Wickes Manufacturing Co. v. Currier Electric Co.

596 A.2d 1331, 25 Conn. App. 751, 1991 Conn. App. LEXIS 354
CourtConnecticut Appellate Court
DecidedSeptember 17, 1991
Docket9194
StatusPublished
Cited by19 cases

This text of 596 A.2d 1331 (Wickes Manufacturing Co. v. Currier Electric Co.) is published on Counsel Stack Legal Research, covering Connecticut Appellate Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wickes Manufacturing Co. v. Currier Electric Co., 596 A.2d 1331, 25 Conn. App. 751, 1991 Conn. App. LEXIS 354 (Colo. Ct. App. 1991).

Opinion

Daly, J.

The plaintiffs predecessor, Eagle Signal Corporation (Eagle), instituted this action under General Statutes § 49-421 seeking reimbursement for equipment furnished to the named defendant, a general contractor (contractor) that had contracted with the state to install traffic control lights in Stamford. Also named as a defendant in this action is United States Fidelity and Guaranty Company (USF&G), which furnished a payment bond pursuant to General Statutes § 49-41.2 The trial court rendered judgment in favor of the plaintiff on its complaint for $58,184.52, plus interest and attorney’s fees, against the contractor and for the plaintiff on the contractor’s counterclaim. The trial court found in favor of USF&G on the plaintiff’s complaint and for the plaintiff on USF&G’s counterclaim. The plaintiff and the contractor have appealed.

The plaintiff appeals from the judgment rendered in favor of USF&G claiming that the trial court failed to recognize that the original contract between the plaintiff’s predecessor, Eagle, and the contractor had been modified to include turn-on services. The plaintiff further claims that the trial court incorrectly concluded that the consulting services, manuals and equipment schematics it provided were not labor and materials [754]*754pursuant to General Statutes § 49-42 (b). The contractor cross appeals3 claiming that the trial court improperly granted the plaintiff’s motion permitting it to be substituted as the plaintiff in place of Eagle. USF&G adopted the contractor’s issues on appeal.

The trial court found the following facts. On March 30,1978, the contractor entered into an agreement with the Connecticut department of transportation (DOT) to install new traffic control lights at sixteen intersections in Stamford for $512,217. USF&G furnished the bond on the contract. On January 16,1980, the contractor entered into a contract for $144,599 with Eagle to supply traffic control devices with solid state activated controllers. Eagle shipped the devices during July and August of 1980, and billed the contractor on August 25,1980, for the agreed price. Some problems occurred with the devices, and Eagle corrected them. The DOT paid the contractor the total contract price in November of 1980 and accepted the project in March, 1982. Eagle sued the defendants for the balance due of $58,184.52.

The contractor denied owing any balance and filed a counterclaim claiming that the equipment supplied by Eagle was defective and did not conform to or function as required by the DOT specifications. The contractor claimed that it was forced to expend additional sums to complete the contract and was subject to damage claims by the DOT.

[755]*755Eagle instituted this action on January 26,1983, and USF&G claimed the action was untimely under General Statutes § 49-42 (b), which provides that “no such suit may be commenced after the expiration of one year after the day on which the last of the labor was performed or material was supplied by the claimant.” Relying on the following findings, the trial court agreed that the action was untimely. Contrary to the plaintiffs claims, there was no contractual agreement that Eagle perform turn-on services until acceptance by the DOT in March, 1982. Eagle did not have any employees on the job site after January 16, 1982. The trial court found that Eagle’s telephone discussion on January 27, 1982, plus the replacement of some defective parts, did not constitute the furnishing of labor or materials under § 49-42 (b). Likewise, the further provision of service manuals and schematics on August 20, 1982, did not constitute labor and materials under § 49-42 (b).

By motion dated April 19,1989, Wickes Manufacturing Company (Wickes) moved that it be substituted as party plaintiff. The trial court found that Eagle had been purchased in 1981 by Gulf & Western Manufacturing Company, which subsequently became Sorensen Manufacturing Company, and, on September 25, 1985, became Wickes. The trial court granted the motion finding that the action commenced in the name of Eagle was a mistake and that the substitution of Wickes was necessary for the determination of the case. The trial court rendered judgment on May 7, 1990.

I

The plaintiff first claims that the original contract did not require it to supervise the installation, start-up or DOT test compliance of the equipment but that the contract was subsequently modified to provide for [756]*756such supervision. Such a modification is known in the trade as a turn-on contract.4

“ ‘ “On appeal, it is the function of this court to determine whether the decision of the trial court is clearly erroneous. . . . This involves a two part function: where the legal conclusions of the court are challenged, we must determine whether they are legally and logically correct and whether they find support in the facts set out in the memorandum of decision; where the factual basis of the court’s decision is challenged we must determine whether the facts set out in the memorandum of decision are supported by the evidence or whether, in light of the evidence and the pleadings in the whole record, those facts are clearly erroneous.” (Emphasis added.) Pandolphe’s Auto Parts, Inc. v. Manchester, 181 Conn. 217, 221-22, 435 A.2d 24 (1980).’ ... In a case tried before a court, the trial judge is the sole arbiter of the credibility of the witnesses and the weight to be given specific testimony. ... On appeal, ‘we will give the evidence the most favorable reasonable construction in support of the verdict to which it is entitled.’ . . . ‘ “A factual finding may be rejected by this court only if it is ‘clearly erroneous.’ ”. . .’ ” (Citations omitted.) Kimberly-Clark Corporation v. Dubno, 204 Conn. 137, 153, 527 A.2d 679 (1987).

Whether a contract exists is a question of fact or a mixed question of fact and law for the court to determine. See Gianetti v. Norwalk Hospital, 211 Conn. 51, 58 n.6, 557 A.2d 1249 (1989). The existence and terms of a contract are determined from the intent of the parties. See Steeltech Building Products, Inc. v. Edward Suit Associates, Inc., 18 Conn. App. 469, 471, 559 A.2d 228 (1989). “The parties’ intentions manifested by their acts and words are essential to the court's determina[757]*757tion of whether a contract was entered into and what its terms were.” Id., 471-72. It is within the province of the trier to draw reasonable and logical inferences from the facts proven. B. Holden & J. Daly, Connecticut Evidence § 64, p. 417.

The trial court could reasonably infer that Eagle had completed the contract on August 25, 1980, when it billed the contractor for $144,559, the complete contract price, and charged interest as of that date. The contractor was paid the total contract price by the state in November of 1980.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gleason v. Durden
211 Conn. App. 416 (Connecticut Appellate Court, 2022)
Rana v. Terdjanian
46 A.3d 175 (Connecticut Appellate Court, 2012)
Lupinacci v. City of Stamford
823 A.2d 456 (Connecticut Superior Court, 2002)
Nygren, Jr. v. Steier, No. Cv00 0156706 (Jan. 10, 2001)
2001 Conn. Super. Ct. 537 (Connecticut Superior Court, 2001)
Dilieto v. County Obs. and Gyn. Gp., No. (X02) Cv97-0150435s (Jan. 27, 2000)
2000 Conn. Super. Ct. 1083 (Connecticut Superior Court, 2000)
Dilieto v. County Ob and Gyn. Group, No. (X02) Cv97-0150435s (Jan. 31, 2000)
2000 Conn. Super. Ct. 1350 (Connecticut Superior Court, 2000)
Town, Stratford v. Ifpte, Local No. 134, No. Cv99 035 99 00 (Jun. 18, 1999)
1999 Conn. Super. Ct. 8665 (Connecticut Superior Court, 1999)
Kelvin Corporation v. Foley, No. 29 22 33 (Oct. 1997)
1997 Conn. Super. Ct. 11110 (Connecticut Superior Court, 1997)
Middletown Commercial Associates Ltd. Partnership v. City of Middletown
680 A.2d 1350 (Connecticut Appellate Court, 1996)
Essex House Inc. v. Simmons, No. Cv94 0138852 (Jan. 9, 1995)
1995 Conn. Super. Ct. 831 (Connecticut Superior Court, 1995)
Sovereign Homes, Inc. v. Jones, No. Cv93 030 86 25 S (Sep. 7, 1994)
1994 Conn. Super. Ct. 8937 (Connecticut Superior Court, 1994)
Wrinn v. State
646 A.2d 869 (Connecticut Appellate Court, 1994)
Joblin v. LaBow
635 A.2d 874 (Connecticut Appellate Court, 1993)
American Masons' Bldg. Co. v. Federal Ins., No. 98272 (Jun. 21, 1993)
1993 Conn. Super. Ct. 6055-a (Connecticut Superior Court, 1993)
Investors Mortgage Co. v. Rodia
625 A.2d 833 (Connecticut Appellate Court, 1993)
Federal Deposit Insurance v. Retirement Management Group, Inc.
623 A.2d 517 (Connecticut Appellate Court, 1993)
Okee Industries, Inc. v. National Grange Mutual Insurance
623 A.2d 483 (Supreme Court of Connecticut, 1993)
Amwax Corp. v. Chadwick
612 A.2d 127 (Connecticut Appellate Court, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
596 A.2d 1331, 25 Conn. App. 751, 1991 Conn. App. LEXIS 354, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wickes-manufacturing-co-v-currier-electric-co-connappct-1991.