Gerhold Concrete Co. v. St. Paul Fire & Marine Insurance Co.

695 N.W.2d 665, 269 Neb. 692, 2005 Neb. LEXIS 84
CourtNebraska Supreme Court
DecidedApril 28, 2005
DocketS-03-1064
StatusPublished
Cited by55 cases

This text of 695 N.W.2d 665 (Gerhold Concrete Co. v. St. Paul Fire & Marine Insurance Co.) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gerhold Concrete Co. v. St. Paul Fire & Marine Insurance Co., 695 N.W.2d 665, 269 Neb. 692, 2005 Neb. LEXIS 84 (Neb. 2005).

Opinion

Connolly, J.

St. Paul Fire and Marine Insurance Company (St. Paul) provided a payment bond for First Dakota Enterprises, Inc. (First Dakota), a general contractor for a public construction project. Gerhold Concrete Company, Inc. (Gerhold), supplied concrete to CMS, Inc., First Dakota’s subcontractor. CMS failed to pay Gerhold for the concrete, and Gerhold sued First Dakota on a contract theory and St. Paul on the performance bond.

The district court dismissed First Dakota from the suit but determined that a jury could find that Gerhold could recover against St. Paul on the bond. A jury returned a verdict for Gerhold. St. Paul appeals the district court’s denial of its motion for a directed verdict. St. Paul claims that Neb. Rev. Stat. § 52-118.01 (Reissue 1998) required Gerhold to give 4 months’ written notice to First Dakota before it could proceed against the bond, that Gerhold failed to give notice, and thus, Gerhold’s claim must fail.

*694 Under § 52-118.01, for Gerhold to recover on the performance bond, it must give written notice to the contractor within 4 months from the date of the last materials supplied, unless it had a contractual relationship, express or implied, with the contractor. Gerhold acknowledges that it did not give written notice to First Dakota. This appeal requires us to determine whether there was a contractual relationship, express or implied, that excused Gerhold from providing written notice to First Dakota.

Resolving every controverted fact in Gerhold’s favor and giving it the benefit of every reasonable inference, we determine that the jury could find that First Dakota told Gerhold that it would pay for concrete supplied to CMS. Thus, the jury could conclude that a contract, and hence, a contractual relationship, existed, and the district court properly overruled the motion for a directed verdict. Likewise, we determine that the court erred when it granted First Dakota’s motion to dismiss because there was evidence from which a jury could determine that a contract was formed. Accordingly, we affirm in part, and in part reverse and remand for a new trial against First Dakota.

BACKGROUND

This appeal arises from a public construction project to build a veterans home in Norfolk, Nebraska. First Dakota obtained discounted prices from Gerhold when it bid on the project. According to Gerhold, it offered those prices only if it were the sole concrete supplier for the project. First Dakota was awarded the project as general contractor. Some time later, Steve Johnson, who was Gerhold’s plant manager, spoke with Wayne July, the project manager for First Dakota. According to Johnson, July confirmed that First Dakota would use Gerhold as its concrete supplier. July admitted that he committed to using Gerhold “to a certain extent,” but did not commit to having Gerhold as the exclusive supplier.

First Dakota subcontracted the concrete work to CMS and specified that CMS should use Gerhold as the supplier. Gerhold agreed to bill CMS for the concrete. Through May, June, and part of July 1999, First Dakota paid CMS, but CMS failed to pay Gerhold.

According to Johnson, he met with July and informed him that CMS failed to pay the invoices for May through July 1999, *695 which amounted to about $100,000, and that Gerhold would stop supplying concrete if it did not receive payment. The record contains the following colloquy between Gerhold’s attorney and Johnson:

Q. What was . . . July’s response to learning that First Dakota might lose its concrete supplier?
A. . . . July was, of course, concerned. And he told me, he says, you don’t want to do that. . . .
I said, what about the CMS account, that past-due account? And Wayne July said, you keep that concrete coming, and First Dakota, don’t worry about it, First Dakota will take care of it.
Q. What did you say when ... July said that First Dakota would take care of the unpaid invoices, just keep the concrete coming?
A. I agreed we would keep the concrete coming.

Johnson later stated again that July agreed to take care of unpaid invoices if Gerhold continued to supply concrete. July denied that Gerhold ever notified him that it would stop supplying concrete if it were not paid or that he agreed to pay for unpaid invoices. He stated that had Gerhold quit delivering concrete, he would have obtained a new supplier. First Dakota paid all further invoices directly to Gerhold but did not pay for the previous, unpaid invoices for May through July.

Gerhold filed suit against First Dakota for breach of contract and against St. Paul on the bond seeking payment for the unpaid May through July 1999 invoices. After Johnson’s testimony, St. Paul and First Dakota moved for a directed verdict. They argued that First Dakota did not enter into a contract for payment and that there was no contractual relationship, express or implied, for Gerhold to recover payment for past invoices. The court granted First Dakota’s motion for directed verdict, stating that the evidence failed to show the formation of a contract for payment of the unpaid invoices; specifically, the court determined that Gerhold failed to show the terms of any oral contract to pay. The court then reviewed §52-118.01, and it concluded there was evidence that a general contractual relationship existed between Gerhold and First Dakota based on the agreement that Gerhold *696 would provide concrete at specified prices and that First Dakota would exclusively use Gerhold’s concrete. Because of that contractual relationship, the court determined a jury could find that § 52-118.01 relieved Gerhold from the notice requirement and denied St. Paul’s motion for a directed verdict.

The jury returned a verdict for $91,582.28, and the district court denied Gerhold’s request for prejudgment interest, finding that the amount of recovery was in controversy. Gerhold had initially sought $111,137.34, but later stipulated that the amount should be reduced by $16,473.06. St. Paul appeals, and Gerhold cross-appeals. We granted St. Paul’s petition to bypass.

ASSIGNMENTS OF ERROR

St. Paul assigns that the district court erred by (1) failing to grant its motion for a directed verdict and to dismiss the action against it, (2) failing to allow evidence that Gerhold previously acknowledged receipt of a payment that was greater than it would admit at trial, and (3) refusing to permit cross-examination of a witness about a prior inconsistent statement in answers to interrogatories.

On cross-appeal, Gerhold assigns, rephrased, that the district court erred by (1) sustaining the motion for directed verdict for First Dakota and (2) denying an award of prejudgment interest.

STANDARD OF REVIEW

A directed verdict is proper at the close of all the evidence only when reasonable minds cannot differ and can draw but one conclusion from the evidence, that is to say, when an issue should be decided as a matter of law. Livingston v. Metropolitan Util. Dist., ante p.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bruce Lavalleur, P.C. v. Guarantee Group
992 N.W.2d 736 (Nebraska Supreme Court, 2023)
Echo Group v. Tradesmen Internat.
980 N.W.2d 869 (Nebraska Supreme Court, 2022)
Weyh v. Gottsch
303 Neb. 280 (Nebraska Supreme Court, 2019)
Gibbons Ranches v. Bailey
289 Neb. 949 (Nebraska Supreme Court, 2015)
Braunger Foods v. Sears
834 N.W.2d 779 (Nebraska Supreme Court, 2013)
GGNSC Omaha Oak Grove, LLC v. Ivan Payich
708 F.3d 1024 (Eighth Circuit, 2013)
Henggeler v. Brumbaugh & Quandahl, P.C.
894 F. Supp. 2d 1180 (D. Nebraska, 2012)
Wojtalewicz v. Pioneer Hi-Bred International, Inc.
939 F. Supp. 2d 965 (D. Nebraska, 2012)
Waldinger Corp. v. WorldCom, Inc. (In Re WorldCom, Inc.)
466 F. App'x 28 (Second Circuit, 2012)
Hinshaw v. Ligon Industries, L.L.C.
551 F. Supp. 2d 798 (N.D. Iowa, 2008)
Jones v. Jones
747 N.W.2d 447 (Nebraska Court of Appeals, 2008)
Ferer v. Aaron Ferer & Sons Co.
725 N.W.2d 168 (Nebraska Supreme Court, 2006)
Kelly Conolly v. James D. Clark
457 F.3d 872 (Eighth Circuit, 2006)
Roth v. Wiese
716 N.W.2d 419 (Nebraska Supreme Court, 2006)
Curran v. Buser
711 N.W.2d 562 (Nebraska Supreme Court, 2006)
Shipler v. General Motors Corp.
710 N.W.2d 807 (Nebraska Court of Appeals, 2006)
LeRette v. American Medical Security, Inc.
705 N.W.2d 41 (Nebraska Supreme Court, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
695 N.W.2d 665, 269 Neb. 692, 2005 Neb. LEXIS 84, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gerhold-concrete-co-v-st-paul-fire-marine-insurance-co-neb-2005.