Lofton v. Don J. Trahan, Inc.
This text of 399 So. 2d 818 (Lofton v. Don J. Trahan, Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
T. E. LOFTON, Jr.
v.
DON J. TRAHAN, INC. and Don J. Trahan.
Court of Appeal of Louisiana, First Circuit.
*819 James C. Walker, Jr., Houma, for plaintiff and appellee.
Eddie N. Pullaro and Robert Cuccia, Houma, for defendants and appellants Don J. Trahan, Inc. and Don J. Trahan.
Maurice Mathieu, Houma, for third party defendants Vernon Hutchinson and Houma Sheet Metal, Inc.
Gerald F. Lofaso and Richard P. Mire, Houma, for third party defendant Chester Nixon.
Joseph J. Piccione, Lafayette, for third party defendant Lafayette Woodworks, Inc.
Jerry H. Schwab, Houma, for third party defendant Top's Woodwork & Supply, Inc.
Before COVINGTON, CHIASSON and LEAR, JJ.
LEAR, Judge.
This suit was filed alleging breach of a construction contract.
Plaintiff, T. E. Lofton, Jr., and defendant, Don J. Trahan, Inc., entered into a contract for construction of a residence in Terrebonne Parish, Louisiana. The contract set the approximate cost of the building at $113,200.00, including defendant's commission. After completion of the building, plaintiff signed an acceptance of the contract or performance except for some twenty-two alleged defects. By letter, some month and a half later, plaintiff informed defendant of some twelve defects which had not been corrected.
Plaintiff alleges that the commission to defendant was for procuring and supervising laborers, subcontractors and suppliers of materials, including payment of sums due for work and supplies.
Plaintiff also sues Don J. Trahan individually, alleging that certain sums advanced to this defendant for payment of materials were misused by defendant, resulting in materialman's liens being filed against plaintiff's property. Plaintiff seeks judgment for $25,750.00 for unearned commission and defects in workmanship and materials plus $10,000.00 for damage to plaintiff's credit and reputation. Defendant answered the petition by a general denial and reconventional demand, seeking judgment for $8,938.16 for funds still due under the contract.
Defendant further filed a third party demand against eight subcontractors for judgment in the amount of any judgment which may be cast against defendant and in favor of the original plaintiff.
After several days of trial, the court rendered judgment in favor of plaintiff and against defendants in the sum of $8,855.00 and further authorized plaintiff to withhold the sum of $7,801.76 representing the amount of the two liens filed against plaintiff's property. Judgment on the reconventional demand was in favor of plaintiff in reconvention and against T. E. Lofton, Jr. in the sum of $8,002.10. All third party demands were disposed of either during the trial by exceptions or in the judgment after trial in favor of the subcontractors.
*820 The trial court, in a lengthy and well reasoned opinion, which we adopt in part, held as follows:
"The defense of this lawsuit by defendant is twofold. First, defendant contends that the contract entered into by the defendant corporation and plaintiff is a cost plus contract and as such any defects in workmanship or materials are the responsibility of plaintiff unless the contrary has been stipulated to in the contract. A copy of the contract agreement is filed in the record and it is clear from a reading thereof that there is nothing in the contract stipulating who will be responsible for the cost of correcting defects in workmanship or materials. Defendants cite several cases which hold that while some mistakes will be made in construction work, the cost of correcting the mistakes is properly included in the amount to be paid to the contractor on a cost plus job. (See Schroeter v. O'Steen, 94 So.2d 556 (2nd [Cir.] [La.App.] 1957), Pennington v. Campanella, 180 So.2d 882 (1st [Cir.] [La.App.] 1965), Delta Paving Company v. Woolridge, 209 So.2d 581 (4th [Cir.] [La.App.] 1967). That is to say, the owner must bear the expenses of correcting the mistakes made in construction on a cost plus contract, unless it has been agreed to differently in the contract.
"The court recognizes that to be the law of this state and would apply it in this case except for the fact that a stipulation was entered into during the trial which the court understands to mean that the responsibility for the satisfactory performance of the contract rests on the contractor and not the owner. The transcript shows that on pages 218 through 221 it was stipulated by the parties that the defendant would be entitled to the sum of $8,002.00 but only in the event that this court finds that the residence has been constructed satisfactorily. The court will state at this time that in its opinion the residence was not constructed satisfactorily in that there were several defects amounting to and costing several thousands of dollars to remedy. Therefore, the court is of the opinion that while this contract, when it was entered into, was a cost plus contract, by virtue of the stipulation it was the intent of the parties that Mr. Trahan would be responsible for the satisfactory construction of this residence and that he would be responsible for whatever defects occurred in carrying out and performing the agreement between the parties. By stipulating that there would be $8,002.00 due and owning him, he was also stipulating that it was his responsibility to perform the job satisfactorily. The stipulation in essence placed the responsibility for performing the job satisfactorily, which included the correction of defects, squarely upon the shoulders of the contractor and not upon the owner. Therefore, the court cannot apply the ruling of law announced by the appellate courts in the cases cited by defendants.
"The second line of defense by defendants is that since Mr. Lofton has accepted and taken possession of the premises as being substantially complete that said acceptance of the residence in its then present condition voided any claim by Mr. Lofton for breach of contract. The court admits that there was an acceptance of the residence by Mr. Lofton as being substantially completed, but the acceptance was conditional and qualified in that there was attached to the acceptance a punch list of mistakes and defects that Mr. Lofton felt should be corrected by the contractor. The court agrees. Because the acceptance was conditional and qualified by Mr. Lofton, the court feels that this defense raised by defendants cannot prevail. Defendant corporation, in the opinion of this court, was still obligated and required by its agreement with Mr. Lofton to complete the house satisfactorily. Said corporation was legally responsible to correct the mistakes set out in the punch list attached to the acceptance, and its failure to do so constitutes a failure and breach of the agreement with plaintiff.
"For the above stated reasons the court has concluded that neither defense raised by defendants can prevail. Defendant corporation is liable for any defects in the construction of this residence and whatever sums of money are required to correct the mistakes is the responsibility of said corporation.
*821 QUANTUM
"The court made a personal visit to the residence, accompanied by the attorneys and parties, and made a visual inspection of the areas of complaint that are in dispute in this lawsuit. The court will consider each item separately.
DRIVEWAY
"An examination of the driveway convinces the court that there were serious defects existing in the slab and that it appeared to be in a condition of deterioration.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
399 So. 2d 818, 1981 La. App. LEXIS 4279, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lofton-v-don-j-trahan-inc-lactapp-1981.