Pennington v. Campanella
This text of 180 So. 2d 882 (Pennington v. Campanella) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
Corrie C. PENNINGTON, Plaintiff-Appellee,
v.
Thomas CAMPANELLA, Defendant-Appellant.
Court of Appeal of Louisiana, First Circuit.
*883 Warren L. Mengis, of Cole & Mengis, Baton Rouge, for appellant.
Sylvia Roberts, of H. Alva Brumfield, Baton Rouge, for appellee.
Before ELLIS, LOTTINGER, LANDRY, REID and BAILES, JJ.
BAILES, Judge.
Plaintiff, Corrie C. Pennington, brings this action against F. O. Jordan, d/b/a *884 River Jordan Pools, and Thomas Campanella to recover the sum of $6,659.63, plus $25 for preparation and recordation of a lien under R.S. 9:4801 et seq. After trial of this matter in the lower court judgment was rendered in favor of the plaintiff and against the defendant, Thomas Campanella, in the amount of $1,913.63, together with legal interest from date of judicial demand until paid. Both parties appeal.
For the purpose of brevity, Corrie C. Pennington will most of the time be referred to as plaintiff; Thomas Campanella as defendant; and F. O. Jordan, d/b/a River Jordan Pools, as Jordan.
In July, 1956, a contract was entered into between Campanella and Jordan for the construction of a swimming pool by Jordan on home property of the defendant in Baton Rouge. Within a few days after this contract was entered into Jordan entered into a verbal contract with the plaintiff, a masonry contractor, for the construction of the pool on a cost plus basis. It appears that the plaintiff had never before built a swimming pool and for that reason was not interested in making any commitment to Jordan on a construction contract other than on the basis of cost plus ten. Under the contract the plaintiff was to furnish all labor and material and Jordan was to pay him the cost of all such material and labor plus ten per cent.
Plaintiff built the pool and a short time later filed a labor and materialman's lien against defendant's property after he had not been paid by Jordan. Then he instituted this proceeding to have his lien recognized and to recover the sum of $6,659.63, plus $25 to cover the cost of filing the lien. This amount was later reduced by plaintiff in his testimony to the sum of $4,924.26. Defendant answered and made a reconventional demand against plaintiff asking for $8,245, basing said reconventional demand upon the allegations that he had been caused mental pain and anguish at the hands of plaintiff for failing to properly fulfill the contract to construct the pool, that plaintiff caused damage to his property, and that because of the faulty manner in which the pool was constructed, it would be necessary to remove the pool and build another one. (The latter was not done. In fact, defendant began using the pool around Labor Day of 1956, and was still using the pool when the last hearing was held in this case in March of 1963.)
After answering plaintiff's petition, Jordan also reconvened. He alleged the same defects in construction as did defendant; and he further alleged that he contracted with plaintiff to build the pool for $3,000, that the cost to Jordan to complete the construction according to plans and specifications was $5,495 and that Jordan had paid plaintiff $1,500; therefore he was indebted to Jordan for the sum of $3,995.
On April 15, 1960, during the pendency of these proceedings, Jordan died. His wife, a Florida resident, refused to appear in substitution for her husband in this proceeding. Hence, this suit by plaintiff to enforce his lien and to recover from defendant the amount owed on his contract with Jordan.
The judgment of $1,913.63 was reached by the trial court in the following manner: (1) Plaintiff admitted that he had made errors in calculating the amount owed to him and reduced his claim to $4,924.26, (2) for various reasons, to be discussed infra, the trial court refused to allow plaintiff to recover certain items included in his claim for labor and materials, and (3) the trial judge found that certain sums paid to Jordan by defendant served to reduce the amount owed by defendant.
Assuming arguendo that he has a cause of action to recover damages, the record does not disclose that defendant proved that any damage had been done to his property as was alleged in his reconventional demand. Therefore, this claim is denied for lack of proof.
The trial court reduced plaintiff's claim in the amount of $263.74 for the reason *885 that this amount represents the cost of certain corrective work. We hold, as did the court in Schroeter v. O'Steen (La.App. 1957) 94 So.2d 556, that it is reasonable that some mistakes may be made on any job and certain work will have to be changed in order to meet the requirements of the contract, and in the absence of an express contrary agreement, such repair work is properly included in the amount to be paid to the subcontractor on the "cost plus" job.
The trial court reduced the claim by $42 because of an apparent error in charging Jordan in one-day for 24 hours labor performed by plaintiff's son; 8 hours each on three separate jobs. Plaintiff admitted that this was an error. The amount to be disallowed is 8 hours at $1.25 per hour or $10, not $42.
The trial judge further reduced plaintiff's claim by the amount of $165.74, giving as his reason, that, "The plaintiff further testified that he had not paid the electrician, Ike Smith, whose bill was in the amount of $165.74." The invoice submitted in evidence by the plaintiff to cover the work done by Ike Smith, who is an electrical contractor admittedly hired by plaintiff in order to carry out the contract with Jordan is $165.59. The record supports the statement of the trial judge to the effect that the bill of the electrician was not paid. However, by hiring the electrician, plaintiff incurred an obligation to pay for his services. Thus, his obligation to pay the electrician became a portion of his expense in performing the contract. The amount is allowed.
Coming now to the plaintiff's claims for $169 for insurance expense and for the ten per cent profit on the total cost of the work done by him rejected by the trial judge, we find no error in this holding. The plaintiff's lien and privilege is purely statutory and is found in R.S. 9:4801 et seq., as stated supra. The courts of this state have repeatedly held that the creation of the lien and privilege in favor of the lienor, the subcontractor in this case, is in derogation of common rights and must be strictly construed in favor of the person whose common rights are affected, i. e., the owner of the property. See: Alfred Hiller Co. v. Hotel Grunewald Co. (1920) 147 La. 129, 84 So. 520; Cole v. Schexnadire (1927) 163 La. 132, 111 So. 651; Casey v. Allain (1929) 9 La.App. 725, 120 So. 420; Price v. Lee (1929) 11 La.App. 291, 123 So. 458; Lawrence v. Wright (1929) 11 La. App. 703, 124 So. 697; Fowler Commission Co. v. E. J. Deas & Co. (1930) 13 La.App. 141, 127 So. 456; Southern Gas Line v. Dixie Oil Co. (1931) 16 La.App. 26, 133 So. 181; Conservative Homestead Ass'n v. Boyle (1931) 172 La. 878, 135 So. 663; Texas Lumber Co. v. E. D. Green Realty Co. (1932) 19 La.App. 585, 140 So. 828; Morehouse Lumber & Building Material Co. v. Jacob & Walker (1932) 177 La. 76, 147 So. 504; Callender v. Marks (La.App. 1936) 166 So. 891; Yellow Pine Lumber Co. v. Maniscalco (La.App.1942) 9 So.2d 320; Griffith v. Williams (La.App.1944) 19 So.2d 277; Hughes v. Will (La.App. 1948) 35 So.2d 241; Clarke v. Shaffett (La. App.1948) 37 So.2d 56; Graeme Spring & Brake Service, Inc. v. De Felice (La. App.1957) 98 So.2d 314; Lumber Products, Inc. v.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
180 So. 2d 882, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pennington-v-campanella-lactapp-1965.