Western Land Roller Co. v. Schumacher

36 N.W.2d 777, 151 Neb. 166, 1949 Neb. LEXIS 75
Nebraska Supreme Court·Decided April 14, 1949·No. No. 32561·Published·Cited by 5 cases

Opinion

Carter, J.

This is a suit to foreclose a mechanic’s lien for the balance due on two contracts for the drilling of two irrigation wells. The defendants alleged that the first well was not in accordance with the agreement and deny liability therefor. They also allege that the second well was not constructed within the time specified and they counterclaim for damages resulting to growing crops because of said breach. The trial court found that there was nothing due plaintiff for drilling the first well, found that there was $1,654.95 due for drilling the second well, and dismissed the counterclaim for damages to crops.

The defendant, Leo M. Schumacher, as executor of the estate of his father, Mathias Schumacher, had the possession and management of 424 acres of land in Sections 18 and 13, the complete legal descriptions of which are accurately set forth in the pleadings. He was also a lessee of a portion of the lands in Section 18. Substantial portions of these lands were irrigable and lay within the boundaries of the Pathfinder Irrigation District. The record shows that a shortage of irrigation water was anticipated during the growing season of 1940.

On December 8, 1939, • the defendant Leo M. Schumacher entered into a written agreement with the plaintiff for the constructon of an irrigation well on the lands leased by him in Section 18. This well was drilled and cased and a test made to determine the amount of water it would produce. The test showed that its capacity was approximately 750 gallons per minute. This amount was not satisfactory to the defendant and it was not [168] accepted. The trial court found that there was nothing due for drilling this well. No. appeal or cross-appeal was taken from this finding and consequently the trial court's disposition of this phase of the case is final.

On May 11, 1940, Leo M. Schumacher as executor of the estate of Mathias Schumacher entered into an agreement with the plaintiff to drill and equip a second well. This agreement provided that the well would be drilled and equipped for use for $1,710.30, with additional charges if the depth of the well exceeded 125 feet, and for a reduction for each foot less than the estimated depth. The amount claimed by the plaintiff for drilling the well and furnishing the pump, including the drilling of test wells, is $1,654.95. This amount is not challenged by the appeal. The sole question for determination is the correctness of the court’s findings on the counterclaim for damages to the growing crops.

The issue here presented turns primarily on a provision of the agreement of May 11, 1940, providing as follows: “The Seller agrees to begin drilling the well on or before May 25 and complete the Well and install the Pump as quickly as possible.”

The evidence shows that a test well was drilled before the contract was entered into for the second well. It shows, also, that plaintiff deemed it advisable to use a rotary or hydraulic drill as a result of the conditions shown to exist when the test well was completed. Plaintiff’s representative informed the defendant Schumacher that plaintiff had such a well-drilling outfit operating at Lodgepole, Nebraska, and that he would move it on this job as soon as the Lodgepole job was completed. Unfavorable conditions developed on the Lodgepole job, and the hydraulic drill did not commence work on Schumacher’s second well until June 4, 1940. This was ten days after the time agreed upon in the contract. The evidence shows that after drilling 32 feet an obstruction was encountered which the hydraulic drill could not penetrate. An orange peel and small drill [169] bar were successively used without success. The final result was that a blind casing drill had to be obtained to drill the well. The evidence shows that the second outfit commenced work on July 17 and completed the drilling and installation of the well casings on July 27. The test of the well’s capacity was made within two or three days thereafter. The pump could not be assembled until the capacity of the well and height of the lift were first ascertained. The pump was subsequently installed and the well completed on August 19, 1940.

It is shown by the record that plaintiff installed a pump in the first well on July 10, 1940, which defendants were permitted tó use while the second well was being drilled and the pump installed. It operated continuously, except when irrigation water was flowing in the ditch, until it was removed at the time or a few days before the second well was ready to operate.

The evidence shows further that the water from the first pump was discharged directly into an irrigation lateral which was located close to this pump. The second well was approximately 440 feet from this lateral. Defendant Schumacher, in order to make proper use of the water from the second well, found it necessary to install a pipeline to this same lateral. He purchased the pipe and caused the pipeline to.be constructed. It was not completed until August 27,1940, at which time the second well and pump were ready to operate. It was upon this evidence that the trial court found no basis for a claim for crop damage.

The contract provides that plaintiff will complete the well and install the pump as quickly as possible. The words “as soon as possible”' mean with all reasonable diligence or without unreasonable delay. In Childs & Co. v. Omaha Paraphernalia House, 80 Neb. 673, 114 N. W. 941, we said: “We do not think that an order sent to a manufacturing company to manufacture a special article ‘as soon as possible’ means ‘immediately,’ or that the company must stop all its other work and devote [170] itself to that particular order; but that, as stated in Rhodes v. Cleveland Rolling-Mill Co., 17 Fed. 426, cited by appellant, the term ‘as soon as possible’ means ‘with all reasonable diligence’ or ‘without unreasonable delay.’ ”

Free access — add to your briefcase to read the full text and ask questions with AI

Western Land Roller Co. v. Schumacher, 36 N.W.2d 777, 151 Neb. 166, 1949 Neb. LEXIS 75 (Neb. 1949).

36 N.W.2d 777 (Western Land Roller Co. v. Schumacher) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Omaha Public Power District v. Darin & Armstrong, Inc.
288 N.W.2d 467 (Nebraska Supreme Court, 1980)
Olson v. Pedersen
231 N.W.2d 310 (Nebraska Supreme Court, 1975)
Siefford v. Housing Auth. of City of Humboldt
223 N.W.2d 816 (Nebraska Supreme Court, 1974)
Snyder v. Lincoln
55 N.W.2d 614 (Nebraska Supreme Court, 1952)