Freedom Specialty Contracting v. Nichol Flats

28 Neb. Ct. App. 797, 950 N.W.2d 109
CourtNebraska Court of Appeals
DecidedSeptember 1, 2020
DocketA-19-646
StatusPublished
Cited by1 cases

This text of 28 Neb. Ct. App. 797 (Freedom Specialty Contracting v. Nichol Flats) is published on Counsel Stack Legal Research, covering Nebraska Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Freedom Specialty Contracting v. Nichol Flats, 28 Neb. Ct. App. 797, 950 N.W.2d 109 (Neb. Ct. App. 2020).

Opinion

Nebraska Supreme Court Online Library www.nebraska.gov/apps-courts-epub/ 09/01/2020 09:07 AM CDT

- 797 - Nebraska Court of Appeals Advance Sheets 28 Nebraska Appellate Reports FREEDOM SPECIALTY CONTRACTING v. NICHOL FLATS Cite as 28 Neb. App. 797

Freedom Specialty Contracting, Inc., appellee, v. Nichol Flats, LLC, appellant. ___ N.W.2d ___

Filed September 1, 2020. No. A-19-646.

1. Mechanics’ Liens: Foreclosure: Equity. An action to foreclose a con- struction lien is one grounded in equity. 2. Equity: Appeal and Error. In an appeal of an equity action, an appel- late court tries factual questions de novo on the record and reaches a conclusion independent of the findings of the trial court, provided, where credible evidence is in conflict on a material issue of fact, the appellate court considers and may give weight to the fact that the trial judge heard and observed the witnesses and accepted one version of the facts rather than another. 3. Breach of Contract: Damages. A suit for damages arising from breach of a contract presents an action at law. 4. Judgments: Appeal and Error. In a bench trial of a law action, the trial court’s factual findings have the effect of a jury verdict and will not be disturbed on appeal unless clearly wrong. 5. Contracts. Contract clauses requiring that any modifications to the con- tract be made in writing are valid and enforceable in Nebraska. 6. Contracts: Substantial Performance. Substantial performance is shown when all the essential elements necessary for the full accomplish- ment of the purposes of the contract have been performed with such an approximation to complete performance that the owner obtains substan- tially what is called for by the contract. 7. Mechanics’ Liens. Neb. Rev. Stat. § 52-136(1)(a) (Reissue 2010) speaks clearly as to the right to a construction lien only with respect to services performed or materials furnished, not with respect to services intended to be performed or materials intended to be furnished.

Appeal from the District Court for Douglas County: J. Michael Coffey, Judge. Affirmed as modified. - 798 - Nebraska Court of Appeals Advance Sheets 28 Nebraska Appellate Reports FREEDOM SPECIALTY CONTRACTING v. NICHOL FLATS Cite as 28 Neb. App. 797

Megan S. Wright and Austin L. McKillip, of Cline, Williams, Wright, Johnson & Oldfather, L.L.P., for appellant. Patrick T. Vint and Todd W. Weidemann, of Woods & Aitken, L.L.P., for appellee. Moore, Chief Judge, and Pirtle and Arterburn, Judges. Pirtle, Judge. INTRODUCTION Nichol Flats, LLC, appeals from a judgment of the dis- trict court for Douglas County in favor of Freedom Specialty Contracting, Inc. (Freedom), in the amount of $196,851.78. Freedom brought suit against Nichol Flats for foreclosure on a construction lien and for breach of contract. Nichol Flats brought a counterclaim for breach of contract and indemnifica- tion. After a bench trial, the district court found that Nichol Flats wrongfully terminated Freedom under the contract and that Freedom was entitled to foreclosure on its lien. The district court dismissed Freedom’s contract claim and Nichol Flats’ counterclaim with prejudice. For the foregoing reasons, we affirm as modified. BACKGROUND In August 2015, Nichol Flats and Freedom entered into a contract whereby Freedom would provide framing and drywall- ing services during the construction of a five-story apartment complex on North 16th Street in Omaha, Nebraska. Exhibit B of the contract provided the following baseline schedule for the completion of Freedom’s services: Floor Duration Start Date Finish Date Level 1 15 Days 11/3/2015 11/23/2015 Level 2 35 Days 11/10/2015 12/28/2015 Level 3 35 Days 12/9/2015 1/26/2016 Level 4 35 Days 1/8/2016 2/25/2016 Level 5 35 Days 2/8/2016 3/25/2016 Due to delay by other subcontractors, and the need for cer- tain work to be completed prior to framing and drywalling, - 799 - Nebraska Court of Appeals Advance Sheets 28 Nebraska Appellate Reports FREEDOM SPECIALTY CONTRACTING v. NICHOL FLATS Cite as 28 Neb. App. 797

the parties agreed Freedom was incapable of adhering to the dates provided in the baseline schedule. At some point in August 2016, prior to completion of the framing and drywalling, Freedom ceased performing work under the contract. The parties dispute the reason Freedom’s work was terminated. On October 27, 2016, Freedom filed suit for foreclosure on its construction lien in the amount of $262,469.04 and for breach of contract. On July 10, 2017, Nichol Flats filed an amended answer and counterclaim denying the allegations contained in Freedom’s complaint and alleging that Freedom breached the contract and owed indemnification costs to Nichol Flats. A bench trial took place on May 13 through 16, 2019. At trial, Freedom called John Jantzon, its project manager, as a witness. Jantzon testified that the construction manager, Tackett Company (Tackett), communicated with him regarding when the drywall work could commence. Under the contract, Freedom was to complete drywall for four floors of apart- ment units, and the metal framing on the first floor commer- cial space. Jantzon testified that if other “trades” or inspections are delayed, it sets back Freedom’s schedule because drywall work cannot be completed. Jantzon testified that exhibit B of the contract, the original baseline schedule, was the only schedule provided by Tackett and the only one he reviewed. No change order or construction change directive regarding Freedom’s schedule was ever provided to Jantzon. Jantzon testified that Freedom began its work after a May 19, 2016, lunch meeting that took place with representatives from Freedom, Tackett, and the Nichol Flats ownership. He acknowledged that some metal framing on the first floor was done previously in October 2015. Jantzon testified that there had been no discussion about amending Freedom’s schedule prior to the meeting. Jantzon denied that Tackett had notified Freedom that it could begin its work on May 15, 2016. He testified that the fifth floor was not ready at that time. Jantzon denied having ever - 800 - Nebraska Court of Appeals Advance Sheets 28 Nebraska Appellate Reports FREEDOM SPECIALTY CONTRACTING v. NICHOL FLATS Cite as 28 Neb. App. 797

agreed to a 15-day-per-floor schedule, which was ­referenced in an email from Tackett’s project manager, Trent Gumm. Jantzon testified that errors by other contractors on the proj- ect caused Freedom to perform additional work outside the scope of its contract. A change order request for $14,842 to add soffits outside of Freedom’s scope of work was refused by Nichol Flats. Another change order for $4,210 related to cor- ridor soffits was refused. Change order requests for $2,291 and $1,107 were approved by Nichol Flats. On August 11, 2016, Kirt Trivedi, a co-owner of Nichol Flats, sent Freedom an email stating, “This email is to provide Freedom the required seven day notice to meet the contractual schedule. This must be met or otherwise we will have to exer- cise other options.” Jantzon testified that he had not previously received any notice from Nichol Flats, or Tackett, alleging that Freedom was behind schedule. He testified that there were ongoing issues with other contractors’ work that prevented Freedom from completing the drywall on certain floors. On August 16, 2016, Freedom received an email from Trivedi with a list of tasks to complete in order to avoid “supplement[ation].” Supplementation, in this context, refers to Nichol Flats’ contractual right to outsource a portion of Freedom’s scope of work upon default or delay by Freedom in breach of the contract. The purpose of supplementation is to complete work that has delayed the project’s schedule.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lueder Construction Co. v. Lincoln Electric System
424 N.W.2d 126 (Nebraska Supreme Court, 1988)
Tilt-Up Concrete, Inc. v. Star City/Federal, Inc.
582 N.W.2d 604 (Nebraska Supreme Court, 1998)
Lange Industries, Inc. v. Hallam Grain Co.
507 N.W.2d 465 (Nebraska Supreme Court, 1993)
Bloedorn Lumber Co. of N. Platte, Corp. v. Nielson
300 Neb. 722 (Nebraska Supreme Court, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
28 Neb. Ct. App. 797, 950 N.W.2d 109, Counsel Stack Legal Research, https://law.counselstack.com/opinion/freedom-specialty-contracting-v-nichol-flats-nebctapp-2020.