Material Service Corp. v. School City of Hammond

116 F.2d 98, 1940 U.S. App. LEXIS 2569
CourtCourt of Appeals for the Seventh Circuit
DecidedNovember 4, 1940
DocketNos. 7246, 7247
StatusPublished

This text of 116 F.2d 98 (Material Service Corp. v. School City of Hammond) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Material Service Corp. v. School City of Hammond, 116 F.2d 98, 1940 U.S. App. LEXIS 2569 (7th Cir. 1940).

Opinion

BRIGGLE, District Judge.

In January, 1938, the E. W. Sproul Construction Company, an Illinois corporation, brought two suits in the District Court against the School City of Hammond, Indiana, and its Board of Trustees to recover balances claimed to be due under separate contracts for the erection of two school buildings, for damages and extras occasioned by delays. On October 1, 1938, the Material Service Corporation, an Illinois corporation, stepped into the shoes of*Sproul by an assignment from Sproul to it of all its claims'against defendant. The first case grew out of a contract for the construction of the Morton School and the second, a similar contract for the construction of the Edison School, both in the City of Hammond. Plaintiff recovered a judgment in the first case for $24,462.14, and in the second case for $25,155.32. From these judgments defendants appeal.

The two school houses were erected under separate contracts containing substantially identical provisions. The complaints and answers and special findings and conclusions of law in each case are substantially identical, and it is agreed by the parties that the cases are to be heard together and the decision in one will control the decision in the other.' Sproul and its assignee will be referred to as the contractor or plaintiff, and, unless otherwise specifically indicated this opinion will refer to the Morton contract. Defendant in the trial below filed a counterclaim but the same has since been abandoned, and it is conceded that the recovery under conclusions of law 1, 2 and 5 of the District Court should stand. Conclusions of law, numbered 3 and 4, present the only questions for review. Conclusion 3 permits recovery of $11,854.86 for furnishing temporary heat during construction, for certain damages due to the failure of defendant to supply proper heat, and for damages occasioned by delay in completion of the permanent heating plant. Conclusion 4 permits recovery of $2,539.61, as damages for delay of the defendant in obtaining confirming orders from the Federal Emergency Administration of Public Works for the performance of certain optional work known as alternates “L” and “M”.

The work contemplated was divided into six branches — the first was the general construction which included all work except electrical work, plumbing, heating, ventilating, and automatic temperature control. Sproul was the general contractor, and we are here concerned only with its contract and that of the heating contractor. Under its bid the general contractor submitted a figure for the building complete and also gave separate figures for certain alternate work. The alternate work was designated as alternates “A,” “B,” “F,” “H,” “L,” and “M,” but we shall have occasion to refer only, to alternates “L” and “M,” as they alone are the subject of controversy. The contractor’s total bid was $414;680, which figure included the various alternates aggregating $44,065. The contract was let to Sproul for thé net figure of $370,615, which covered all general construction excepting the alternates. Under the contract the board had the right within one hundred and twenty days from the day of its execution to require the contractor to construct the extra work provided by the alternates, by serving notice upon the contractor. The board did, in fact, exercise this option as to alternates “L” and “M” and notified the contractor to proceed with the construction of the work provided by alternate “L” at the bid of $15,868 and that provided for by alternate “M” at the bid of $6,495. It was the delay in gaining the approval of the Federal Emergency Administration in regard to these two alternates that brought about plaintiff’s claim for damages represented by the District Court’s conclusion of law 4.

Temporary Heat, Conclusion of Law No. 3.

The permanent heating system was to be installed by the heating contractor whose contract among other things provided as follows:

“Time. The contract shall be sufficiently completed that temporary heat can be used, if necessary during and after plastering. The entire contract shall be completed on or before the time of completion of the building structure.”
“Temporary Connections. The Contractor shall erect and connect all direct radiators temporarily prior to the permanent setting, as a part of the contract, without extra compensation, when so ordered by the Architect. Temporary valves shall be furnished for such temporary connections, [101]*101as the valves for permanent use may not be used for temporary setting.”
“Heating During Construction. See general conditions.”

The general specifications were for the guidance of all contractors and, so far as applicable, became part of the contract of each. Such general specifications contained the following in reference to temporary heat during construction:

“Temporary Heat. The permanent heating plant shall be used to furnish heating during construction, at such times as the Architect may require.
“If impractical, in the judgment of the Architect, to use the permanent heating plant, other satisfactory, approved equipment that will in no way cause damage to finished work, shall be furnished and operated by the Contractor.
“It must be fully understood that at no time shall the temperature be allowed to fall below fifty (50) degrees Fahrenheit in any portion of the building which has received the first coat of plastering.
>Jt sfc sfc ^
“ ‘Contractor and Contractors’ refers to and indicates the party or parties contracting to perform the work to be done in pursuance of this contract and these specifications.”

The general specifications also contained the following provision applicable to the general contractor:

“Protection Against Damage. The Contractor will be held responsible for the protection of all work and materials, furnished by him, from damage and loss resulting from carelessness or other causes until the entire work is completed and accepted. Any damaged work or materials will be condemned and rejected, and shall be removed from the premises as hereinafter specified.
“The Contractor shall 'furnish and erect his own storage sheds, platforms, etc., for the protection of work and materials.
“All necessary precautions shall be taken to protect inflammable materials from fire at all times.”

The contract also provided that the decision of the Architect as to the proper interpretation of the drawings and specifications should be final and further provided that if the Contractor should disregard the instructions of the Architect, or otherwise be guilty of a substantial violation of the Contract, the Board under direction of the Architect might terminate the employment of the Contractor, take possession of the premises, materials, tools, and appliances and finish the work by whatever method it deemed expedient.

It is from the confusion arising in the interpretation of these provisions of the heating contract and the general contract that the controversy in reference to temporary heat has arisen.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Yuhaszv v. United States
109 F.2d 467 (Seventh Circuit, 1940)
Louisville, Evansville & St. Louis Railway Co. v. Donnegan
12 N.E. 153 (Indiana Supreme Court, 1887)
McCoy v. Able
30 N.E. 528 (Indiana Supreme Court, 1892)
Indianapolis Northern Traction Co. v. Brennan
87 N.E. 215 (Indiana Supreme Court, 1909)

Cite This Page — Counsel Stack

Bluebook (online)
116 F.2d 98, 1940 U.S. App. LEXIS 2569, Counsel Stack Legal Research, https://law.counselstack.com/opinion/material-service-corp-v-school-city-of-hammond-ca7-1940.