All States Painting, Inc. v. State

43 Ill. Ct. Cl. 231, 1991 Ill. Ct. Cl. LEXIS 70
CourtCourt of Claims of Illinois
DecidedJune 18, 1991
DocketNos. 88-CC-0946, 87-CC-1000 cons.
StatusPublished

This text of 43 Ill. Ct. Cl. 231 (All States Painting, Inc. v. State) is published on Counsel Stack Legal Research, covering Court of Claims of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
All States Painting, Inc. v. State, 43 Ill. Ct. Cl. 231, 1991 Ill. Ct. Cl. LEXIS 70 (Ill. Super. Ct. 1991).

Opinion

OPINION

Montana, C.J.

Claimant All States Painting, Inc. (hereinafter referred to as All States) brought these claims seeking payment for work performed pursuant to a contract with the Respondent’s Capital Development Board (hereinafter referred to as the CDB). The claims were initially filed on standard lapsed appropriation form complaints. The allegations were, inter alia, that demands for payments were made to the CDB and that the demands were refused on the grounds that the funds appropriated for the payments had lapsed. As the cases developed it became clear that much more than lapsed appropriations were involved. The cases were assigned to a commissioner and consolidated. A hearing was held, briefs were filed, the commissioner has made his report, and the case is now before us for decision on the merits.

The facts are for the most part undisputed. On March 24,1986, All States responded to an invitation by the CDB to submit bids for the rehabilitation of a 500,000 gallon elevated water tower located at the Jacksonville Developmental Center in Jacksonville, Illinois.

The bidding documents provided for the bidder to quote a price for “General/Painting Work” and also asked bidders to quote a unit price for doing electric fusion pit-welding, the unit price to be stated in terms of the bidders’ price for doing units of 50 pit-welds. The base bid included welding 300 pits.

All States’ bid was $36,000.00 for the base and a unit price of $350.00 for each 50 pits. On May 21,1986, CDB sent All States a notice of award stating that its bid was accepted. This document showed the contract amount as $36,000.00 and made no reference to the unit price portion of All States’ bid. In this document, as was true with the bidding documents, All States was warned that all work “shall be completed # * no later than September 1,1986.” All States on that same date signed a contract which provided for a contract amount of $36,000.00 and left blank the area following the phrase, “the following alternate bids, unit prices and material substitutions have been accepted and are incorporated in this contract.” However, the project manual, which was incorporated into the contract by reference, stated “All pits on waterside surfaces of bowl, shell and riser cylinder shall be filled with weld metal by electric fusion welding process. This shall include all pits 1/8 inch or deeper.”

A “pit” is an area one inch square on the inside of the elevated water tank that has become so corroded that it must be repaired so that after the tank has been repainted debris will not adhere to it. Pit-welding consists of filling these pits so that the metal of the tank is restored to its original thickness.

According to the Claimant, before any pit-welding could be done the interior of the tank had to be sandblasted to remove loose particles and to clean the tank down to the bare metal. The Claimant also stated that when the interior of a tank is badly corroded and a substantial amount of pit-welding is needed, the initial sandblasting takes three times as long as it does if the inside of the tank is smooth.

It was only after the initial sandblasting was complete that it could be determined how extensive was the need for pit-welding. Prior to that there was no way of knowing how many pits would require welding. It was ultimately agreed that 18,350 pits required welding, 18,050 (316 units of 50 pits each) more than what were included in the base bid.

After the pit-welding was completed, it was necessary to sandblast the interior of the tank again in order to smooth the surface. The presence of the pit-welds, which make the surface quite uneven, causes this sandblasting to take four times as long as would be the case on a smooth surface. Only then was the interior ready for the two coats of paint called for in the specifications. The necessity of pit-welding thus resulted in a substantial labor cost to Claimant, over and above what would have been required otherwise, not only for the sandblasting, but also in providing men on site while the welding was going on in order to comply with safety regulations. The pit-welding work, which was done by All States’ subcontractor, Birdco Fabricators, took 28 days to complete, using three men.

All States began its work on the tower soon after July 10, 1986. By August 8, 1986, the subcontractor had completed a substantial portion of the pit-welding work. Bernie McCabe, project manager for CDB was on the site approximately three times a week during performance of the job. However, at no time did he ask or demand that All States stop the pit-welding in order to get a change order approved. Indeed, Mr. McCabe stated to both the subcontractor, Everett Birdsell, and to All States’ vice president and job superintendent, Michael Desyllas, that the pit-welding was being done under the unit price of $350.00 per 50 pits and that All States should go ahead with the work. Mr. McCabe, who was the only CDB representative with whom All States had contact during this project, made this statement to Mr. Birdsell close to completion of the pit-welding work. Also, two men from the CDB, described by the Respondent as engineers and investigators, came to the site while the pit-welding was ongoing in order to inspect the condition of the interior and determine the amount of pit-welding required. Again, no stop work order was given after this inspection, and the pit-welding was continued to completion.

In fact, it was not until August 18, 1986, when the pit-welding was virtually completed, that All States was informed that its unit price bid had not been accepted. Patricia Desyllas, president of All States, testified that the company would never have signed the contract if it had known that the CDB was attempting to accept only a part of its bid.

On September 2,1986, John Evans of CDB wrote to All States asking for its cost breakdown in welding the pits. On September 17, 1986, All States submitted its invoice-voucher requesting payment of $162,350.00 being the amount of its base bid and welding of 18,050 pits at $350.00 per 50 pits. However, these documents were returned to All States in mid-October.

Thereafter, without the knowledge of All States, CDB contacted Birdco Fabricators, the subcontractor, and asked for its costs involved in the pit-welding so that a change order could be prepared. The subscontractor’s information was placed on a form used to start the change order process. The change order document itself was prepared December 15, 1986, and ultimately was approved by CDB on March 20,1987. This change order in the amount of $32,248.87, was based solely on the subcontractor’s costs in doing the pit-welding; other than the subcontractor costs, none of All States’ costs were figured into the change order. During the three months that this change order request was pending, no one from CDB notified All States that this process was going on or asked for All States’ costs involved in the pit-welding. All States had no knowledge that this process was taking place. CDB was interested in getting its paperwork finished and closing its file.

Relying upon advice of counsel, All States did not submit a request for change order in the Fall of 1986 because it believed the unit prices to be a part of the written contract and because the project was not finished anyway.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ude, Inc. v. State
35 Ill. Ct. Cl. 384 (Court of Claims of Illinois, 1982)
Loewenberg/Fitch Partnership v. State
38 Ill. Ct. Cl. 227 (Court of Claims of Illinois, 1986)
Bojko v. State
41 Ill. Ct. Cl. 202 (Court of Claims of Illinois, 1989)
A & H Plumbing & Heating Co. v. State
42 Ill. Ct. Cl. 195 (Court of Claims of Illinois, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
43 Ill. Ct. Cl. 231, 1991 Ill. Ct. Cl. LEXIS 70, Counsel Stack Legal Research, https://law.counselstack.com/opinion/all-states-painting-inc-v-state-ilclaimsct-1991.