Nebraska Statutes

§ 25-1216 — Evidence; instrument; written and printed matter; writing controls

Nebraska § 25-1216
JurisdictionNebraska
Ch. 25Courts; Civil Procedure

This text of Nebraska § 25-1216 (Evidence; instrument; written and printed matter; writing controls) is published on Counsel Stack Legal Research, covering Nebraska primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Neb. Rev. Stat. § 25-1216 (2026).

Text

When an instrument consists partly of written and partly of printed form, the former controls the latter, where the two are inconsistent.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lange Industries, Inc. v. Hallam Grain Co.
507 N.W.2d 465 (Nebraska Supreme Court, 1993)
114 case citations
Charley v. Farmers Mut. Ins. Co. of Nebraska
366 N.W.2d 417 (Nebraska Supreme Court, 1985)
13 case citations
Niedbalski v. Board of Education of School District No. 24
418 N.W.2d 565 (Nebraska Supreme Court, 1988)
7 case citations

Legislative History

Source: R.S.1867, Code § 340, p. 451; R.S.1913, § 7908; C.S.1922, § 8850; C.S.1929, § 20-1216; R.S.1943, § 25-1216. Cross References: Commercial paper, see section 3-114, Uniform Commercial Code. Annotations: In a typed contract, writing subsequent to the typing controls where there is a conflict between the typed and written provisions thereof. Spencer-O'Neill House, Inc. v. Denbeck, 196 Neb. 456, 243 N.W.2d 767 (1976). Typewriting controls printed form where two are inconsistent. Jacobsen v. Farnham, 155 Neb. 776, 53 N.W.2d 917 (1952). Typewriting is writing within the contemplation of the statute. Mack Investment Co. v. Dominy, 140 Neb. 709, 1 N.W.2d 295 (1941); New Masonic Temple Assn. v. Globe Indemnity Co., 134 Neb. 731, 279 N.W. 475 (1938). Sewer contractor could recover for sheeting lumber left in trench by city engineer's order, where payment was provided for in specifications, though contract provided no extras would be allowed for sheeting left in trench. Petersen v. City of Omaha, 120 Neb. 219, 231 N.W. 763 (1930). Where first paragraph of conditions of builder's bond is in typewriting complete within itself, and inconsistent provisions are in fine print as part of blank form evidently not intended to be used, typewritten part controls. American Surety Co. v. School Dist. No. 64 of Douglas Co., 117 Neb. 6, 219 N.W. 583 (1928). Where printed part of land contract says "good title of record," but typewritten part says "title satisfactory to attorney" of purchaser, latter prevails. Flower v. Coe, 111 Neb. 296, 196 N.W. 139 (1923).

Nearby Sections

15
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Nebraska § 25-1216, Counsel Stack Legal Research, https://law.counselstack.com/statute/ne/25-1216.