Indianapolis Northern Traction Co. v. Brennan

87 N.E. 215, 174 Ind. 1, 1909 Ind. LEXIS 174
CourtIndiana Supreme Court
DecidedFebruary 18, 1909
DocketNo. 21,010
StatusPublished
Cited by50 cases

This text of 87 N.E. 215 (Indianapolis Northern Traction Co. v. Brennan) is published on Counsel Stack Legal Research, covering Indiana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Indianapolis Northern Traction Co. v. Brennan, 87 N.E. 215, 174 Ind. 1, 1909 Ind. LEXIS 174 (Ind. 1909).

Opinions

Jordan, C. J.

Appellees James J. Brennan and Arthur B. Hogue, as plaintiffs below, commenced this suit to recover a money judgment and to enforce a lien against appellant Indianapolis Northern Traction Company which is alleged to be a railroad company duly incorporated and organized under the laws of this State for the purpose of constructing and operating an electric railroad extending from the city of Indianapolis, through several intervening counties, to the city of Peru, with certain lateral lines extending from the city of Kokomo, Howard county, to the city of Logansport, Cass county, and also for constructing and operating other electric traction lines from the city of Anderson, and embracing a series of other cities and towns, as mentioned in the amended complaint filed by the aforesaid parties.

The complaint is based on a working contract executed by the Indianapolis Northern Traction Company and the firm of Brennan & Nelson, contractors. By this contract that firm agreed to install and to complete what is denom[5]*5mated as the over-head construction of the railroad in question along the portion of appellant’s line that extends from the city of Tipton to the city of Logansport. This work consists of placing poles, trolley wires and also other wires for the proper transmission of electricity as a motive power, together with all the equipment connected therewith. At the time this suit was commenced, Brennan & Hogue had acquired and succeeded to whatever rights the firm of Brennan & Nelson originally had under the contract in question. Brennan & Hogue alleged that there was due to them on the contract in suit $15,000. This included certain extra work and labor mentioned in the complaint, and they demanded judgment for that amount, together with a foreclosure of a mechanic’s lien, notice of which having previously been filed, as required by law, in the recorder’s office of the several counties through which the road extended. Other persons, in addition to appellant railroad company, were made codefendants to answer in respect to their several interests in the lien against the railroad property involved. Among these parties was appellee Jacob N. Bick. He appeared to the suit, and on September 16, 1904, filed a cross-complaint, consisting of three paragraphs, to which cross-complaint plaintiffs Brennan & Hogue and all of Bick’s codefendants were made cross-defendants. Bick was the contractor for the construction of the grade of the railroad in question under two working contracts with the Indianapolis Northern Traction Company. One of these contracts bore date of December 6, 1902, and included that part of the road’s grade designated as section 1, station 20, to section 16, station 980. This part extended from a point near the city of Kokomo to the city of Peru. The other contract, known as number two, bore date of March 1, 1903, and covered that part of the road between points mentioned as section station 1,100 and section station 1,740, all in Hamilton eounty, Indiana. Bick, by his cross-complaint, sought to recover a remainder alleged to be due to him from [6]*6appellant Indianapolis Northern Traction Company, under contract for the construction of the railroad bridge, as well as other damages alleged to have been sustained by him. He also sought to foreclose a mechanic’s lien to secure the payment of the amount due to him.

It will lie noted that the suit was in two branches — one branch based on the complaint of Brennan & Hogue and the other founded upon the cross-complaint of Bick. Under the issues joined the two branches were tried together. The cause was submitted to the court for trial and a general finding was made, there being no request by either party for a special finding. Upon evidence given in the cause, the court found that appellees Brennan & Hogue should recover upon their complaint against the Indianapolis Northern Traction Company the sum of $5,044.88, and further found that they were entitled to be allowed the sum of $1,200 for attorney’s fees — in the aggregate $6,244.88, and that this amount was a lien upon the property described in the complaint, and a foreclosure of the lien was decreed. On the issues joined upon the cross-complaint of appellee Bick, the court found that said cross-complainant was entitled to recover from the Indianapolis Northern Traction Company the sum of $57,969.02, together with attorneys’ fees, making a total amount of $61,969.02. Of the total amount awarded in favor of Bick, the court found that he was entitled to hold and enfroce a lien to the amount of only $52,539.34 upon the property described in the cross-complaint, and that he was entitled to a foreclosure in payment of said sum of $52,539.34, but denied his right to a lien upon the remainder’, $9,429.68. Over a separate motion for a new trial by the Indianapolis Northern Traction Company, wherein it assigned statutory grounds and other reasons, the court entered its decree against said traction company in favor of the respective appellees. To review this decree appellants prosecute this appeal. The Indianapolis Northern Traction [7]*7Company, separate and apart from its codefendants, assigns errors.

The two branches of the case herein may be said to present two questions in common with each other: (1) Whether, under the statute of the State of Indiana, appellees Brennan & Hogue and Bick could acquire any lien upon appellant company’s electric railroad. (2) Whether we will yield to the contention of counsel for said appellant, and weigh conflicting evidence given at the trial upon the issues tendered in each branch of the case.

We here state, in substance, what is averred in the three paragraphs of the amended complaint of Brennan & Hogue on which their branch of the case was tried. The first paragraph discloses that, in order for said contractors successfully to prosecute the work undertaken by them, it was necessary that the railroad company should have all poles and overhead material on hand ready for use and the grade prepared not later than March, 1903; that immediately after entering upon the performance of their contract these plaintiffs arranged to begin work on or before the aforesaid month of March, and so notified the company; that the latter did not however have its poles, grades and other material in condition for said contractors to proceed until about the first of May, 1903, at which time they were notified to have their men at work on the job; that although said contractors complied promptly with the request of the company to begin work, they were constantly impeded, hindered and interfered with in the performance of their contract by reason of the failure of the company to furnish the necessary poles and materials at the storehouse agreed upon, and by reason of the facts that the grade was not finished and that the company’s engineer capriciously required the work to be reconstructed after it had been completed in a proper manner; that because of the incomplete condition of the grade, absence of stakes, and other alleged failures on the part of the traction company to put its property in condi[8]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Premier Investments v. Suites of America, Inc.
644 N.E.2d 124 (Indiana Supreme Court, 1994)
Johnson v. Taylor Bldg. Corp.
371 N.E.2d 404 (Indiana Court of Appeals, 1978)
Johnson v. Taylor Building Corp.
371 N.E.2d 404 (Indiana Court of Appeals, 1977)
Spangler v. United States Rubber Co.
183 N.E.2d 212 (Indiana Court of Appeals, 1962)
Studer v. Rasmussen
344 P.2d 990 (Wyoming Supreme Court, 1959)
Buckler v. Hood River County
341 P.2d 555 (Oregon Supreme Court, 1959)
Hayworth v. Bromwell
158 N.E.2d 285 (Indiana Supreme Court, 1959)
People v. Sacks
2 Misc. 2d 201 (New York City Magistrates' Court, 1956)
Brady v. Central Excavators, Inc.
25 N.W.2d 630 (Michigan Supreme Court, 1947)
Sahutsky v. E. G. Budd Mfg. Co.
55 Pa. D. & C. 466 (Philadelphia County Court of Common Pleas, 1945)
Beeson v. Overpeck
44 N.E.2d 195 (Indiana Court of Appeals, 1942)
George v. Massey Harris Co.
34 N.E.2d 956 (Indiana Court of Appeals, 1941)
Byrne v. Bellingham Consolidated School District No. 301
108 P.2d 791 (Washington Supreme Court, 1941)
Material Service Corp. v. School City of Hammond
116 F.2d 98 (Seventh Circuit, 1940)
Morley v. McCaskey
1928 OK 604 (Supreme Court of Oklahoma, 1928)
Baker v. Multnomah County
246 P. 352 (Oregon Supreme Court, 1926)
Feldschau v. Clatsop County
244 P. 528 (Oregon Supreme Court, 1926)
Oliver, Auditor v. State, Ex Rel.
144 N.E. 612 (Indiana Supreme Court, 1924)
Millett v. Aetna Trust & Savings Co.
122 N.E. 344 (Indiana Court of Appeals, 1919)
Sweeney v. Jackson County
178 P. 365 (Oregon Supreme Court, 1919)

Cite This Page — Counsel Stack

Bluebook (online)
87 N.E. 215, 174 Ind. 1, 1909 Ind. LEXIS 174, Counsel Stack Legal Research, https://law.counselstack.com/opinion/indianapolis-northern-traction-co-v-brennan-ind-1909.