mine site in St. Clair County, Illinois.

2. That the AML plans which were incorporated into the contract failed to take into account the Dunn Geoscience Report, failed to correctly incorporate the AML’s own core sample data, the cooperative wildlife service data, and failed to include the project manager’s posterboard which indicated slurry that did not appear on the AML plans.

3. That article 102.05 of the Standard Specifications indicated that the subsurface information set forth in the AML plans represented the best knowledge of the Department as to the location, character or quantity of the materials encountered.

4. That Respondent failed to provide Claimant with the Dunn Geoscience Report, the posterboard and soil core sample chart and results prior to the bid acceptance although requested to do so by Claimant. Standard Specifications, article 102.05 indicated that, all soil information upon which the design was prepared was available for inspection by bidders.

5. That Respondent drafted the contract.

6. That under the terms of the contract, the Claimant was to complete the work in accordance with the plans and specifications.

7. Article 105.04 required that all work performed and all materials furnished shall be in reasonably close conformity with the lines, grades, cross-sections, dimensions, and material requirements, including tolerances, shown on the plans or indicated on the specifications.

8. That articles 101.24 and 104.01 indicate that the plans and specifications show the location, character, dimensions, and details of the work to be done and prescribe a complete outline of the work which the contractor undertook to do to satisfy the contract.

9. That the plans prepared by the project manager differed materially from the actual work to be done in that the soil lines in the plans were substantially different than those actually encountered; there was substantial slurry encountered that was not shown on the plans and specifications; and there were buried levees and dams now shown on the plans.

10. That the Claimant’s inspection of the site prior to bidding was reasonable in light of the conduct of the Respondent.

11. That AML failed to obtain the right-of-way for the Ahring property prior to letting the contract in violation of the terms of the contract.

12. That the Dunn Geoscience Report was reasonably accurate in regard to the conditions at the site.

13. That because of the defective plans, the following additional work was required:

(a) In the north quadrant, approximately 258,425 cubic yards of mine refuse were below the grade indicated on the AML plans;

(b) In the west area, approximately 146,403 cubic yards of mine refuse material were below the grade indicated on the AML plans;

(c) The moisture content of much of the material to be excavated was materially higher;

(d) That the amount of wet material to be handled above and below the AML plan lines was materially increased;

(e) Different methods were required to obtain and haul the refuse because of the changed character of the refuse than could have been anticipated from the AML plans;

(f) Hauling distances were increased and top loading was required because of the character of the refuse which could not have been anticipated from the AML plans;

(g) Drainage as called for in the AML plans could not be achieved because soil lines were not accurate;

(h) That the delays in obtaining the right-of-ways delayed implementing a drainage plan, required pumping, and allowed for trapping of moisture.

14. On March 12, 1992, Claimant gave AML notice in writing that the actual site conditions were materially different from those shown on the AML plans.

15. That Respondent by letter directed Claimant to remove all refuse above the upper surface of the soil.

16. That Claimant gave the notice through letters and progress reports required under the changed conditions clause of Standard Specifications, article 104.04.

17. That Respondent materially changed the scope of the work under the terms of the contract.

18. That Respondent required Claimant to do substantial extra work as defined by Standard Specifications, article 101.15.

19. That the extra work was required because the work differed materially in design and required a change in the type of construction.

20. That adjustments in compensation and contract under these circumstances are to be made in accordance with articles 104.03 and 108.09.

21. That the AML’s requirement that Claimant remove all refuse above the upper surface of the soil was a significant change in the character of the work.

22. That the character of the work as altered differed materially in kind and nature from that involved or included in the original proposed construction.

23. That AML had written án actual notice of the changed conditions and character of the work under the contract.

24. That the parties were unable to agree on a basis for an adjustment of the contract price.

25. That in the letter to Claimant to continue work, AML indicated article 109.03 of the Standard Specifications addresses the issue of how payment is to be made for increased or decreased quantities of contract unit pay price.

26. That Respondent refused to adopt a contract and payment adjustment.

27. That the contract documents affirmatively represented the subsurface conditions which form the basis of this claim.

28. That the contractor acted as a reasonably prudent contractor in interpreting the contract documents.

29. The contractor reasonably relied on the subsurface conditions in the contract documents.

30. The subsurface conditions actually encountered differed materially from the subsurface conditions indicated in the contract.

31. The actual subsurface conditions were reasonably unforeseeable.

32. That Claimant had excess costs solely attributable to the materially different subsurface conditions.

33.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ude, Inc. v. State
35 Ill. Ct. Cl. 384 (Court of Claims of Illinois, 1982)
Loewenberg/Fitch Partnership v. State
38 Ill. Ct. Cl. 227 (Court of Claims of Illinois, 1986)
First National Bank v. State
43 Ill. Ct. Cl. 1 (Court of Claims of Illinois, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
52 Ill. Ct. Cl. 191, Counsel Stack Legal Research, https://law.counselstack.com/opinion/boyd-bros-v-state-ilclaimsct-1998.