United States of America Ex Rel. Carter-Schneider-Nelson, Inc., a Corporation v. Jack T. Campbell, Doing Business as Campbell Construction and Equipmentcompany, and Fidelity and Casualty Company of New York, a Corporation,appellees. United States of America Ex Rel. Carter-Schneider-Nelson, Inc., a Corporation v. Jack T. Campbell, Doing Business as Campbell Construction and Equipmentcompany, and Phoenix Assurance Company of New York, a Corporation

293 F.2d 816
Court of Appeals for the Ninth Circuit·Decided August 17, 1961·No. 17182·Published·Cited by 1 cases

Opinion

293 F.2d 816

UNITED STATES of America ex rel. CARTER-SCHNEIDER-NELSON,
INC., a corporation, Appellant,
v.
Jack T. CAMPBELL, doing business as Campbell Construction
and EquipmentCompany, and Fidelity and Casualty
Company of New York, a corporation,Appellees.
UNITED STATES of America ex rel. CARTER-SCHNEIDER-NELSON,
INC., a corporation, Appellant,
v.
Jack T. CAMPBELL, doing business as Campbell Construction
and EquipmentCompany, and Phoenix Assurance
Company of New York, a corporation, Appellees.

Nos. 17181, 17182.

United States Court of Appeals Ninth Circuit.

Aug. 17, 1961.

Anderson, McPharlin & Conners and Kenneth E. Lewis, Los Angeles, Cal., for appellant.

Thomas E. Davis, Arthur M. Bohnert, Jr., Bohnert & McCarthy and Dudley Harkleroad, Barrett, Lucy & Harkleroad, San Francisco, Cal., for appellees.

Before BARNES, HAMLIN and JERTBERG, Circuit Judges.

BARNES, Circuit Judge.

These are two suits under the Miller Act. Jurisdiction in the trial court was based upon 40 U.S.C.A. 270a through 270d. Jurisdiction in this court rests upon 28 U.S.C. 1291.

Appellant is a lessor of earth moving equipment. In March 1956 it leased such equipment to Anderson-Kerber Co., a subcontractor engaged in work on public works projects at Fort Funston and Travis Air Force Base. The prime contractor on both projects was appellee Campbell Construction and Equipment Company (Campbell). The original lease arrangement contemplated use of the machinery at Fort Funston and not elsewhere, but a subsequent oral modification provided that the subcontractor could use the equipment at Travis.

After the subcontractor had been in default on the rent for several months, appellant brought an action, under the Miller Act (40 U.S.C.A. 270a through 270e), against Campbell, the general contractor, and Fidelity and Casualty Company of New York (Fidelity), the surety on the Fort Funston project. A separate Miller Act action was brought against Campbell and Phoenix Assurance Company of New York (Phoenix), the surety on the Travis project. The two actions were consolidated for trial but were concluded by separate judgments.

Appellant was granted no relief in the action against Phoenix. The court held that appellant had not given timely notice of his claim as required by the Miller Act. In the action against Fidelity, appellant was awarded a judgment in the sum of $7,273.33 for the reasonable value of the machinery used at Fort Funston. Appellant has taken appeals from both judgments.

I-- Appeal of the Action Against Fidelity:

A. In this appeal appellant claims that the judgment in its favor was insufficient in amount. Further, appellant claims, the court erred in not awarding it pre-judgment interest on the judgment recovered.

Appellant contends that it should receive rental payments for the total period during which the equipment was out of its possession. Appellant notes that it rented the equipment to a single subcontractor working under a single prime contractor. It would not be faced with its present difficulty, it maintains, were it not for the facts that the equipment was used on two jobs and that the prime contractor chose a different surety for each job.

Appellant does not contend, however, that the surety on the Funston project should be held for the whole amount of rental allegedly due for equipment used on both projects. It admits that such a result would be inequitable. Furthermore such a result would be beyond the contemplation of the Act. 40 U.S.C.A. 270b makes the surety liable only for material supplied in connection with the bonded project.

Appellant does contend, however, that the amount awarded it in connection with the Funston project was inadequate. The court granted a judgment of $7,273.33 against Fidelity; while appellant claims that it is entitled to a judgment of $9,654.11. The court's computation of the unpaid rent is in error, appellant claims, because it is based upon the actual use of the equipment at the Funston project; appellant should be compensated, it contends, for the time during which the equipment was available for use at Funston, even if it was not actually used all the time. This, however, is a false issue (and the battle of case authority which the parties have engaged in with respect to it is irrelevant), for the court's computations purport to award rent for the time during which the equipment was 'located at' Funston (Findings IV and V, especially at pp. 67 and 69 of the Record, Volume I in appeal No. 17181). And it does not appear that 'available at' means anything other than 'located at,' especially when it is noted (as will be seen below) that appellant's computation of the 'availability' of particular equipment at various places corresponds significantly and almost precisely with the court's computation of when the equipment was 'located at' those places. We note that appellant has not explicitly attacked the court's findings with respect to the location of the equipment at various relevant times, nor has it alleged that those findings are not supported by substantial evidence.

Free access — add to your briefcase to read the full text and ask questions with AI

United States of America Ex Rel. Carter-Schneider-Nelson, Inc., a Corporation v. Jack T. Campbell, Doing Business as Campbell Construction and Equipmentcompany, and Fidelity and Casualty Company of New York, a Corporation,appellees. United States of America Ex Rel. Carter-Schneider-Nelson, Inc., a Corporation v. Jack T. Campbell, Doing Business as Campbell Construction and Equipmentcompany, and Phoenix Assurance Company of New York, a Corporation, 293 F.2d 816 (9th Cir. 1961).

293 F.2d 816 (United States of America Ex Rel. Carter-Schneider-Nelson, Inc., a Corporation v. Jack T. Campbell, Doing Business as Campbell Construction and Equipmentcompany, and Fidelity and Casualty Company of New York, a Corporation,appellees. United States of America Ex Rel. Carter-Schneider-Nelson, Inc., a Corporation v. Jack T. Campbell, Doing Business as Campbell Construction and Equipmentcompany, and Phoenix Assurance Company of New York, a Corporation) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

United States v. Continental Casualty Co.
230 F. Supp. 557 (W.D. Pennsylvania, 1964)