United States v. Van de Riet

316 F.2d 912
CourtCourt of Appeals for the Fourth Circuit
DecidedApril 25, 1963
DocketNo. 8867
StatusPublished
Cited by4 cases

This text of 316 F.2d 912 (United States v. Van de Riet) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Van de Riet, 316 F.2d 912 (4th Cir. 1963).

Opinion

HARRY E. WATKINS, District Judge.

This is an action by plaintiff, The Henry Walke Company, which furnished material on a government contract, to recover the sum of $9,181.20 under the Miller Act (Title 40 U.S.C.A. § 270a et seq.) directly from Van de Riet Construction Company, the prime contractor, and Reliance Insurance Company, the surety on the prime contractor’s payment bonds, for such materials furnished to Acme Fence Co., Inc., a subcontractor. The original complaint, which alleged that full and proper notice as required under the Miller Act had been given, was subsequently amended to contain the alternate allegation that no notice was required, as plaintiff had a direct contractual relationship with defendant, Van de Riet, the prime contractor. Two questions were presented to the District Court, hearing the case without a jury, for decision. (1) Was there a contractual relationship, within the meaning of the Miller Act, between Van de Riet and Walke, and, if so, is Walke entitled to recover thereunder? (2) Was the 90 day notice required under the Miller Act given by Walke to Van de Riet? Both questions were answered in the negative by the trial court, and judgment was entered for Van de Riet and its surety, and plaintiff Walke has appealed. In a clear and able opinion, the District Court has set forth his findings of fact and conclusions of law. We find no error and affirm the judgment of the Court below.

On September 16, 1958, Van de Riet was awarded a construction contract for off-site improvements, utilities and structures essential to a 500-unit Capehart Housing Facility at Langley Air Force Base, Langley Field, Virginia, at a contract price of $369,000.00. As required by the Miller Act, Van de Riet, with Reliance as surety, executed a payment bond. Included in the work to be performed by Van de Riet was an item for fencing. Van de Riet subcontracted this portion of the job to Acme, at a price of $13,500.00 for both labor and materials, the subcontract being dated October 31, 1958, but providing for a beginning date on October 7, 1958, and for completion of all work in 540 days. Acme furnished Van de Riet a performance [914]*914and payment bond with Standard Accident Insurance Company as surety. The subcontract to Acme provided for periodic payments to Acme upon presentation of certificates issued under the schedules of values contained in the contract between Van de Riet and the United States.

Acme was in very weak financial condition, and to assist itself in obtaining materials on credit Acme prepared and submitted to Van de Riet for approval an assignment of the proceeds of its contract to Walke, the assignment reading as follows:

“Assignment of Contract to Henry Walke Company
“For value received we the undersigned have assigned unto Henry Walke Company contract drawn between Van de Riet Construction Company and Acme Fence Co., Inc. dated October 7, 1958.
“The amount of this contract is $13,-500.00 to furnish fencing material and labor to install same for the Armed Services Housing Project Off-Site Improvements and Utilities for U. S. Air Force, at Langley Air Force Base, Virginia.
“For consideration of pipe and supplies Acme Fence Company, Inc. hereby assigns to Henry Walke Company all moneys due or to become due on above contract.
“Acme Fence Co., Inc.
“/s/ Samuel Gugino
President
“Nov.-18-1958
“Date
“Approved
“Van de Riet Const. Co.
“/s/ Peter H. Van de Riet
“12-1-58 Date”

Acme also obtained the written consent of Standard that such assignment would not invalidate its bond. This consent was given after Acme had executed its assignment, but apparently prior to the date Van de Riet approved the assignment on December 1, 1958, and prior to the time any order for materials was placed by Acme. .

On December 2, 1958, Walke acknowledged receipt of the approved assignment of the account in a letter to Van de Riet stating:

“It is our understanding that the amount of the contract between you and Acme Fence Company, Incorporated is $13,500.00 and we further understand that this sum will be paid to us under the assignment rather than to Acme Fence Company.
“If the above does not conform to your understanding of the transaction, please advise us at once.”

The first order for materials was placed by Acme with Walke by letter dated December 2, with request for delivery to Acme’s rail siding. The price for such material, shipped on December 2, 1958, and January 13, 1959, aggregated $12,-602.38, or $897.62 less than the total subcontract price of $13,500.00. The order was for “tons” of pipe and wire. Before Acme could use the pipe or rolls of wire on the project it would have been necessary for Acme to cut the pipe to size and fabricate the wire. It is conceded that only a portion of the material was used on the project in question. Acme’s president admitted that some of the material was never intended and could not be used for this particular subcontract and this is so despite Acme’s letter to Walke dated December 3, which assured Walke that the material purchased was to be used on this job. There was a conflict in the testimony as to whether any substantial part of such material conformed to the specifications of the subcontract. The material was delivered to Acme’s rail siding, not to the job site itself.

Acme performed a part of its subcontract for which Van de Riet paid $2,-592.00, not to Acme, but directly to Walke under the assignment. According to Acme, Walke had been informed that payment on the contract would not be made until the job was completed. After receiving the payment mentioned above, Walke telephoned Van de Riet to inquire as to when the fence would be installed.

[915]*915Walke does not contend that Van de Riet ever promised or agreed to do anything as far as Walke was concerned, other than to recognize the assignment of the proceeds of the contract. It is true that the assignment refers to an assignment of the contract, but Walke does not contend that it was to perform the obligations of the subcontract.

Subsequently, Acme became insolvent and defaulted under its subcontract. The District Court found that much of the material purchased from Walke had been used by Acme on other jobs. When Acme was financially unable to complete the contract, Van de Riet proceeded to do so at a total cost in excess of the original contract price of $13,500.00.

Walke’s officers testified that Walke was looking to Van de Riet for payment, but the trial court found, and we think correctly, that there is no evidence to substantiate the view that Van de Riet was of the same opinion, except as to the assignment that was accepted by Van de Riet. Van de Riet states that while he was aware of the assignment he had no knowledge of the non-payment of Acme’s indebtedness to Walke until sometime in May I960,1 long after the 90-day notice period in the Miller Act had passed.

The gist of the amended complaint is that Walke did, on or about December 1, 1958, enter into a contract with Van de Riet, and that Van de Riet agreed to pay Walke for the materials supplied to Acme.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gerhold Concrete Co. v. St. Paul Fire & Marine Insurance Co.
695 N.W.2d 665 (Nebraska Supreme Court, 2005)
US, METAL MFG., INC. v. Federal Ins. Co.
656 F. Supp. 1194 (D. Arizona, 1987)
United States v. Van Riet
316 F.2d 912 (Fourth Circuit, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
316 F.2d 912, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-van-de-riet-ca4-1963.