Olson v. Pedersen

231 N.W.2d 310, 194 Neb. 159, 1975 Neb. LEXIS 778
CourtNebraska Supreme Court
DecidedJune 19, 1975
Docket39859
StatusPublished
Cited by22 cases

This text of 231 N.W.2d 310 (Olson v. Pedersen) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Olson v. Pedersen, 231 N.W.2d 310, 194 Neb. 159, 1975 Neb. LEXIS 778 (Neb. 1975).

Opinion

Clinton, J.

This multifaceted action arises out of a gravel mining lease between the defendant landowners, Pedersens, as lessors, and the plaintiff, J. Myron Olson, as lessee.

The nature of the case and the issues involved make it desirable to first set forth some background facts. In .1967 the parties made their first lease agreement. It provided for payment of a 20 cents per yard royalty with a minimum payment of $500 per year and contained provisions relating to the disposal of the overburden. Approximately 35,000 cubic yards of gravel were mined and sold under that lease. In the first part of April 1971, Pedersens, who had kept records of the gravel sold, brought suit against Olson for allegedly unpaid *161 royalty. This suit was dismissed by the Pedersens without payment of any sums by Olson and the parties resolved their differences by entering into a new and more elaborate lease on April 29, 1971. The present action grows out of that lease. At the time the new lease was entered into, in addition to the gravel which had been sold, there had been mined and stockpiled on the premises approximately 11,000 cubic yards of gravel. There was at that time, also, a substantial amount of overburden piled upon what was formerly level ground referred to in the record as the first orchard level.

The lease of April 29, 1971, was for a 5-year term. It provided for payment to the Pedersens of “twenty cents ($.20) for each cubic yard of limestone, sand, rock or gravel removed from said premises to be marketed or for lessee’s own use, including approximately 10,000 cubic yards already mined and stockpiled on said premises-.” The lease provided that the royalty was to be paid within 10 days after the end of each 30-day period. It also provided: “In no event shall the payments herein specified be less than five hundred dollars ($500.00) in any 12 month period beginning with the execution of this lease.” The provision with reference to disposal of overburden was as follows: “LESSEE AGREES to level all dirt, waste material and refuse from said operation to a height not to exceed the first level west of the orchard. The dirt now piled on the first level west and south of the orchard shall be pushed westward into a hole, into the area now occupied by the stockpile or in any area agreed upon around the farm buildings designated by lessors for their use and benefit. In no event shall any material of any type be pushed any further east of its present location except into the hole now existing or the stockpile area, nor shall the same be pushed over or upon any existing structure or fence. It is understood that the original first level was 50- feet wide on the average before gravel operations commenced, and lessee has no obligation to remove or level any dirt which is *162 more than 50 feet west of first level. All material shall be pushed in a westerly direction if practical. The parties shall agree on a new site for any future stockpiles of gravel. The present pile of dirt now on the first level west of the orchard shall be removed or leveled as herein provided within two years from date of execution of this lease. Lessee agrees to construct adequate dikes around the excavating site to prevent erosion and excess water drainage onto surrounding areas, especially toward lessor’s house and other farm buildings.”

No mining was done during the first year of this lease. Before the end of the first year Olson made a check for the minimum $500 yearly royalty payable to the Pedersens and to John Hancock Insurance Company, holder of a mortgage on the Pedersen land, to whom the royalties had been assigned, and sent this check to Pedersens’ attorney. This check was never negotiated. Not only was no mining done under the lease, but none of the stockpile was sold. Timely tenders of the minimum annual royalty for 1973 and 1974 were made and refused.

On July 26, 1972, Pedersens sent Olson a “Notice to Terminate Lease,” which recited as grounds for termination, the following:

“(1) Nonpayment of rent by Lessee;
(2) Failure by Lessee to construct one cattle and hog crossing which was sufficient to restrict cattle and hogs from crossing the same.
(3) Failure by Lessee to level all dirt, waste material and refuse from said gravel operation to a height not to exceed the first level west of the orchard.
(4) Failure of Lessee to construct adequate dikes around the excavating site to prevent erosion and excess water drainage on surrounding areas.
(5) Failure by Lessee to stock pile gravel on premises leased.
(6) Stock piling gravel on premises not agreed to by Lessors,” '

*163 and then demanded delivery and possession of the premises within 15 days of the receipt of the notice.

About 30 days after the receipt of the notice, Olson commenced this action and alleged three causes. The first was for a declaratory judgment, praying that the rights of the parties be determined. This cause was much later amended to allege that the Pedersens’ actions were such a material breach of the lease as to excuse further performance by Olson. The second cause was for an injunction to prevent termination of the lease and to restrain Pedersens from interfering with Olson’s use and enjoyment of the leasehold estate. The third cause claimed damages allegedly resulting to Olson by publicity arising out of the earlier litigation and also asked for damages from Pedersens for their having prevented Olson from disposing of the stockpiled gravel. The.third cause was also later amended to allege that Pedersens had breached the lease by, among other things, serving the notice to terminate. It also asked damages for the loss of use of certain equipment on the premises used in the mining operation, namely a D9 dozer, a link-belt crane, a conveyor,, and two trucks, which items Pedersens allegedly prevented Olson from removing.

Pedersens answered, admitting certain allegations and denying others, alleged nonpayment of rent due April 29, 1972, and asked damages for failure to level the dirt and waste and for failure to build the dike, and also prayed for certain consequential damages.

The trial court found that both parties had breached the lease and that it. was terminated; and that Olson breached the lease by failing to build the dike and permitting waste and erosion. It awarded Olson $10,000 damages for loss of use of his equipment, and it allowed Pedersens $10,000 damages from Olson for the latter’s failure to level, fill, and build dikes: It awarded Pedersens $1,000 for rent payments, and Olson $344.10 for gravel sold by Pedersens from the stockpile and not paid *164 for by them. It ordered that the stockpile of gravel be sold within 18 months and authorized injunctive relief to bring this about. Its order terminated the lease as of April 29, 1974, the third anniversary date thereof.

Olson appeals. Pedersens cross-appeal. Olson here, by proper assignment, urges: (1) The court erred in ruling that the lease had been terminated. In the alternative Olson asserts that the purported termination by Pedersens excused further performance on his part.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Union Ins. Co. v. Land and Sky, Inc.
568 N.W.2d 908 (Nebraska Supreme Court, 1997)
Begley v. Peabody Coal Co.
978 F. Supp. 861 (S.D. Indiana, 1997)
Allemang v. KEARNEY FARM CENTER, INC.
554 N.W.2d 785 (Nebraska Supreme Court, 1996)
Watts v. Butte School District No. 5
939 F. Supp. 1418 (D. Nebraska, 1996)
RW Power Partners, L.P. v. Virginia Electric & Power Co.
899 F. Supp. 1490 (E.D. Virginia, 1995)
Lange Industries, Inc. v. Hallam Grain Co.
507 N.W.2d 465 (Nebraska Supreme Court, 1993)
Carroll v. Holthus
447 N.W.2d 22 (Nebraska Supreme Court, 1989)
Gottsch Feeding Corp. v. Red Cloud Cattle Co.
429 N.W.2d 328 (Nebraska Supreme Court, 1988)
Caeli Associates, Inc. v. Firestone Tire & Rubber Co.
415 N.W.2d 116 (Nebraska Supreme Court, 1987)
Hutchison v. Sunbeam Coal Corp.
519 A.2d 385 (Supreme Court of Pennsylvania, 1986)
Birkel v. Hassebrook Farm Service, Inc.
363 N.W.2d 148 (Nebraska Supreme Court, 1985)
Towne v. Sautter
326 N.W.2d 694 (North Dakota Supreme Court, 1982)
Hogan v. Pelton
315 N.W.2d 644 (Nebraska Supreme Court, 1982)
Archer v. Mountain Fuel Supply Co.
642 P.2d 943 (Idaho Supreme Court, 1982)
Calvert Fire Insurance v. Unigard Mutual Insurance
526 F. Supp. 623 (D. Nebraska, 1980)
Commonwealth Edison Co. v. State
615 P.2d 847 (Montana Supreme Court, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
231 N.W.2d 310, 194 Neb. 159, 1975 Neb. LEXIS 778, Counsel Stack Legal Research, https://law.counselstack.com/opinion/olson-v-pedersen-neb-1975.