Henton v. Nokes

603 N.W.2d 1, 258 Neb. 230, 1999 Neb. LEXIS 213
CourtNebraska Supreme Court
DecidedDecember 3, 1999
DocketS-97-1203
StatusPublished
Cited by30 cases

This text of 603 N.W.2d 1 (Henton v. Nokes) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Henton v. Nokes, 603 N.W.2d 1, 258 Neb. 230, 1999 Neb. LEXIS 213 (Neb. 1999).

Opinion

Miller-Lerman, J.

NATURE OF CASE

Robert E. Henton and Delores M. Henton, doing business as Prairie View Development, brought suit to enforce a construction lien against Laura H. Nokes in connection with a house the Hentons built for Nokes in McCook, Nebraska. Nokes counterclaimed against the Hentons for damages from breach of contract. The district court for Red Willow County found generally in favor of the Hentons on their construction lien claim and dismissed Nokes’ counterclaim.

Nokes appealed to the Nebraska Court of Appeals which, in Henton v. Nokes, No. A-97-1203, 1999 WL 294488 (Neb. App. May 11, 1999) (not designated for permanent publication), affirmed the trial court’s decision as to the Hentons’ construction lien claim, but reversed the trial court’s dismissal of Nokes’ counterclaim and remanded the cause with directions to the district court to enter a judgment on Nokes’ counterclaim in the amount of $7,998.68.

The Hentons petitioned for further review of the Court of Appeals’ decision on the basis that the Court of Appeals erred in applying a de novo rather than a clearly erroneous standard of review to its appellate evaluation of Nokes’ counterclaim and in holding that Nokes was entitled to breach of contract damages in the amount of $7,998.68. Nokes did not cross-appeal seeking further review of the Court of Appeals’ affirmance of the judgment in favor of the Hentons on their construction lien claim, and accordingly, that ruling is affirmed. We granted the Hentons’ petition for further review and now reverse the Court of Appeals’ decision granting relief to Nokes on her counterclaim.

STATEMENT OF FACTS

The Hentons sold two adjoining lots in McCook, Nebraska, to Nokes, upon which Nokes planned to build a house in which her *232 in-laws would live. The Hentons agreed to coordinate the construction of the house.

Nokes selected a floor plan and photograph of the type of house she wanted to build, and the Hentons then ordered blueprints. Neither the floor plan nor the blueprints included a basement, but Nokes, who had no training in architecture or engineering, drew up a sketch of a house modified to include a basement and provided it to the Hentons. The Hentons then arranged for construction of the house, including the hiring of a subcontractor, Daniel Rempel.

On April 24,1994, at the office of Nokes’ attorney, Nokes and the Hentons signed a six-page document (the Agreement) pursuant to which the Hentons agreed to build the house for a total of $132,224. The Agreement provided that the house would be built “in conformity with the plans, drafts, blue prints, specifications, and explanations thereof, which are hereunto annexed and made a part hereof.”

The record shows that Nokes met with Delores Henton numerous times during the construction of the house. At those times, Delores Henton and Nokes would review the work in progress and the pending bills, and Nokes would pay up to 90 percent of the amount then due. Nokes performed a walk-through of the house in early October 1994 and sent the Hentons a letter, dated October 6, 1994, outlining problems that needed to be corrected. The uncontroverted testimony of Delores Henton at trial was that the majority of the problems listed in the letter were corrected and that she had not been advised of additional problems.

Although not listed in the October 6, 1994, letter, it was established without contradiction at trial that the floor under the guest room sagged and that the sagging occurred because the floor was inadequately supported. The parties stipulated that Nokes spent $7,998.68 to repair it.

On or about October 1, 1994, Nokes’ in-laws took possession of the house. On November 22, the Hentons presented Nokes with a final statement which asserted that an additional $22,177.71 was due, consisting of $9,320.10 due under the original agreement and $12,857.61 attributed to “extras.” Nokes refused to pay.

*233 On January 17, 1995, the Hentons recorded a construction lien against the house in the amount of $21,222.82, and on February 27, they filed the petition in the instant case. In her answer, Nokes denied, inter alia, that she had received all the credits to which she was entitled. She also counterclaimed for an accounting and for expenses incurred due to contractual breaches by the Hentons, including “the contracted labor and materials which must be paid in the future to correct faulty work and to complete the house.”

On October 2, 1997, following a 2-day trial, the district court found generally for the Hentons. The court concluded that Nokes was indebted to the Hentons in the amount of $20,252.33, which consisted of the $9,320.10 claimed by the Hentons as the balance due pursuant to the original contract, plus an additional $10,932.23 for “extras.”

The district court also found that Nokes’ counterclaim should be dismissed. The district court’s decree stated:

The Court finds that many of the difficulties in the construction were of the Defendants [sic] making. The Court specifically finds that the Defendant ordered the major subcontractor to not place a beam which would reinforce the first floor of the home. The contractor clearly had the beams on site and was ready to use them in the construction until ordered not to by the Defendant. The Court further finds that the subcontractor, Rempel, used his best efforts in obtaining a system which would support the main floor, and, attempted to have the Defendant use a truss system which would fully support the floor. The Defendant wanted to save costs by using the method that was used. Had the Defendant accepted the beam, most of the structural problems that arose would not have arisen, and she can not [sic] be now heard to complain that the house has defects created by her decision. . . .
The Court has no difficulty in accepting the testimony of Bob Hinde [an architect called by Nokes who testified as an expert witness as to the quality of the construction of the house], but the Court finds that in light of the Defendant’s decision to not use the beam in the first place, *234 his testimony becomes unnecessary for the Court to reach its decision.

Nokes appealed the district court’s decision to the Court of Appeals, asserting eight assignments of error which the Court of Appeals

restated and summarized into the following five: The district court erred in (1) finding that the Hentons constructed the house as provided in the contract; (2) failing to correctly assess charges, credits, and penalties; (3) finding that the Hentons pled or proved the existence of subsequent oral change orders; (4) overruling Nokes’ motion for new trial; and (5) failing to “clearly set forth findings of fact and conclusions of law in the Decree.”

Henton v. Nokes, No. A-97-1203, 1999 WL 294488 at *3 (Neb. App. May 11,1999) (not designated for permanent publication).

In its unpublished opinion, the Court of Appeals concluded for its standard of review applicable to the case that an action to foreclose a construction lien is one grounded in equity and that

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nathan Paul Valin v. State of Iowa
Court of Appeals of Iowa, 2021
Bloedorn Lumber Co. v. Nielson
300 Neb. 722 (Nebraska Supreme Court, 2018)
Bloedorn Lumber Co. of N. Platte, Corp. v. Nielson
300 Neb. 722 (Nebraska Supreme Court, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
603 N.W.2d 1, 258 Neb. 230, 1999 Neb. LEXIS 213, Counsel Stack Legal Research, https://law.counselstack.com/opinion/henton-v-nokes-neb-1999.