Barreira Landscaping & Masonry v. Frontier Insurance

779 A.2d 244, 47 Conn. Super. Ct. 99, 47 Conn. Supp. 99, 2000 Conn. Super. LEXIS 3410
CourtConnecticut Superior Court
DecidedDecember 6, 2000
DocketFile No. CV970346908S.
StatusPublished
Cited by3 cases

This text of 779 A.2d 244 (Barreira Landscaping & Masonry v. Frontier Insurance) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Barreira Landscaping & Masonry v. Frontier Insurance, 779 A.2d 244, 47 Conn. Super. Ct. 99, 47 Conn. Supp. 99, 2000 Conn. Super. LEXIS 3410 (Colo. Ct. App. 2000).

Opinion

I

INTRODUCTION

MOTTOLESE, J.

In this action by a subcontractor to recover for sums due under two separate municipal construction contracts, the plaintiff, Barreira Landscaping and Masonry, a subcontractor, makes two claims. The first is against the defendant general contractor, Wright Brothers Builders, Inc. (contractor), for breach of contract and unjust enrichment. The second is against the defendant Frontier Insurance Company (surety or defendant surety) under each payment bond issued to support the contract pursuant to General Statutes §§ 49-41a and 49-42, known as the “Little Miller Act.” 2

The dispositive issue in the present case grows out of the proper interpretation of the terms of § 49-42. The plaintiff first alleges that it gave notice of its claim to the contractor and to the surety in accordance with the requirements of § 49-42 (a), which the contractor denies. Second, the plaintiff alleges that the surety did *101 not give notice of denial of liability or failure to pay any portion of the claim as mandated by the statute.

The facts necessary for a resolution of these issues will be set forth as each issue is discussed.

II

NOTICE TO SURETY BY THE PLAINTIFF

On March 4, 1997, within the time specified in § 49-42 (a), the plaintiff gave notice of its claim to the surety by sending individual letters by certified mail, return receipt requested, stating the amount of its claim for the balance due under each of the two contracts, i.e., $14,467.54 for the North Street Elementary School job, and $5761.99 for the Old Greenwich Elementary School job. Neither defendant disputes the legal sufficiency of the contents of these letters. The surety acknowledged receipt of the notices of claim through its letter dated March 27, 1997, but the contractor denies ever having received copies of the notices from the plaintiff.

The letters in question each contain a legend at the bottom which indicates that copies were sent to ten different parties, including the contractor. The plaintiff, however, produced return receipts for certified mailing (green cards) for only four of the ten to whom copies were mailed, not including the contractor. Nevertheless, Jorge Barreira, the plaintiffs principal, testified that he had received signed return receipts from the contractor but mislaid them and has been unable to locate them. The court credits Barreira’s testimony not only because it finds it credible, but also because of four additional reasons. First, he produced the other return receipts, which correspond with the names of the persons shown on the “cc” legend on the letter. Second, the contractor’s name was listed on the top of the list of ten. Third, he produced each of the two *102 return receipts from one of the ten, Fletcher Thompson Architects. Fourth, and finally, each of the receipts was dated either March 13 or 14, 1997.

Federal precedents make compliance with the statutory notice requirement of § 49-42 (a) a precondition to the plaintiffs recovery on the surety bond. American Masons’ Supply Co. v. F. W. Brown & Co., 174 Conn. 219, 224, 384 A.2d 378 (1978). In Okee Industries, Inc. v. National Grain Mutual Ins. Co., 225 Conn. 367, 371, 623 A.2d 483 (1993), our Supreme Court hypothesized compliance with the notice requirement had the subcontractor “appended a legend indicating that a copy [of the notice] was being sent to the general contractor, and had then proceeded to forward a copy as indicated.” In fact, the subcontractor in that case sent notice to the general contractor by regular mail at a later date in a different letter from that which notified the surety. The court deemed this notice to constitute compliance, though not technically and strictly adhering to the letter of the statute. Id., 376. Likewise, this court holds that the plaintiff in the present case complied with the contractor notice requirement of the statute.

III

NOTICE TO THE PLAINTIFF BY SURETY

As stated previously, the defendant surety does not deny receiving letters from the plaintiff which asserted claims under both the North Street and Old Greenwich contracts. Likewise, there is no dispute that the surety received these letters on March 17, 1997, and sent its notice of denial to the plaintiff on June 26,1997, clearly more than the ninety days prescribed by the statute. The plaintiff argues that the surety’s failure to pay or deny the claim by written notice, as required by the statute, entitles it to judgment. The defendant surety, on the other hand, argues that the ninety days did not *103 begin to ran until the plaintiff completed and filed with that defendant a proof of claim under oath which would then permit it to commence its investigation.

Section 49-42 (a) provides in pertinent part: “The notice of claim shall state with substantial accuracy the amount claimed and the name of the party for whom the work was performed or to whom the materials were supplied, and shall provide a detailed description of the bonded project for which the work or materials were provided. If the content of a notice prepared in accordance with subsection (b) of section 49-41a complies with the requirements of this section, a copy of such notice, served within one hundred eighty days of the payment date provided for in subsection (a) of section 49-41a upon the surety that issued the bond and upon the contractor named as principal in the bond, shall satisfy the notice requirements of this section. Within ninety days after service of the notice of claim, the surety shall make payment under the bond and satisfy the claim, or any portion of the claim which is not subject to a good faith dispute, and shall serve a notice on the claimant denying liability for any unpaid portion of the claim. The notices required under this section shall be served by registered or certified mail, postage prepaid in envelopes addressed to any office at which the surety, principal or claimant conducts his business, or in any manner in which civil process may be served. If the surety denies liability on the claim, or any portion thereof, the claimant may bring action upon the payment bond in the Superior Court for such sums and prosecute the action to final execution and judgment.” (Emphasis added.)

Once again, relying on federal precedent construing the federal Miller Act, our Supreme Court has adopted a “substantial performance rather than [a] strict compliance [test] when construing statutory notice requirements dealing with the service of notice and with the *104 contents of notice.” Okee Industries, Inc. v. National Grain Mutual Ins. Co., supra, 225 Conn 375. An examination of both notices of claim, reveals that they state with substantial accuracy the amount claimed, the name of the party for whom the work was performed and a detailed description of the bonded project.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Connecticut Elec. v. Fidelity Guaranty, No. Cv00-0274893-S (Oct. 24, 2002)
2002 Conn. Super. Ct. 13633 (Connecticut Superior Court, 2002)
Millgard Corp. v. White Oak Corp.
224 F. Supp. 2d 425 (D. Connecticut, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
779 A.2d 244, 47 Conn. Super. Ct. 99, 47 Conn. Supp. 99, 2000 Conn. Super. LEXIS 3410, Counsel Stack Legal Research, https://law.counselstack.com/opinion/barreira-landscaping-masonry-v-frontier-insurance-connsuperct-2000.