American Masons' Bldg. Co. v. Federal Ins., No. 98272 (Jun. 21, 1993)

1993 Conn. Super. Ct. 6055-a
CourtConnecticut Superior Court
DecidedJune 21, 1993
DocketNo. 98272
StatusUnpublished

This text of 1993 Conn. Super. Ct. 6055-a (American Masons' Bldg. Co. v. Federal Ins., No. 98272 (Jun. 21, 1993)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Masons' Bldg. Co. v. Federal Ins., No. 98272 (Jun. 21, 1993), 1993 Conn. Super. Ct. 6055-a (Colo. Ct. App. 1993).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.] MEMORANDUM OF DECISION The plaintiff, American Masons' and Building Supply Company (hereinafter "American Masons"), commenced this action for damages on a bond furnished pursuant to General Statutes 49-41 et seq. (hereinafter the "Little Miller Act"). The defendants are Vinco, Incorporated (hereinafter "Vinco"), the general contractor for the construction of a CT Page 6055-b municipal office complex for the Town of Colchester and principal on the bond, and the Federal Insurance Company, the surety who issued the Labor and Material Payment Bond for the project.

The parties stipulated to the following relevant facts:

(1) On March 10, 1989, Vinco entered into a general construction contract with the Town of Colchester.

(2) Pursuant to General Statutes 49-41, Vinco, as principal, and Federal Insurance Company, as surety, provided a labor and material payment bond.

(3) Vinco entered into various subcontracts.

(4) On March 31, 1989, Sarma CT Page 6055-c Masonry, Inc. and Vinco entered into a subcontract for the performance of certain masonry work.

(5) American Masons supplied Sarma with certain materials for this project.

(6) These materials were supplied between July 27, 1989 and September 11, 1990.

(7) American Masons supplied materials to Sarma as follows:

Invoice Number Amount Date

53977 $ 26.40 07/27/89 54477 1,345.20 08/11/89 54491 122.50 08/14/89 54958 212.00 08/29/89 CT Page 6055-d 55373 1,255.50 09/13/89 55494 412.50 09/18/89 56275 543.86 10/17/89 56355 536.18 10/19/89 56421 148.56 10/23/89 56687 470.00 10/31/89 57218 236.75 05/21/90 58476 87.50 05/29/90 63670 4.50 09/11/90

Total: $5,401.25

(8) All materials aforementioned were incorporated into the project.

(9) American Masons did not have a contractual relationship with Vinco.

(10) American Masons was a supplier to Sarma which was a subcontractor to Vinco. CT Page 6055-e

(11) American Masons did not have a contract with Sarma to supply all materials on this project.

(12) American Masons supplied the materials to Sarma on an open account basis.

(13) Each invoice for materials delivered or picked up was its own separate contract.

(14) Sarma was not obligated to purchase any or all materials from American Masons for this project.

(15) By purchasing materials from American Masons, Sarma was not obligated to purchase additional materials. CT Page 6055-f

(16) Vinco and Federal paid the plaintiff the sum of $328.75 representing invoice numbers 57218, 58476 and 63670 under an agreement that it [the payment] should not prejudice any rights of American Masons to pursue the remainder of the claim.

(17) The total amount of American Masons claim, after credit of the $328.75 for the three invoices paid excluding applicable interest, is $5,073.50.

(18) Notice of the claim was sent by American Masons to Vinco and Federal on November 6, 1990.

General Statutes 49-42 provides in CT Page 6055-g relevant part:

(a) Every person who has furnished labor or material in the prosecution of the work provided for in such contract in respect of which a payment bond is furnished under the provisions of 49-41 and who has not yet been paid in full heretofore before the expiration period of ninety days after the day on which the last of the labor was done or performed by him or material was furnished or supplied by him for which the claim is made, may enforce his right to payment under the bond by serving a notice of claim within one hundred eighty days after the date on which he performed the last of the labor or furnished the last of the material for which the claim is CT Page 6055-h made, on the surety that issued the bond and a copy of the notice on the contractor named as principal in the bond.

The defendant Federal Insurance Company denied the plaintiff's claim for payment on the ground that the notice of claim was untimely for those materials furnished prior to May 21, 1990, because the materials were furnished more than one hundred eighty days before the notice of claim was sent.

The plaintiff argues that General Statutes49-42(a) requires that the notice of claim be sent within one hundred eighty days after the date the last materials were furnished, which occurred in this instance on September 11, 1990. Therefore, the plaintiff concludes, the notice sent on November 6, 1990 was timely as to all materials furnished.

The defendants argue that because each time the plaintiff furnished materials under these circumstances it CT Page 6055-i did so pursuant to a separate contract, then the notice provision of General Statutes 49-42(a) requires that either notice be given within one hundred eighty days after each date that the plaintiff furnished materials or after the last date that materials were furnished provided that there are no intervening gaps between such purchases of more than one hundred eighty days.

The appellate courts of this state have yet to address this issue. However, the appellate courts have interpreted provisions of this statute which provide guidance in the interpretation of the notice provision at hand.1

In Okee Industries, Inc. v. National Grange Mutual Insurance Company, 225 Conn. 367, ___ A.2d ___ (1993), the plaintiff subcontractor sought to recover the balance due for hardware it supplied to the general contractor. The plaintiff sent a letter to the general contractor stating that it was seeking payment and sent a copy of the notice to the surety. The statute reads that the party shall serve a "copy of the notice" on the contractor. Here, the plaintiff CT Page 6055-j mirrored what was required by the statute.

The court stated:

The statutes having created the cause of action and prescribed the procedure, the mode of proceeding is mandatory and must be strictly complied with. On the other hand . . . 49-42 is a remedial statute enacted to provide security for workers and materials suppliers unable to avail themselves of the protection of a mechanic's lien. Because the statutory requirement of a bond is designed to protect and benefit those who furnish materials and labor to the contractor on public work, in that they may be sure of payment of their just claims, without defeat or undue delay . . . such CT Page 6055-k statutory provisions are to be liberally construed.

(Internal quotations and citations omitted.) Id., 373.

The court then noted that, in the past, it has relied on strict construction of statutes when the issue was timeliness of notice, whereas it has relied upon liberal construction when determining whether certain subcontractors were eligible for coverage under the statute. Id. "In other words, if the statute itself imposes specific constraints, we have held these constraints to be mandatory; if the statute leaves room for construction, we have construed its requirements liberally in order to implement the statute's remedial purpose." Id., 367.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Okee Industries, Inc. v. National Grange Mutual Insurance
623 A.2d 483 (Supreme Court of Connecticut, 1993)
Wickes Manufacturing Co. v. Currier Electric Co.
596 A.2d 1331 (Connecticut Appellate Court, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
1993 Conn. Super. Ct. 6055-a, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-masons-bldg-co-v-federal-ins-no-98272-jun-21-1993-connsuperct-1993.