Lange Industries, Inc. v. Hallam Grain Co.

507 N.W.2d 465, 244 Neb. 465, 1993 Neb. LEXIS 258
CourtNebraska Supreme Court
DecidedNovember 5, 1993
DocketS-91-548
StatusPublished
Cited by114 cases

This text of 507 N.W.2d 465 (Lange Industries, Inc. v. Hallam Grain Co.) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lange Industries, Inc. v. Hallam Grain Co., 507 N.W.2d 465, 244 Neb. 465, 1993 Neb. LEXIS 258 (Neb. 1993).

Opinion

Fahrnbruch, J.

Hallam Grain Co. (Hallam) appeals the entry of a construction lien foreclosure in favor of Lange Industries, Inc. (Lange), based upon the district court’s finding that Lange had substantially performed its agreement to build a $510,000 *467 four-bin grain elevator facility for Hallam. The grain company had filed six counterclaims at law.

After taking into account various credits and charges, the district court for Lancaster County found that Hallam owed Lange a net balance of $56,203.25 in its foreclosure action, but reduced that amount by $1,464.30 for repairs and modifications to a dump pit because Lange had not properly designed it. Counterclaims or, in the alternative, setoffs, except one for repairs and modifications of the dump pit, requested by Hallam were dismissed.

I. ASSIGNMENTS OF ERROR

In its assignments of error, Hallam claims that the district court erred in (1) improperly allocating the burden of proof on the issue of “substantial performance,” (2) finding that Lange had substantially performed the construction contract, (3) finding that Hallam was liable for “site preparation” and for repair and replacement of a conveyor belt, (4) failing to admit Hallam’s evidence of damages regarding its counterclaim, (5) failing to award Hallam setoffs for repairs it made to the facility, (6) failing to award Hallam damages for damaged grain, and (7) considering Lange’s “manufacturer’s warranty defense” and evidence of a design defect in the failed bins.

In its cross-appeal, Lange claims that the trial court erred in denying it prejudgment interest and in awarding Hallam $1,464.30 on its counterclaim for modifications to the dump pit.

We affirm the judgment of the district court for Lancaster County.

II. STANDARD OF REVIEW

An action to foreclose a construction lien is one grounded in equity. Mid-America Maintenance v. Bill Morris Ford, 232 Neb. 920, 442 N.W.2d 869 (1989). In an appeal of an equity action, an appellate court tries factual questions de novo on the record and reaches a conclusion independent of the findings of the trial court, provided, where credible evidence is in conflict on a material issue of fact, the appellate court considers and may give weight to the fact that the trial judge heard and observed the witnesses and accepted one version of the facts *468 rather than another. Mid-America Maintenance, supra; O’Keefe Elevator v. Second Ave. Properties, 216 Neb. 170, 343 N.W.2d 54 (1984).

A suit for damages arising from breach of a contract presents an action at law. Fisbeck v. Scherbarth, Inc., 229 Neb. 453, 428 N.W.2d 141 (1988). In a bench trial of a law action, the trial court’s factual findings have the effect of a jury verdict and will not be set aside on appeal unless clearly erroneous. Broekemeier Ford v. Clatanoff, 240 Neb. 265, 481 N.W.2d 416 (1992); Nebraska Builders Prod. Co. v. Industrial Erectors, 239 Neb. 744, 478 N.W.2d 257 (1992). As pled, Hallam’s counterclaims or, in the alternative, requests for setoffs are claims for damages arising from the alleged breach of a contract.

Therefore, this court must review Lange’s foreclosure suit de novo and Hallam’s counterclaims under the “clearly erroneous” standard.

III. FACTS

On June 21, 1986, Hallam entered into a written agreement, consisting of three purchase orders, with Lange for Lange to construct a $510,000 four-bin grain elevator facility for Hallam. A change order, dated October 6,1986, provided some relatively minor changes at a cost of $4,500.

Lange agreed to provide and erect (1) two Blount/MFS 48-foot-diameter bins and two Blount/MFS 60-foot-diameter bins with aeration fans and temperature cables in each bin, (2) a custom-built dump pit and boot pit with a 7,000-bushels-per-hour (b.p.h.) drag conveyor, (3) a leg support tower with platforms, (4) a swivel Ioadout spout with support tower, (5) a gravity 7,000-b.p.h. grain cleaner, (6) a Blount/York model 36-70 elevator leg 7,000 b.p.h., (7) 7.000- b.p.h. drag unloading conveyors, and (8) two 7.000- b.p.h. drag conveyors mounted on catwalks. Most of the parts were manufactured by MFS Blount/York (Blount), which company provided “working drawings” to Lange for the construction of the facility. Blount was not a party to the contract or a party to this litigation.

In addition to the list of parts, the purchase orders included typewritten provisions stating that a “clean level site is to be *469 provided by the buyer” and “electrical hook-up beyond the Main disconnect is included.” Stricken from each purchase order was a preprinted provision stating, “Concrete, Electrical Wiring, Gas Hook-up, Fill Sand and Level Site to be furnished by the Buyer [Hallam].”

William Lange, president of Lange, testified that he and Melvin Holsing, president of Hallam, verbally agreed that to avoid water draining into the grain facility, the floor of the grain bins should be 1 foot above the top of the railroad tracks which were located to the west of the construction site. Holsing testified that he wanted “nothing below 12 inches above the tracks.” (Emphasis supplied.)

Apparently, there was a general understanding that Lange would attempt to have the bins ready to receive grain by the fall of 1986. Construction began in late June or early July 1986. Excavation of the site uncovered some concrete rubble and foundations. The rubble was removed by Lange and Beatrice Concrete, a company that had previously owned the site. By late September, Lange had constructed two 48-foot-diameter bins on the west side of Hallam’s property, and Hallam began loading them with grain.

While loading the first bins, Holsing and his employees noticed that grain was “boiling over” in places and plugging the system. They found that various mechanisms in the system, including the leg, the boot pit shroud, and the upper spouts, were not operating properly. As a result, several adjustments were made to the system. Holsing testified he tested the system and determined that it was moving approximately 4,000 b.p.h. Holsing notified a Lange foreman, and a Blount representative was called. Blount’s representative testified that he inspected the facility and found that “it was functioning as it was designed for.” He said he attempted to test the system’s capacity, but could not do so because of dirt collecting in the spouts of the distributor. He was to return later to conduct a capacity test, but never did.

Hallam claims that the capacity problem occurred because of Lange’s poor workmanship in constructing the system. Henry Hollman, a local grain bin contractor, testified for Hallam as an expert witness. In his opinion, the spouts had not been angled *470 steeply enough to prevent the accumulation of grain and dust.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Echo Group v. Tradesmen Internat.
980 N.W.2d 869 (Nebraska Supreme Court, 2022)
Freedom Specialty Contracting v. Nichol Flats
28 Neb. Ct. App. 797 (Nebraska Court of Appeals, 2020)
George Clift Enters. v. Oshkosh Feedyard Corp.
306 Neb. 775 (Nebraska Supreme Court, 2020)
Infogroup, Inc. v. DatabaseUSA.com LLC
956 F.3d 1063 (Eighth Circuit, 2020)
Cullinane v. Beverly Enters. - Neb.
300 Neb. 210 (Nebraska Supreme Court, 2018)
Cullinane v. Beverly Enters.-Neb., Inc.
300 Neb. 210 (Nebraska Supreme Court, 2018)
Laura Powers v. Credit Management Services, In
776 F.3d 567 (Eighth Circuit, 2015)
Digital Ally, Inc. v. Z3 Technology, LLC
754 F.3d 802 (Tenth Circuit, 2014)
Thurston v. Nelson
Nebraska Court of Appeals, 2014
Hawkins Construction Co. v. Peterson Contractors, Inc.
970 F. Supp. 2d 945 (D. Nebraska, 2013)
Oettinger v. Hiatt
Nebraska Court of Appeals, 2013
Ferer v. Aaron Ferer & Sons Co.
725 N.W.2d 168 (Nebraska Supreme Court, 2006)
Moglia v. McNeil Co., Inc.
700 N.W.2d 608 (Nebraska Supreme Court, 2005)
Gerhold Concrete Co. v. St. Paul Fire & Marine Insurance Co.
695 N.W.2d 665 (Nebraska Supreme Court, 2005)
Zoucha Ex Rel. D.H. v. Henn
604 N.W.2d 828 (Nebraska Supreme Court, 2000)
Henton v. Nokes
603 N.W.2d 1 (Nebraska Supreme Court, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
507 N.W.2d 465, 244 Neb. 465, 1993 Neb. LEXIS 258, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lange-industries-inc-v-hallam-grain-co-neb-1993.