Charbonnet v. Ochsner

246 So. 2d 844, 258 La. 507, 1971 La. LEXIS 4541
CourtSupreme Court of Louisiana
DecidedMarch 29, 1971
Docket50713
StatusPublished
Cited by17 cases

This text of 246 So. 2d 844 (Charbonnet v. Ochsner) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Charbonnet v. Ochsner, 246 So. 2d 844, 258 La. 507, 1971 La. LEXIS 4541 (La. 1971).

Opinion

*511 DIXON, Justice.

The plaintiff, an architect and contractor, brought suit to recover the balance he claimed for certain remodeling work on defendant’s residence. The defense set up in the answer was that certain of the work was defective, and the balance was withheld pending satisfactory correction and completion. Both plaintiff and defendant set up in the pleadings that an attempt was made to settle their differences ; the plaintiff contended that the compromise amount was contingent on prompt payment by the defendant; the defendant contended that the compromise amount was contingent upon completion and correction of the work in a manner satisfactory to the defendant.

There was judgment in the district court for the plaintiff in the amount of $14,000. In a written opinion, the trial judge held that both the plaintiff and defendant were bound by the agreement they made on October 25, 1967 to settle their differences for $19,000. (A partial payment was made shortly after October 25 by the defendant in the amount of $5,000, leaving the $14,-000 for which the district court rendered judgment). The trial court further found that the defendant failed to prove either that there was substantial work to be completed, or that the damage complained of by the defendant was caused by the lack of skill or imprudence or negligence of the plaintiff.

The trial court found that the agreement made between the plaintiff and defendant in a conference on October 25 was “confirmed” in writing by the plaintiff in a letter or statement dated October 26, 1967, and “confirmed” by the defendant in a letter to plaintiff’s attorney dated February 14, 1968. This finding was in spite of the fact that, continually throughout the trial, the attorneys for both the plaintiff and the defendant pointed out to the trial judge that there was no meeting of the minds between the plaintiff and the defendant, and that the “compromise” did not comply with the requirements of Civil Code Article 3071 which provides: “This contract must be reduced into writing.” 1

*513 The Court of Appeal affirmed, holding that there had been a compromise settlement between the plaintiff and defendant. 236 So.2d 86. The Court of Appeal held that the trial court had not committed manifest error in finding that the defendant had failed to prove the plaintiff guilty of “unworkmanlike” performance, and had failed to prove that the faulty construction complained of by the defendant was caused by lack of skill or negligence on the plaintiff’s part. The Court of Appeal found, in addition, that Louisiana jurisprudence placed ultimate responsibility on the owner for errors or mistakes made by the contractor on “cost-plus” contracts. 2

The “compromise agreement” referred to in this case was never completed. It was not reduced to writing by the parties, as required by C.C. 3071, and the parties never did agree on the same thing. The contractor’s testimony made it abundantly clear that his oral agreement to compromise was contingent on prompt payment. The defendant’s testimony, and his position throughout the litigation, has been that he agreed to pay the $19,000 only if the plaintiff corrected certain deficiencies that had appeared in the work.

The trial court found that the statement sent by the plaintiff to defendant on October 26, pursuant to the conference of October 25, 1967, did not indicate that the plaintiff expected prompt payment, because it contained only the words “balance due at this time $19,000.” The trial court said that “there is no mention of the fact that the ‘balance due’ was payable at that time.” This seems to be a distinction without a difference. At any rate, plaintiff and defendant were then, and are still, in disagréement about what correctional work plaintiff was to do.

The “revised statement as per agreement” typed by plaintiff on October 26 and mailed to defendant, claiming the balance of $19,000 does not satisfy the codal requirement of C.C. 3071 that the “contract must be reduced into writing.” Nor does the letter from defendant to plaintiff’s lawyer, dated February 14, 1968. That letter demonstrates that the parties had not reached a meeting of the minds on October 25, 1967.

In brief plaintiff argues that defendant alleges in answer and reconventional demand a compromise and is bound, under C.C. 2291, by his judicial confession.

It is true that defendant alleged an agreement between Ochsner and Charbonnet. Defendant alleged the agreement was that $19,000 would be “due, owing and payable to Charbonnet” when certain correc *515 tions and remedial work was done, and that Charbonnet failed to live up to his agreement.. ■

Plaintiff in answer to «conventional demand admitted that plaintiff and defendant agreed to a settlement of $19,000, but denied the other allegations concerning the agreement.

The.judicial confession “cannot be divided against him” (against the pleader), says C.C. 2291. Defendant further alleges in his r'e'conventional demand that it would cost $19,000 to repair the bad work for which plaintiff' is responsible. Plaintiff cannot “divide” defendant’s answer, but must fairly construe the whole answer, and not merely those allegations which, considered alone and without the further allegations in the same pleading, might he construed against the pleader.

Although the parties made an effort to compromise, they did not reach an agreement, and did not put an end to their differences. Their principal difference was about what was to be done to correct a condition in “bedroom #4.” The owner complained that doors that would not open and horizontal cracks in the sheetrock walls were caused by structural defects. The contractor called them “expansions,” and offered to fill the cracks and trim up the doors. This, said the owner, would be merely repetitious, having been tried twice before, and would not prevent a recurrence. The owner adduced evidence to show that bedroom #4 was located over an old kitchen that had been removed and replaced with a patio. Certain .exterior supports for the old structure had been removed and replaced with new supports in different places and numbers.

Plaintiff testified that $50.00 would cover the cost of repairs in the bedroom. Defendant’s evidence was to the effect that the racking of the structure was due to changes in the distribution of loads and inadequate structural support, and would cost about $8,000 to correct.

The Court of Appeal, 236 So.2d 86, cites the three cases (noted in footnote 2) as establishing the jurisprudence “that the owner is ultimately responsible for errors or mistakes made on a ‘cost-plus’ contract.”

We make no attempt here to announce any broad rule with reference to the relationship between the owner and contractor on cost-plus contracts. We need only to point out that plaintiff was not only a contractor. He is an architect. The case before us is not one in which an owner employs a craftsman to do certain remodeling around the house.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Feingerts v. State Farm Mutual Automobile Insurance
117 So. 3d 1294 (Louisiana Court of Appeal, 2013)
Elder v. Elder & Elder Enterprises, Ltd.
948 So. 2d 348 (Louisiana Court of Appeal, 2007)
LeBlanc v. State Farm Ins. Co.
878 So. 2d 715 (Louisiana Court of Appeal, 2004)
Walker v. Air Liquide America Corp.
113 F. Supp. 2d 983 (M.D. Louisiana, 2000)
Walk Haydel & Assocs. v. Coastal Power
720 So. 2d 372 (Louisiana Court of Appeal, 1998)
Parich v. State Farm Mutual Automobile Insurance
919 F.2d 906 (Fifth Circuit, 1990)
Williams v. Winn Dixie
447 So. 2d 8 (Louisiana Court of Appeal, 1984)
Nguyen v. Lengsfield Bros., Inc.
417 So. 2d 525 (Louisiana Court of Appeal, 1982)
Carter v. Mule
346 So. 2d 882 (Louisiana Court of Appeal, 1977)
St. Amand v. Marriott Hotel, Inc.
430 F. Supp. 488 (E.D. Louisiana, 1977)
Morrow v. American Bank & Trust Company
397 F. Supp. 803 (M.D. Louisiana, 1975)
Senegal v. Delahoussaye
311 So. 2d 58 (Louisiana Court of Appeal, 1975)
Foster v. Soule
310 So. 2d 170 (Louisiana Court of Appeal, 1975)
Lytle v. Commercial Insurance Co. of Newark, NJ
285 So. 2d 289 (Louisiana Court of Appeal, 1973)
Dunham Concrete Products, Inc. v. Donnell Construction Co.
268 So. 2d 104 (Louisiana Court of Appeal, 1972)
Zeringue v. Liberty Mutual Insurance Company
248 So. 2d 83 (Louisiana Court of Appeal, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
246 So. 2d 844, 258 La. 507, 1971 La. LEXIS 4541, Counsel Stack Legal Research, https://law.counselstack.com/opinion/charbonnet-v-ochsner-la-1971.