Cole v. Schexnadire

111 So. 651, 163 La. 132, 1927 La. LEXIS 1605
CourtSupreme Court of Louisiana
DecidedJanuary 31, 1927
DocketNo. 28258.
StatusPublished
Cited by9 cases

This text of 111 So. 651 (Cole v. Schexnadire) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cole v. Schexnadire, 111 So. 651, 163 La. 132, 1927 La. LEXIS 1605 (La. 1927).

Opinion

OVERTON, J.

Plaintiff, on February 23, 1925, entered into a contract with J. M. Sutton for the erection of a residence on a lot belonging to the former in the city of Shreveport for the sum of $7,590. The contractor executed in favor of plaintiff a bond for the full amount of the contract with solvent surety. The bond furnished was a mere indemnity bond,’ in favor of plaintiff, and did not comply with Act 139 of 1922, under which the building was constructed, nor were the contract and bond recorded until after the building had been constructed and accepted, which was not within the time required by law, the law requiring that this be done either before the commencement of the work or not later than 30 days thereafter. Section 1 of Act 139 of 1922.

■ A number of persons and firms furnished material to the contractor to construct the building. Those who were not paid duly recorded their claims, with the proof thereof, and served attested accounts on the owner. Many, if not all of these, instituted suit against the owner and the contractor to recover judgment on their claims.

After the filing of the foregoing suits, plaintiff instituted the present proceeding, provoking a coneursus. He admits therein that, due to his failure to require the proper bond and to record the contract and bond within the time required by law,’ he is liable to those having claims against the building, but alleges that this liability does not exceed 50 per cent, of the amount of thé contract, or $3,795. He deposited this amount in court for the benefit of those enjoying privileges against the property, and prayed that those who had recorded their claims against it be cited to assert them, and that he have and recover judgment canceling all of the liens recorded against the building constructed and the lot upon which it is situated, and that those to whom said claims are due, so far as relates to him, be required to accept said fund, in proportion to their respective rights therein, in full settlement thereof. <

The claims recorded against the building and lot amount to $4,637.34, which is more than the amount deposited in court by plaintiff, that amount being, as stated, $3,795. The amount deposited is less than the various claimants contend plaintiff is required, under the law, to deposit. They have therefore refused to accept said deposit, as tendered, and contend that they are entitled, by reason of the failure of plaintiff to accept a proper bond and to record the bond and contract timely, to judgment against him for the full amount of their claims, with recognition of their liens on the building constructed and on the lot upon which it is located.

It is not disputed that the contractor owes the various claimants the amounts claimed by them. It is not disputed that the various claimants duly and timely recorded their claims and served sworn statements of them on plaintiff. It is not questioned that plaintiff paid the contractor the amount of the contract. The only dispute to be decided, as conceded by both sides and incorporated in the agreed statement of facts, is whether the various claimants are entitled, under the law, on the foregoing facts, to judgment against *135 plaintiff for their claims against the contractor, in full, with recognition of their liens, as furnishers of material on the building constructed and the lot on which it is located, or is plaintiff and his property liable to these claimants for only 50 per cent, of the amount of the contract.

The contract for the construction of the building was signed in 1925, and the building was constructed in that year-. The rights of the parties are therefore controlled by Act 139 of 1922. Section 1 of that act, inter alia, creates liens and privileges in favor, among others, of furnishers of material, on the building or other structure erected or repaired and on the lot on which it is situated. The same section provides that:

“The owners of such work shall require' of said undertaker, contractor, master mechanic, or engineer, a bond with good and solvent surety as follows: For all contracts not exceeding five thousand dollars the amount of the bond shall be the amount of the contract; for contracts over five thousand .dollars, and not exceeding one hundred thousand dollars the bond shall not be less than 50 per cent, of the contract. * * * ”

Section 2 of the act provides, among other things, for the recordation of the contract and bond, for the preservation of the privileges granted by the act, and for the convoking of a concursus.

Section 4 of the act provides that:

“If no objections are made by any of the recorded claimants to the sufficiency or solvency of the surety on the bond within ten days after the filing of said concursus, the court shall order its clerk to give to any party interested a certificate to that effect and on presentation of said certificate to the recorder of mortgages he shall cancel and erase all inscriptions created by the recordation of said contract, bond and claims.”

Section 5 of the act relates to the liability of the owner for accepting insufficient bond, or for failing to require a bond, or to duly and timely record the contract and bond, and reads as follows:

“If the bond is found to be insufficient in amount or not to have a proper and solvent surety, or if the owner fails to require a bond, or if he fails to record the contract and bond during the time herein provided, he shall be liable to subcontractors, journeymen, cartmen, truck-men, workmen, laborers, and mechanics and furnishers of material to the same extent as the surety would have been. And the privilege hereinbefore provided for if recorded as provided in section 2 hereof, shall remain in full force and effect until all claims against the building or other work erected on the land on which it is situated shall have been paid, unless otherwise ordered by the court. In all cases where surety has been furnished, the surety shall be entitled to make only the same defenses that the contractor for whom he signed the bond is authorized to make except as to the owner who has made payments in anticipation.”

From the foregoing, or, to be more specific, from section 1 of the act, it appears that where the contract is for $7,590, the amount of the contract in this case, then the owner must give bond with good and solvent surety for not less than 50 per cent, of the contract, or to state the amount in dollars, in this particular instance, for not less than $3,795. From the foregoing, or, more specifically, from section 5 of the act, it also appears that if the owner should fail to require a bond, meaning the bond that the law requires him to exact from the contractor, or if he should require the proper bond, but should fail to record it together with the contract, within the time prescribed by the act, or if the bond accepted by him should be found to be insufficient in amount, or not to have a proper and solvent surety, then the owner is liable to the same extent that the surety would have been, had he (the owner) complied with the requisites of the law.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brown v. Edwards
321 So. 2d 394 (Louisiana Court of Appeal, 1975)
Continental Casualty Co. v. Associated Pipe & Supply Co.
310 F. Supp. 1207 (E.D. Louisiana, 1969)
Courshon v. MAURONER-CRADDOCK INC.
219 So. 2d 258 (Louisiana Court of Appeal, 1969)
Capital Bank & T. Co. v. Broussard Paint & Wall. Co.
198 So. 2d 204 (Louisiana Court of Appeal, 1967)
McGee v. Missouri Valley Dredging Co.
182 So. 2d 764 (Louisiana Court of Appeal, 1966)
Pennington v. Campanella
180 So. 2d 882 (Louisiana Court of Appeal, 1965)
Southport Petroleum Co. v. Fithian
13 So. 2d 382 (Supreme Court of Louisiana, 1943)
Sklar v. Oil Incomes, Inc.
133 F.2d 512 (Fifth Circuit, 1943)
Sklar v. Lilly-Thompson Drilling Corp.
45 F. Supp. 470 (W.D. Louisiana, 1942)

Cite This Page — Counsel Stack

Bluebook (online)
111 So. 651, 163 La. 132, 1927 La. LEXIS 1605, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cole-v-schexnadire-la-1927.