Welded Construction, L.P. v. The Williams Companies, Inc.

CourtUnited States Bankruptcy Court, D. Delaware
DecidedFebruary 4, 2025
Docket19-50194
StatusUnknown

This text of Welded Construction, L.P. v. The Williams Companies, Inc. (Welded Construction, L.P. v. The Williams Companies, Inc.) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, D. Delaware primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Welded Construction, L.P. v. The Williams Companies, Inc., (Del. 2025).

Opinion

IN THE UNITED STATES BANKRUPTCY COURT FOR THE DISTRICT OF DELAWARE In re: Chapter [1 WELDED CONSTRUCTION, L.P., et. al., Case No. 18-12378 (LSS) Debtors. (Jointly Administered)

WELDED CONSTRUCTION, L-P., Plaintiff, Adv. Pro. No. 19-50194 (LSS) v. THE WILLIAMS COMPANIES, INC., WILLIAMS PARTNERS OPERATING LLC, and TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC., Defendants.

OPINION Introduction This is a multi-million dollar contract dispute arising out of the construction of a natural gas pipeline in the Commonwealth of Pennsylvania. ‘The contractor, Welded Construction, L.P. “Welded” or “Debtor”), and the owner of the pipeline, Transcontinental Gas Pipe Line Company, LLC (“Transco”), each assert the other breached the construction contract and seek damages and penalties, as appropriate. Debtor’s claims are deceptively simpie: it billed for services performed and costs incurred under the contract and seeks the balance of unpaid invoices. Transco asserts both that Debtor billed for items not compensable under the contract and that Debtor’s poor

performance under the contract negates amounts owed. ‘Transco concludes that it, not Debtor, is the net winner. After a ten-day trial, I am left to determine whether numerous categories of costs are compensable under the contract. While certain categories can be determined as a legal matter by review of the contract, certain items require determinations of fact. Having considered the evidence and the credibility of the witnesses presented both through testimony in court and by deposition designations, I make the following findings of fact and draw conclusions of law. I. BACKGROUND

A, Transco Decides to Build a Pipeline Transco is a natural gas transmission pipeline company that constructs, maintains and operates pipelines across the country. No later than May 2014,” Transco began planning the Atlantic Sunrise Pipeline Project (“ASR Project”)}—the construction of a 197 mile large-diameter intrastate natural gas pipeline running through the Commonwealth of Pennsylvania.’ This new pipeline would permit Transco to bring gas from the Marcellus Shale south to Transco’s existing pipeline system.*

| "This background contains my findings of fact as required by Federal Rule of Civil Procedure 52, made applicable by Federal Rule of Bankruptcy Procedure 7052. Additional factual findings will be made when addressing specific disputes. 2 Aug. 28, 2023 Trial Tr. (Sztroin) 1128:19-22. 3 See generally D0007.0005. The ASR Project contained several pipelines of varying lengths. Aug. 28, 2023 Trial Tr. (Sztroim) 1130:9-11; D0007.0006. For example, Welded’s spreads were located on the Central Penn Line South, which had a total length of 128.3 miles. Aug. 28, 2023 Trial Tr. (Sztroin) 1132:25-1133:2. 4 Aug. 28, 2023 Trial Tr. (Sztroin) 1132:2-1133:7.

Tn May 2014, David Sztroin, Transco’s Project Manager for the portion of the ASR Project known as the Central Penn Line South, was engaged in planning activities, including (1) selecting the route of the pipeline, (2) performing environmental analyses and gathering data from the field to obtain necessary permissions and permits, (3) working with and obtaining permission and permits to construct the pipeline from federal and state agencies such as the Federal Energy Regulatory Commission and the Pennsylvania Department of Environmental Protection and (4) securing easements from landowners.° In June 2015, Transco hosted a full day pipeline job showing to which it invited approximately ten contractors capable of performing the required work.® An eighty-seven page slide presentation provided detailed drawings and specifications for the ASR Project and set out numerous permitting milestones culminating in the beginning of construction in July 2016 and an in-service date of July 2017.’ For bidding purposes, the ASR. Project was divided into seven spreads. Transco’s pipeline job showing occurred at a time when domestic pipeline work was starting to pick up. In 2015 and 2016, the pipeline industry for both liquids and natural gas was very competitive in the northeast/Marcellus Shale region.’ Large diameter pipeline work (over thirty-six inches), which was dormant in the United States for the prior ten years, provided significant opportunities for contractors and owners. But, the increased

5 Aug. 28, 2023 Trial Tr. Sztrom) 1128:20-1129:22. § See Aug, 28, 2023 Trial Tr. (Sztroin) 1131:7-14. 7 See generally DOOQ7. § 1)0007.0006. 9 See Aug, 22, 2023 Trial Tr. (Hawkins) 59:8-17.

demand also created limitations on the equipment and labor fronts as all companies were pulling from the same pools.” Welded was well positioned to take advantage of the abundance of work. It had fifty years of experience in the pipeline business, was centrally located in Ohio, had yards from Michigan to Pennsylvania and an experienced superintendent." As most relevant here, Welded owned a fleet of equipment that could service large diameter pipeline construction in the United States.” In the late summer, Welded received requests for construction proposals from two good customers: (1) the ASR Project from Williams Co. (“Williams”), Transco’s parent company, and (2) a thirty-six inch pipeline project in Ohio from Spectra," Welded submitted a proposal for both.’ Welded’s bid for the Spectra work was initially on a fixed price basis for two spreads.’> When approached to bid on three spreads, which required commitment of more of Welded’s equipment, Welded would only bid on the work on a cost-reimbursable plus fixed fee basis. Spectra eventually determined to move forward with

Aug. 22, 2023 ‘Trial Tr. (Hawkins) 59:8-61:16; Aug 23, 2023 ‘Trial Tr. (Wall) 389:24-390; Kirchen Dep, 35:17-24, Dec, 14, 2020; see Springer Dep. 51:22-52:12, Dec. 3, 2020; Sztroin Dep. 35:14-36:4, Dec. 3, 2020. 1 Aug. 22, 2023 Trial Tr. Hawkins) 60:7-18. ® Aug, 23, 2023 Trial Tr. (Wall) 391:23-392:11; see also Kirchen Dep. 36:8-13, 36:22-37:7, 41:12- 15, Dec. 14, 2020. 3 Aug. 23, 2023 Trial Tr. (Wall) 390:5—14. 4 Aug, 23, 2023 Trial Tr. (Wall) 390:15-18. 5 Aug, 23, 2023 Trial Tr. (Wall) 391:1-7.

Welded on a two-spread, fixed price contract and the parties began to finalize documentation. In the meantime, Welded heard nothing from Williams on the ASR. Project bid. It was not until November 2015, on the eve of signing the deal with Spectra, that Williams reached out to secure Welded’s participation on the ASR Project.'? Welded responded by detailing its current situation: (1) a meeting the following Monday to sign/accept the deal with Spectra, (2) the extremely high demand for Welded’s fleet and (3) the need to reach a preliminary understanding on the ASR Project by that Friday afternoon. To facilitate meetings, Welded sent a draft letter of intent (contingent award) outlining the compensation terms it would require to work on the ASR Project, including a cost-reimbursable fixed fee structure and cash flow neutrality for Welded." Transco returned a signed Letter of Intent to Rich Wall, Welded’s then-CEO, on November 7, 2015 (the following Saturday).” Aside from changing certain dates, the only major change from the draft letter of intent is that the proposed contract party is Transco, not Williams.” Based on the signed Letter of Intent, Welded declined to go forward with Spectra.

Aug. 23, 2023 Trial Tr. (Wall) 391:12-392:20. Aug, 23, 2023 Trial Tr. (Wall) 392:21-393:9, Aug, 23, 2023 Trial Tr. (Wall) 395:15-397:19; PXO13. PX009; PX638. In a Motion in Limine, ‘Transco objected to the use of parol evidence, arguing that the Contract is unambiguous and contains an integration clause such that looking beyond the four corners of the Contract is forbidden. Def.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Klaxon Co. v. Stentor Electric Manufacturing Co.
313 U.S. 487 (Supreme Court, 1941)
Mustang Pipeline Co. v. Driver Pipeline Co.
134 S.W.3d 195 (Texas Supreme Court, 2004)
Forrest Construction Co. v. Laughlin
337 S.W.3d 211 (Court of Appeals of Tennessee, 2009)
Burdette v. Drushell
837 So. 2d 54 (Louisiana Court of Appeal, 2002)
Collins v. Baldwin
1965 OK 55 (Supreme Court of Oklahoma, 1965)
Polymer Fabricating, Inc. v. Employers Workers' Compensation Ass'n
1998 OK 113 (Supreme Court of Oklahoma, 1998)
Zimmerman v. Harrisburg Fudd I, L.P.
984 A.2d 497 (Superior Court of Pennsylvania, 2009)
Jones v. J.H. Hiser Construction Co.
484 A.2d 302 (Court of Special Appeals of Maryland, 1984)
Lofton v. Don J. Trahan, Inc.
399 So. 2d 818 (Louisiana Court of Appeal, 1981)
Kerner v. Gilt
296 So. 2d 428 (Louisiana Court of Appeal, 1974)
LJL Transportation, Inc. v. Pilot Air Freight Corp.
962 A.2d 639 (Supreme Court of Pennsylvania, 2009)
Babby v. City of Wilmington Department of Police
614 F. Supp. 2d 508 (D. Delaware, 2009)
Stevens v. Harris
2002 OK 35 (Supreme Court of Oklahoma, 2002)
Prieto Corp. v. Gambone Construction Co.
100 A.3d 602 (Superior Court of Pennsylvania, 2014)
Scungio Borst v. 410 Shurs Lane Developers, LLC
106 A.3d 103 (Superior Court of Pennsylvania, 2014)
Commonwealth v. UPMC, Appeal of: UPMC
129 A.3d 441 (Supreme Court of Pennsylvania, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
Welded Construction, L.P. v. The Williams Companies, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/welded-construction-lp-v-the-williams-companies-inc-deb-2025.