Walsh v. State

24 Ill. Ct. Cl. 441, 1964 Ill. Ct. Cl. LEXIS 4
CourtCourt of Claims of Illinois
DecidedMay 12, 1964
DocketNo. 4791
StatusPublished
Cited by4 cases

This text of 24 Ill. Ct. Cl. 441 (Walsh v. State) is published on Counsel Stack Legal Research, covering Court of Claims of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Walsh v. State, 24 Ill. Ct. Cl. 441, 1964 Ill. Ct. Cl. LEXIS 4 (Ill. Super. Ct. 1964).

Opinion

Pezman, J.

On September 30, 1957, claimants filed their original complaint seeking an award in the amount of $151,549.89 for losses, alleged to have been sustained by them in the construction of certain buildings at the Tinley Park State Hospital, Tinley Park, Hlinois. On April 24, 1959, claimants filed an amendment to the complaint by adding-additional items to the bill of particulars, and thereby increasing the ad damnum to $216,788.61.

The above entitled cause was heard by a Commissioner on December 19, 1958 at Chicago, Illinois. Claimant, Matthew M. Walsh, was the sole witness for claimants. Respondent’s evidence consisted of the Departmental Report. On the 2nd day of June, 1959, the Court on its own motion found that the record was inadequate and insufficient for a proper consideration of the cause and of claimants ’ damages, and ordered the matter heard ££en banc”. The cause was heard in 1960 by the Court of Claims, consisting of Judge Gerald W. Fearer, Judge James B. Wham and the late Joseph J. Tolson, Chief Justice.

Since the facts of the case are extremely complex, a preliminary statement identifying the separate contracts, the location of the buildings, and the problems confronted are hereafter set forth.

Prior to June 1,1951, the State of Illinois determined that a new hospital was needed, and a large tract of land, formerly a farm, was purchased near Tinley Park, Illinois. The firm of Skidmore, Owens and Merrill of Chicago, Illinois, was engaged as associate architects to prepare plans and specifications, and thereafter bids were taken for the proposed work. The project involved multiple bids for the different kinds of work to be performed, and claimants were the successful bidders on three of the jobs.

1. Contract No. 66921 — Power Plant-__________________________$370,411.00

2. Contract No. 6748 — Water Treatment Plant_______ 334,000.00

3. Contract No. 6745 — Sewage Treatment Plant._______ 227,000.00

The work was commenced at a time when the Korean War was in progress, and the matter of obtaining priorities for needed material was of great significance in the performance of the contracts.

For the purpose of clarity, each of the jobs will be identified by its number and discussed separately, and thereafter a summary of each claim will be set forth in a recapitulation.

CONTRACT NO. 66921

POWER HOUSE

The plans and specifications called for the construction of a two story brick and glass building, together with a full basement and smaller brick building located nearby.

Matthew M. Walsh testified that he examined the plans and specifications, and, prior to May 1, 1951, went out to the site to examine the premises, so that he could prepare a bid. (The plans were in accordance with usual practices, requiring a bidder to inspect the site, as he would thereafter be charged with knowledge of bidding-conditions.) An access road was under construction at the time, and he stated, though it was rough, he could and did drive over it to the area where the contracts were to be performed, if his firm was the successful bidder. The contract for the road had been let at a prior time, and was to be finished in 45 days, so that the other contractors would have access to the interior of the farm land to perform their work.

Claimants submitted their bids on May 5, 1951, and the State extended the time for acceptance to June 30, 1951, as the road was incomplete. Mr. Mocardell, Chief of Construction, assured claimants that the road would be completed when construction started. The road was not completed in the 45 days, and, in fact, was not completed until 1956 due to a peat condition, which was discovered in the road bed.

Claimants lay great stress on this absence of an access road, as their bid was predicated on the plans, which described the road in the blueprints, and their examination of the building site, which showed the road under construction, and their assurances that a hard road would be ready for them to haul in steel, concrete, etc., needed in the performance of their contract.

On July 10, 1951, claimants started the excavation of the basement, and completed it on August 17, 1951. Wooden perimeter forms were set so that the concrete floor could be poured.

At this state of the construction, plumbers should have been installing drains, and electricians should have been installing conduits, and, if this had, in fact, been done, the entire floor would have been in place by September 4,1951.

It was then discovered that the plans for plumbing and electrical work were incomplete, and Mr. Gilbertson, Field Superintendent for the State, stopped the pouring of the concrete.

While claimants waited for the State to procure plans and specifications for the plumbers and electricians, who were bidders on separate contracts, torrential rains hit the area, and claimants were obliged to pump the excavation for many days, and thereafter to remove and clean the reinforcing steel, remove and wire brush the steel rods, reset and realign the forms.

On October 5, 1951, claimants were directed to pour the slab despite the fact that the electrical conduits were not in place. At this point, claimants allege that the State was negligent in not having plumbing and electrical plans available, so that the work could have been performed a month earlier, and, if they had been available, claimants would not have had to pump the excavation, and re-do the work that was in place ready for concrete.

On October 25, 1951, claimants started work on the walls. This work was stopped by the State, as the electrical plans were still incomplete, and no provisions were made for sleeves for the pipe contractor.

Claimants made repeated efforts to get the State Architect and the associate architect to complete the drawing, so that they could continue with the work. Months went by, and it was not until March 5, 1952 that claimants were authorized to proceed with the work. The basement concrete was not finished until April 24, 1952, many months behind the schedule.

The slab floor and walls had been poured with reference to the location of the steel to be erected on the area built up for a certain type of diesel motor and generator. It appeared that the electrical contractor was given the option to install another type of equipment, and, when he exercised his option, the slab had to be altered, footings had to be cut, the roof had to be altered, and changes had to be made in the type and kind of steel.

Claimants urge that the State should have inquired as to the type of electrical equipment to be installed before directing claimants to comply with the original plan, and thereby avoided the additional work.

In summarizing Contract No. 66921, claimants allege that they bid the job, so that it could be completed in 360 working days, i.e., June 30, 1952. They allege that the State failed to provide other contractors with plans and specifications on time, so that their work could be correlated into his contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

James Cape & Sons Co. v. State
52 Ill. Ct. Cl. 322 (Court of Claims of Illinois, 2000)
Fru-Con Corp. v. State
50 Ill. Ct. Cl. 50 (Court of Claims of Illinois, 1996)
Illinois Constructors Corp. v. State
45 Ill. Ct. Cl. 124 (Court of Claims of Illinois, 1993)
Johnson County Asphalt, Inc. v. State
39 Ill. Ct. Cl. 36 (Court of Claims of Illinois, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
24 Ill. Ct. Cl. 441, 1964 Ill. Ct. Cl. LEXIS 4, Counsel Stack Legal Research, https://law.counselstack.com/opinion/walsh-v-state-ilclaimsct-1964.