Chicago & E. I. R. R. v. Moran

85 Ill. App. 543, 1898 Ill. App. LEXIS 1082
CourtAppellate Court of Illinois
DecidedNovember 21, 1899
StatusPublished
Cited by3 cases

This text of 85 Ill. App. 543 (Chicago & E. I. R. R. v. Moran) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chicago & E. I. R. R. v. Moran, 85 Ill. App. 543, 1898 Ill. App. LEXIS 1082 (Ill. Ct. App. 1899).

Opinion

Mr. Justice Freeman

delivered the opinion of the court.

It is first contended by appellant that the notice and copy of contract, required to be served in accordance with the railroad lien act (Rev. Stat. Chap. 82, Sec. 9), were not served upon appellant within twenty days after the completion by appellee of the work under his sub-contract with Chapman. It is contended that the arrangement made Avith Chapman’s consent, betAveen appellee and appellant, about November 23, 1892, in accordance with Avhich appellant completed the parapet walls for Moran, operated as a termination and completion at that date of the sub-contract between appellee and Chapman.

The railroad company finished the work about the mid-die of December. The notice required to maintain appellee’s lien was served upon appellant December 27th, and within the time required by statute, if it be considered that appellee’s sub-contract with Chapman was not completed, until the appellant company finished, under its agreement with appellee, the construction of the parapet walls, which were included within said sub-contract.

If, on the other hand, the arrangement between appellant and appellee, made about November 23d previous, operated as a completion of appellee’s sub-contrac't, because appellant agreed to finish the work itself with the material already furnished by appellee, then the notice served December 27th following, was not served within twenty days of the completion of the sub-contract.

There is no controversy “ as to the dates, facts and circumstances of this transaction,” as appellant’s counsel concede. It is manifest that while Moran did not do any actual work under the sub-contract with Chapman after the arrangement of November 23d, or thereabouts, was made with the appellant company, still the work itself, as required by said sub-contract, was not done until finished by appellant about December 14th. Appellee’s contract with Chapman was not completed until that date. It is evident also that his responsibility for a portion of the work, at least, did not cease until that date. According to evidence introduced in behalf of appellant, appellee was allowed for the material and the cutting of the stone composing the wall. All that the appellant company undertook was to lay the stone furnished by Moran in place, that is, erect the wall; and in making the arrangement as to price, Moran allowed, and the appellant company was to receive—deducting it from what, under the sub-contract, Moran was otherwise entitled to—three dollars a cubic yard for setting the stone. No arrangement was made that appellant should supply or cut or recut any stone in case of any deficiency or defect or misfit. It does not appear even that any investigation was made by appellant of the quantity or quality or condition of the stone. The company merely agreed to set it in place, and all the other work and material agreed to be furnished by Moran under his sub-contract with Chapman he was still liable for until the whole was completed. He was not released from his contract by the arrangement with appellant and his liability thereunder did not end until the stone he agreed to and did furnish was actually in place and the parapet walls completed. This was not until about December 14th, and his notice of lien was served December 27th, within twenty days of the completion of the sub-contract.

There are other considerations which lead to the same conclusion. The railroad company clearly, under the arrangement with Moran, would not have been obliged to settle with Chapman, the original contractor, and pay him for the work Moran was to do until it was actually done, and it was thus ascertained that the stone Moran was furnishing was sufficient in quantity and in all other respects to comply with the contract. Appellant did not, in fact, settle with Chapman until December 19th, four days after the completion of the parapet walls, as required by the contracts.

When it did thus settle, Chapman admitted indebtedness to Moran, and appellant accepted his statement of the amount of that indebtedness without verifying its correctness, when, according to its own answer, it might have been put upon its guard by the condition wkich Chapman exacted to be complied with before Moran should be paid what Chapman admitted was due him, viz., that he should sign a receipt in full and a release of both Chapman and appellant from.further liability.

It is urged that the Circuit Court erred in overruling certain exceptions to the master’s report. These refer to an extra allowance to Moran for cutting 3,548.8 yards of Joliet stone at $1 per yard, and to the allowance of interest. The real contention is as to the allowance of anything extra for cutting the Joliet stone.

It is conceded that a verbal agreement was made between Moran, Chapman and one Baldwin, representing appellant as its chief engineer, that Moran should receive this $1 per cubic yard for the 3,548.8 cubic yards of stone for which the allowance complained of was made. Appellant’s contention is that this verbal agreement is in contravention of the written contract between Moran and Chapman, and therefore void. It is not denied that Moran proceeded under the agreement, in good faith, to furnish, and did furnish and cut, this quantity of Joliet limestone.

We perceive no reason why the railroad company could not agree—if it desired that Joliet limestone should be used instead of the Indiana sandstone called for by the contract—to pay Chapman, for Moran, the excess, or supposed excess, in cost of the former stone over the latter ; nor why appellant could not make an explicit and binding agreement to pay the extra dollar per cubic yard in consideration of getting the Joliet stone.

It is urged, however, that the contract in writing between Chapman and appellee contemplated this very contingency, that it might become necessary to use other stone than that described therein, and provided just what extra compensation should be paid in such case, whether for Joliet or any other stone, and that no more can be recovered, notwithstanding the new verbal agreement.

The sub-contract contains a provision that if Moran “ is obliged to secure stone from quarries other than those mentioned above, and from such other quarries the rough stone costs more than $3 per cubic yard, the party of the second part (Chapman) will pay the difference between $3 per cubic yard and the cost of such stone. But no stone shall be secured from such other quarries without the written consent of the engineer of the second party.”

The contract expressly distinguishes between the “ cost of and freight rates on stone.” While the charge for freight in ease stone was procured from other quarries was specified in the contract, the difference in cost of such stone was not thereby expressly fixed. It was left to be ascertained when the contingency should arise.

It would appear that the use of Joliet limestone, involving extra expense in cutting over Indiana sandstone, was a contingency not contemplated when the contracts were drawn. This is indicated by the conduct of the parties. When the question arose, appellant’s chief engineer did not claim that the appellee could be compelled to use Joliet stone under the contract. Such an idea seems not to have been suggested.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Town of Milford v. O'Neil Bros., Inc.
8 Conn. Super. Ct. 403 (Connecticut Superior Court, 1940)
First Savings & Trust Co. v. Milwaukee County
148 N.W. 22 (Wisconsin Supreme Court, 1914)
W.H. Stubbings Co. v. World's Columbian Exposition Co.
110 Ill. App. 210 (Appellate Court of Illinois, 1903)

Cite This Page — Counsel Stack

Bluebook (online)
85 Ill. App. 543, 1898 Ill. App. LEXIS 1082, Counsel Stack Legal Research, https://law.counselstack.com/opinion/chicago-e-i-r-r-v-moran-illappct-1899.