Barreira Land. Mason. v. Frontier In., No. Cv97 034 69 08 (Dec. 6, 2000)

2000 Conn. Super. Ct. 15914, 29 Conn. L. Rptr. 188
CourtConnecticut Superior Court
DecidedDecember 6, 2000
DocketNo. CV97 034 69 08
StatusUnpublished

This text of 2000 Conn. Super. Ct. 15914 (Barreira Land. Mason. v. Frontier In., No. Cv97 034 69 08 (Dec. 6, 2000)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Barreira Land. Mason. v. Frontier In., No. Cv97 034 69 08 (Dec. 6, 2000), 2000 Conn. Super. Ct. 15914, 29 Conn. L. Rptr. 188 (Colo. Ct. App. 2000).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]

MEMORANDUM OF DECISION
In this action by a subcontractor to recover for sums due under two separate municipal construction contracts, the plaintiff makes claim against the prime contractor (hereinafter "the contractor") for breach of contract and unjust enrichment and against the surety under each payment bond issued to support the contract pursuant to General Statutes. §49-41a and § 49-42, known as the "Little Miller Act".1

The dispositive issue in this case grows out of the proper interpretation of the terms of § 49-42. The plaintiff alleges (a) that it gave notice of its claim to the contractor and to the surety in accordance with the requirements of § 49-42(a), which the contractor denies; and (b) that the surety did not give notice of denial of liability or pay any portion of the claim as mandated by the statute.

The facts necessary for a resolution of these issues will be set forth as each issue is discussed.

I. Notice to Surety By Subcontractor CT Page 15915

On March 4, 1997, within the time specified in § 49-42(a) the plaintiff gave notice of its claim to the surety by sending individual letters by certified mail, return receipt requested, stating the amount of its claim for the balance due under each of the two contracts, i.e. $14,467.54 for the North Street Elementary School job, and $5,761.99 for the Old Greenwich Elementary School job. Neither defendant disputes the legal sufficiency of the contents of these letters. The surety acknowledged receipt of the notices of claim through its letter dated March 27, 1997 but the contractor denies ever having received copies of the notices from the subcontractor/plaintiff.

The letters in question each contain a legend at the bottom which indicates that copies were sent to ten different parties, including the contractor. The plaintiff, however, produced return receipts for certified mailing (green cards) for only four of the ten to whom copies were mailed, not including the contractor. Nevertheless, the plaintiff's principal, Mr. Jorge Barreira testified that he had received signed return receipts from the contractor but mislaid them and has been unable to locate them. The court credits Mr. Barreira's testimony not only because it finds it credible but also because (i) he produced the other return receipts which correspond with the names of the persons shown on the cc legend on the letter; (ii) the contractor's name was listed on the top of the list of ten, (iii) he produced each of the two return receipts from one of the ten, Fletcher Thompson Architects, and (iv) each of the receipts was dated either March 13 or 14, 1997.

Federal precedents make compliance with the statutory notice requirement of § 49-42(a) a precondition to the plaintiff's recovery on the surety bond. American Masons' Supply Co. v. F. W. Brown Co.,174 Conn. 219, 224 (1978). In Okee Industries v. National Grain MutualInsurance Co., 225 Conn. 367, 371 (1993) our Supreme Court hypothesized compliance with the notice requirement had the subcontractor "appended a legend indicating that a copy [of the notice] was being sent to the contractor and had then proceeded to forward a copy as indicated." In fact, the contractor in that case sent notice to the contractor by regular mail at a later date in a different letter from that, which notified the surety. The court deemed this notice to constitute compliance, though not technically and strictly adhering to the letter of the statute. Likewise, this court holds that the plaintiff complied with the contractor-notice requirement of the statute.

II. Notice to Subcontractor by Surety

As stated above, the surety does not deny receiving letters from the subcontractor which asserted claims under both the North Street and Old Greenwich contracts. Likewise, there is no dispute that the surety CT Page 15916 received these letters on March 17, 1997 and sent its notice of denial to the subcontractor on June 26, 1997, clearly more than the 90 days prescribed by the statute. The plaintiff argues that the surety's failure to pay or deny the claim by written notice as required by the statute entitles it to judgment. The defendant surety, on the other hand, argues that the 90 days did not begin to run until the plaintiff completed and filed with the defendant a proof of claim under oath which would then permit it to commence its investigation.

The relevant portion of § 49-42 provides as follows:

The notice of claim shall state with substantial accuracy the amount claimed and the name of the party for whom the work was performed or to whom the materials were supplied, and shall provide a detailed description of the bonded project for which the work or materials were provided. If the content of notice prepared in accordance with subsection (b) of section 49-41a complies with the requirements of this action, a copy of such notice, served within one hundred eighty days of the payment date provided for in section (a)of section 49-41a upon the surety that issued the bond and upon the contractor named as principal in the bond, shall satisfy the notice requirements of this section.

Within ninety days after service of the notice of claim, the surety shall make payment under the bond and satisfy the claim, or any portion of the claim which is not subject to a good faith dispute. and shall serve a notice on the claimant denying liability for any unpaid portion of the claim. The notices required under this action shall be served by registered or certified mail, postage prepaid in envelopes addressed to any office at which the surety, principal or claimant conducts his business, or in any manner in which civil process may be served. If the surety denies liability on the claim, or any portion thereof, the claimant may bring action upon the payment bond in the Superior Court for such sums and prosecute the action to final execution and judgment. (Emphasis added.)

Once again, relying on federal precedent construing the federal Miller Act, our Supreme Court has adopted a "substantial performance rather than a strict compliance test when construing statutory notice requirements CT Page 15917 dealing with the service of notice and with the contents of notice." OkeeIndustries v. National Grain Mutual Insurance Co., supra at 375. An examination of both notices of claim, reveals that they state with substantial accuracy the amount claimed, the name of the party for whom the work was performed and a detailed description of the bonded project. Nothing more is required by the statute. There is no authority in the statute or in the case law for a surety to delay commencement of the 90 day claim assessment period until receipt of a proof of claim under oath which it has designed for its own administrative purpose.

The next issue is whether the failure of the surety to act upon the subcontractor's notice of claim within the prescribed 90 ninety period is mandatory or directory.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jones v. Civil Service Commission
400 A.2d 721 (Supreme Court of Connecticut, 1978)
American Masons' Supply Co. v. F. W. Brown Co.
384 A.2d 378 (Supreme Court of Connecticut, 1978)
Premier Roofing Co. v. Insurance Co. of N. A., No. 31 24 38 (Mar. 3, 1995)
1995 Conn. Super. Ct. 1933 (Connecticut Superior Court, 1995)
Zoning Board of Appeals v. Freedom of Information Commission
503 A.2d 1161 (Supreme Court of Connecticut, 1986)
Hartford Principals' & Supervisors' Ass'n v. Shedd
522 A.2d 264 (Supreme Court of Connecticut, 1987)
Okee Industries, Inc. v. National Grange Mutual Insurance
623 A.2d 483 (Supreme Court of Connecticut, 1993)
Bridgeport Hospital v. Commission on Human Rights & Opportunities
653 A.2d 782 (Supreme Court of Connecticut, 1995)
United Illuminating Co. v. City of New Haven
692 A.2d 742 (Supreme Court of Connecticut, 1997)
Office of Consumer Counsel v. Department of Public Utility Control
742 A.2d 1257 (Supreme Court of Connecticut, 2000)
Oxford Tire Supply, Inc. v. Commissioner of Revenue Services
755 A.2d 850 (Supreme Court of Connecticut, 2000)
Willoughby v. City of New Haven
757 A.2d 1083 (Supreme Court of Connecticut, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
2000 Conn. Super. Ct. 15914, 29 Conn. L. Rptr. 188, Counsel Stack Legal Research, https://law.counselstack.com/opinion/barreira-land-mason-v-frontier-in-no-cv97-034-69-08-dec-6-2000-connsuperct-2000.