G. T. Fogle & Co. v. United States

135 F.2d 117, 1943 U.S. App. LEXIS 4164
CourtCourt of Appeals for the Fourth Circuit
DecidedApril 20, 1943
DocketNo. 5025
StatusPublished
Cited by13 cases

This text of 135 F.2d 117 (G. T. Fogle & Co. v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
G. T. Fogle & Co. v. United States, 135 F.2d 117, 1943 U.S. App. LEXIS 4164 (4th Cir. 1943).

Opinion

DOBIE, Circuit Judge.

G. T. Fogle & Company (hereinafter called Fogle) instituted a civil action under the Tucker Act, 28 U.S.C.A. § 41(20), against the United States of America (hereinafter called the Government) in the United States District Court for the Southern District of West Virginia, seeking the recovery of damages for an alleged breach by the Government of three separate contracts entered into between Fogle and the Government for the rental of street and road construction equipment. The District Court rendered judgment for the Government and Fogle has duly taken an appeal to this Court

[118]*118The facts of the case are undisputed and all of the evidence in the case is documentary. The three contracts sued upon, designated as Claims No. 1, No. 2, and No. 3, respectively, were rental agreements for the use by the Government of a concrete mixer, a gasoline shovel, and another concrete mixer. Fogle contracted to furnish this equipment to the W. P. A., pursuant to the terms of the three separate written contracts.

Each of these contracts was executed on United States Revised Standard Form No. 33, on the reverse side of which certain instructions and conditions were printed. To this Form No. 33, in Claims No. 1 and No. 2, Form S. P. O. No. 7 was attached and expressly made a part of the contract between the parties. In the case of Claim No. 3, Form S. P. O. No. 7 was inadvertently omitted but Fogle has waived this oversight, so we may regard Form S. P. O. No. 7 as having been properly attached to this third contract. The material terms of Form S. P. -O. No. 7 bearing on a proper construction of the contracts are as follows :

“Each bidder, by submitting a bid for the rental of equipment, agrees to the following terms and conditions:
“1. Without additional cost to the Government, to furnish transportation of all equipment to and from the point of operation, and to furnish fuel, grease, oil and operator or operators therefor, except as otherwise specified in the invitation for bids. •
“2. That by submission of its bid the bidder has guaranteed and does guarantee that all equipment furnished is in first class condition * * *.
“5. All bidders must agree to the rental period specified in the invitation for bids, but the rate agreed upon shall apply to actual operating time only. Payment will be made only for such actual operating time, as determined by the proper administrative officer.
“6. If the work in connection with which the equipment is to be used is not completed at the expiration of the rental period, the Government shall have the option to extend such period for thirty (30) days, or any part thereof, at the rental rate agreed upon.
“7. The bidder shall bear all expenses incident to the maintenance and repair of all equipment rented, and for depreciation or wear and tear resulting from the operation thereof.
“8. When first ordered by the supervisor on the job, any item * * * of equipment shall be delivered to the location designated in such order within three (3) days from the date thereof. All equipment shall thereafter remain available for use on the job for the full rental period,
“9. The supervisor on the job shall inspect all equipment when delivered. If any item so delivered does not comply with the requirements of the invitation for bids * * * it may be rejected by the supervisor on the job, and it shall be the duty of the bidder to furnish, a satisfactory substitute therefor.
“10. In case of default of the contractor, the Government may procure any or all items of equipment called for by the contract from other sources, and the contractor shall be responsible for any excess cost occasioned thereby.
“12. This agreement shall be attached to U. S. Standard Form 33 (Revised), and the terms and conditions agreed upon shall be in addition to the conditions therein provided, which shall likewise apply so far as applicable.” (Italics ours.)

We shall now discuss in detail the provisions of the individual contracts.

Claim No. 1. This contract provided for the rental of a concrete mixer to the Government for 100 hours at 75 cents per hour, and required Fogle to furnish transportation for the mixer, at its own expense, to and from the point of operation. The mixer was promptly delivered by Fogle at the place specified in the contract and the project foreman acknowledged receipt of the mixer in good condition. Although Fogle admits that the mixer was never actually used by the Government, it nevertheless claims it is entitled, as damages for the alleged breach of contract by the Government in failing to use the mixer, to the sum of 300 dollars (the fair rental value of the mixer at 75 dollars per month for the 4 months’ period during which the mixer was left on the site of the project).

Claim No. 2. This contract called for the rental of a % c. y. gasoline shovel with caterpillar traction for a period of 3 months, at a rental of 400 dollars per month. Fogle agreed to pay the wages of an operator and maintain the shove] in [119]*119good repair. Here again the Government admits proper delivery of the equipment in working condition at the site of the project, and Fogle concedes that the Government at no time made use of the shovel. Fogle, however, claims damages for the alleged breach of this contract by the Government in the sum of $549.03, which amount represents the net profit Fogle would have made on the contract if the Government had operated the shovel in accordance with the contract.

Claim No. 3. This contract was for the rental of a concrete mixer at $84.00 per month. Fogle duly delivered this mixer on the project, but it was neither accepted nor used by the Government for the reason that the project had already been completed. Fogle now seeks damages for the alleged breach of this contract by the Government in the sum of $9.18. This amount represents the cost of transporting the mixer to the side of the project.

Since the same legal principles apply to each of the contracts, we shall group them together in our treatment of the case. We have no quarrel with Fogle’s general statement of the law that a contract must be read as a whole, with effect given to each provision thereof in order to arrive at the true intention of the parties. While Fogle concedes the absence on the part of the Government of an express agreement to use the equipment furnished, we are urged to read into the contracts an implied promise by the Government to operate the shovel and mixers. Thus, Fogle emphasizes the fact that it was obliged to deliver this equipment on the project and to maintain the equipment in good condition, all at its own expense. Why, asks Fogle, would it assume these obligations unless the Government was correspondingly bound to make use of the equipment furnished it?

In support of this proposition, our attention is called to the case of Southern Ry. Co. v. Franklin, 1899, 96 Va. 693, 32 S.E. 485, 44 L.R.A. 297. Here a railroad leased its property to the receiver of another road for a term of 34 years. Nine years later, the lessee manifested its intention to abandon the leased road.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
135 F.2d 117, 1943 U.S. App. LEXIS 4164, Counsel Stack Legal Research, https://law.counselstack.com/opinion/g-t-fogle-co-v-united-states-ca4-1943.