Hart v. Carsley Manufacturing Co.

116 Ill. App. 159
CourtAppellate Court of Illinois
DecidedOctober 4, 1904
DocketGen. No. 11,495
StatusPublished
Cited by1 cases

This text of 116 Ill. App. 159 (Hart v. Carsley Manufacturing Co.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hart v. Carsley Manufacturing Co., 116 Ill. App. 159 (Ill. Ct. App. 1904).

Opinion

Mr. Presiding Justice Windes

delivered the opinion of the court.

A preliminary question is presented, viz., as to whether there can be any recovery in this case on the common counts, the trial court having held that the contract between the parties was not admissible in evidence under the special count, but was competent only under the common counts, and that ruling not being questioned. In view of the recent case of Foster v. McKeown, 192 Ill. 339-48, we deem it unnecessary to make any review of the numerous authorities referred to by appellants’ counsel. ' That case is quite similar in its facts to the case at bar, in so far as concerns the right to recovery on the common counts. It was there claimed, as in this case, that the plaintiff, who sought to recover on the common counts without the architect’s certificate, had performed his part of a written building contract. The court, in speaking approvingly of a previous decision-—Fowler v. Deakman, 84 Ill. 130—-say, that it announces the rule that “ where there is a special contract, and the work has been performed in substantial compliance with it, and the only thing lacking is the certificate of the architect, and that is withheld, not because the architect finds that the work is improperly done or unsuitable mar terial furnished, but simply because he may not see fit to give it, or because he may be directed by the owner not to do so, the action will lie under the common counts, and proof may be made as to the excuse for not furnishing the certificate.”

The jury in this case held, and the evidence in the record in our opinion sustains the finding, that the final certificate of the architect was withheld through collusion with the defendants, or one of them, and that in withholding such final certificate the architects did not exercise their honest judgment. The evidence also tends strongly to show that the appellee substantially complied with its contract for the furnishing of the material and performance of the work thereunder, and that appellants accepted the same as a substantial compliance with the contract. In this regard the verdict of the jury cannot be said to be without support, and we think the case was properly submitted to the jury under the evidence and on the common counts.

JSText, appellants’ counsel claim that the verdict and special findings of the jury are not supported by the evidence. In this regard counsel make numerous claims as to the details of the evidence, which we will not attempt to follow. They relate in the main to alleged delay on the part of appellee in carrying out the contract, and its alleged failure to perform the contract, in that on the second and third floors and the rear part of the first floor of the different buildings, the interior finish, as it is claimed, was “knockdown” work, whereas it should have been, under the contract, “ cabinet ” work.

It should be noted that under the contract appellee was to do the work and furnish the material in question under the direction and to the satisfaction of Peabody & Beauley, architects, the work to be done being that mentioned in the specifications and shown on the drawings, which were made a part and illustrative of the contract, and that “ all cabinet work, including all mill work except for exterior.” was to be furnished, installed, finished and varnished complete; also the architect was to furnish the contractor such further drawings or explanations as might be necessary to detail and illustrate the work to be done; also that no alterations should be made in the work shown by the drawings and specifications except upon written order of the architect; that if the contractor at any time refused or neglected to supply sufficient skilled workmen or materials of proper quality, or failed in any respect to prosecute the work with promptness and diligence, such refusal or neglect or failure being certified by the architect, the owner should be at liberty, after three days notice to the contractor, to provide such labor or materials, or make good or remedy any such failure, neglect or omission of the contractor, and deduct the cost thereof from any money due to the contractor, and in such case the owner should be at liberty to terminate the contract, with other provisions as to its completion, as set out in the statement; that the contractor should “ commence work immediately and prosecute the same without delay,” and in case the contractor should be delayed by the owner for any reason, by the architect, or any other contractor employed by the owner, then the time fixed by the contract for the completion of the work should be extended for a period equivalent to the time lost by reason of any or all of said causes; and that the contract price, $22,715, should be paid to the contractor in installments as follows: “Contractor to receive eighty-five per cent of the contract price as the work progresses.” It is also provided by the specifications, that if the contractor varies therefrom in the quality of any work, the architects should be at liberty, before or after the completion of the work, to order the same removed, remade and replaced at the contractor’s expense.

Very soon after the making of the- contract, June 29, 1901, appellee entered upon its performance and completed it, as the evidence on its behalf tends to show, on the 20th day of June, 1902, and on the following day in a written communication to the architects, Peabody & Beauley, made a request for an architect’s certificate in full, less fifteen per cent to be retained under the terms of the contract. After considerable delay, and on August 6, 1902, said architects in a written communication to appellee declined to issue a final certificate. This ended all communications between the parties, and this suit was begun a few days thereafter.

The trial was had apparently upon the theory, by both parties, that it was appellee’s duty, under the provision of the contract, to “commence work immediately and prosecute the same without delay,” to complete the work within a reasonable time from the making of the contract. Appellants’ sixteenth instruction, given, is based upon this theory. The evidence on behalf of appellee in this regard is to the effect that a reasonable time within which its work under the contract could be completed was from eleven to twelve months, and that the work was commenced the next day after thé contract was made, and substantially completed within eleven months and about twenty days from the date of the contract. The evidence on behalf of appellants is that such reasonable time would have been ninety days to four months from the date of the contract. There is evidence tending to show that the work of appellee was delayed by the architects, the defendants and their contractors for different reasons, mainly because of the failure of the plastering contractor to complete his work so that the appellee’s work could proceed. The specifications have a provision that no finished floor should be laid before the plastering was thoroughly dry, and no finished woodwork should be even brought to the building before the plastering was completed. The plastering was not completed until about February 18, 1902, as is shown by a letter of the architects of that date. There is also evidence tending to show that appellee did not make the progress with its work that it should have done for several reasons, the principal ones being that in the fall of 1901 it moved its factory from the south to the west side of Chicago, and because it did not employ upon the work a sufficient number of men.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kleinschnittger v. Dorsey
152 Ill. App. 598 (Appellate Court of Illinois, 1910)

Cite This Page — Counsel Stack

Bluebook (online)
116 Ill. App. 159, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hart-v-carsley-manufacturing-co-illappct-1904.