Summit Crane Co. v. Continental Metalcraft, No. Cv 93035564s (Sep. 26, 1996)

1996 Conn. Super. Ct. 5613, 17 Conn. L. Rptr. 651
CourtConnecticut Superior Court
DecidedSeptember 26, 1996
DocketNo. CV 93035564S
StatusUnpublished
Cited by1 cases

This text of 1996 Conn. Super. Ct. 5613 (Summit Crane Co. v. Continental Metalcraft, No. Cv 93035564s (Sep. 26, 1996)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Summit Crane Co. v. Continental Metalcraft, No. Cv 93035564s (Sep. 26, 1996), 1996 Conn. Super. Ct. 5613, 17 Conn. L. Rptr. 651 (Colo. Ct. App. 1996).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.] Memorandum Filed September 26, 1996 In this case the plaintiff, Summit Crane Company, supplied construction equipment for a state public works project, pursuant to the state contract a payment bond was issued. Rights under such a bond are determined by an analysis of § 49-42 of the general statutes Suffolk Construction Company was the general contractor on the job and Seaboard Surety Company issued a payment bond under General Statutes § 49-41. CT Page 5614

Summit Crane claims it was not paid for having supplied equipment to the job and has brought suit against Suffolk and Seaboard Surety in the third count. The latter two companies have moved for summary judgment and argue that Summit Crane cannot make a claim under the payment bond.

The tests to be applied on a motion for summary judgment are well known. If there is a genuine issue of material fact the court cannot resolve it because the nonmoving party is entitled to a trial for the resolution of such issues.

Here, at least from the court's perspective, the facts are not so much in dispute but the proper categorization and construction that should be given to the facts. As mentioned the defendants' claim § 49-42 does not provide the plaintiff with protection and they also claim that in any event Summit Crane failed to meet the notice requirement of the statute.

The first question presented is whether § 49-42, as it read when the plaintiff provided equipment to this job in the fall of 1992, can be said to provide protection to the plaintiff.

Our Supreme Court on several occasions has said that we should look for guidance on payment bond questions to federal court interpretations of the so-called Miller Act. Our act was modeled on the Miller Act and the wording of our act is borrowed from the federal act. Under these circumstances, it would only create confusion in the local construction industry if state and federal courts gave different interpretations to their respective payment bond acts; for cases saying federal precedent should be looked to by our courts, see Pittsburgh Plate Glass Co. v. Dahm,159 Conn. 563, 567 (1970), International Harvester Co. v. L.G.Defelice Sons, Inc., 151 Conn. 325, 331; American Masons'Supply Co. v. F. W. Brown Co., 174 Conn. 19, 226 (1978), held that §§ 49-41 and 49-42 of the General Statutes were intended by the legislature "to operate in general conformity with the federal statute, popularly known as the Miller Act, (40 U.S.C §§ 270a-270e)."

It is true, as the plaintiff claims, that it has been held that our payment bond statute should be given a liberal interpretation in light of its ameliorative purpose of protecting people and companies who actually supply labor and material to a job site and do not get paid. CT Page 5615

But the federal courts have held that under the Miller Act, Congress "intended the scope of protection of a payment bond to extend no further than to sub-subcontractors." JW Bateson Co. v.Board of Trustees, 434 U.S. 586, 591 (1977). This has been the law for over 50 years, see McEvoy Co. v. United States, 322 U.S. 102 at pp. 107-08 (1943). The Bateson court explicitly recognized its obligation "to construe the `highly remedial' Miller Act `liberally' . . . but felt constrained to give this interpretation by the language of the act and its conclusion that the word `subcontractor' has to be limited in meaning to one who contracts with a prime contractor." Id. At 434 U.S. p. 594.

Thus, the court cannot accept the plaintiff's argument that this court can refuse to apply the analysis used in Bateson andMcEvoy on the notion that "the tier analysis used by some courts is unfortunate." Our court explicitly followed McEvoy and held that the protections of our act only applied to suppliers of material that have a direct contractual relationship with a subcontractor, that is sub-subcontractors, and not suppliers to the latter. American Masons' Supply Co. v. FW Brown Co., 174 Conn. At pp. 226-27. The court at page 227 gave its reasoning for such a position:

The purpose of limiting the right of action upon the bond to only those having a direct contractual relationship with a subcontractor is to prevent the imposition of unlimited liability upon the prime contractor and his (sic) surety . . . While it is easy for the prime contractor to secure himself against by requiring the relatively few subcontractors to provide some type of security for the payment of those who contract directly with these subcontractors. "This method of protection is generally inadequate to cope with remote and undetermined liabilities incurred by an ordinary materialman who may be a manufacturer, a wholesaler or retailer."

The cases referred to in its brief by the plaintiff do not differ from this analysis but generally recognize that payment bonds protect sub-subcontractors; in other words, they adopt a so-called tier analysis. Tremack Co. v. Homestead Paving,582 So.2d 26 (Fla. 1991); Mai Steel Service v. Blake Construction Co.,981 F.2d 414 (CA9, 1992); U.S. for Use of Superior Insulation v.McKee, Inc., 702 F. Sup. 1298 (ND Tex, 1988). CT Page 5616

The question then becomes was the plaintiff a sub-contractor; did it supply its construction and crane services to a subcontractor? A reading of the First Count of the complaint directed against Continental Metalcraft and the Second Count directed against RS Welding, Inc., obviously admissions by the plaintiff, make clear that Suffolk was the principal contractor. RS Welding was a subcontractor, and Continental Metalcraft was a sub-subcontractor — in other words, "The plaintiff supplied services to the defendant, Continental Metalcraft. Inc., a subcontractor on the project for the benefit of the defendant, RS Welding" (par 5 of Second Count), also see Ex. B, attached to defendant's motion, from the plaintiff's general manager which sets forth in a letter to the surety the nature of the plaintiff's claim; the "Narrative" attached to the letter indicates the plaintiff was a so-called third tier supplier — it delivered its services to a sub-subcontractor, such a letter and the attached Narrative can be considered, along with the pleading to be an admission.

But the plaintiff maintains that in fact Continental Metalcraft is a subcontractor, and points to interrogatories submitted by the defendant.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Northeast W. Sys. v. Ct. Abatement Techs., No. Cv 98-0419724 (Jun. 28, 1999)
1999 Conn. Super. Ct. 7862 (Connecticut Superior Court, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
1996 Conn. Super. Ct. 5613, 17 Conn. L. Rptr. 651, Counsel Stack Legal Research, https://law.counselstack.com/opinion/summit-crane-co-v-continental-metalcraft-no-cv-93035564s-sep-26-connsuperct-1996.