Tilt-Up Concrete, Inc. v. Star City/Federal, Inc.

582 N.W.2d 604, 255 Neb. 138, 1998 Neb. LEXIS 190
CourtNebraska Supreme Court
DecidedJuly 31, 1998
DocketS-96-508
StatusPublished
Cited by42 cases

This text of 582 N.W.2d 604 (Tilt-Up Concrete, Inc. v. Star City/Federal, Inc.) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tilt-Up Concrete, Inc. v. Star City/Federal, Inc., 582 N.W.2d 604, 255 Neb. 138, 1998 Neb. LEXIS 190 (Neb. 1998).

Opinion

Gerrard, J.

Tilt-Up Concrete, Inc. (Tilt-Up), constructed improvements on real estate owned by Star City/Federal, Inc. (Star City). Upon Star City’s failure to make payments for the improvements, Tilt-Up filed a construction lien on the real estate and, subsequently, filed a petition for foreclosure in the district court. The district court found that Tilt-Up had a valid construction lien in the amount of $852,243.70 and entered judgment against Star City in that amount plus prejudgment interest and costs. Star City appeals. Because we determine in our de novo review that the district court erred in calculating the value of Tilt-Up’s construction lien at full contract damages, rather than at the reasonable value of services performed and materials furnished, we find that Tilt-Up is entitled to recover from Star City the sum of $235,418 and modify the judgment of the district court accordingly.

FACTUAL BACKGROUND

Tilt-Up is a contractor specializing in the construction of buildings using concrete wall panels that are cast on the building site and then “tilted up.” Steve Miers is the president of Tilt-Up. Tilt-up walls differ from precast walls in that the wall panels are formed and poured on casting slabs at the building site rather than at the factory.

Star City is the owner of the real estate upon which Tilt-Up constructed improvements pursuant to the authorization of H. Lee Gendler, now deceased. Gendler was a shareholder and the president of Star City, the company he formed to provide a building for lease to the U.S. General Services Administration *140 (GSA) to house the Lincoln, Nebraska, office of the Immigration and Naturalization Service (INS). The construction of the building was known as the INS Project. Gendler also was a shareholder and the president of Marathon Realty, Inc., and Olympic General, Inc. The INS project was the last of 5 construction projects performed by Tilt-Up for the Gendler companies during the 1989-93 time period and was 1 of over 50 projects for which Gendler obtained lump-sum price quotes from Tilt-Up for Tilt-Up’s normal scope of work. James Nicas was an employee of the Gendler companies and provided information to Miers for use in furnishing such price quotes.

In the fall of 1992, Miers informed Gendler that the GSA intended to lease a building in the downtown Lincoln area. Thereafter, Gendler negotiated an option to purchase the real estate upon which the INS Project was constructed. In early 1993, Gendler obtained the GSA Solicitation for Offers (SFO) for the INS Project and began to assemble a proposal to construct a building to lease to the GSA.

During early 1993, Nicas and Gendler began formulating Star City’s lease price proposal for the INS Project by determining construction and financing costs. In so doing, Nicas requested a price from Miers for the normal Tilt-Up scope of work, which included constructing the foundations and floor slabs, erecting structural steel supports and wall panels, and doing the caulking, grouting, and exterior finish work. Miers was provided with the SFO and the design information necessary to price Tilt-Up’s scope of work.

On April 27, 1993, Tilt-Up submitted to Nicas its first lump-sum bid on the INS Project. Nicas testified that he absolutely expected and wanted a price from Tilt-Up such that if Star City were awarded the project, Nicas could require Miers to perform the work for that amount. In order to facilitate the pricing of Tilt-Up projects, Nicas had developed a “Building Shell Estimating Form” (Form) upon which he delineated the specific work activities which Tilt-Up was to include in its bid price, and Nicas used it whenever Gendler was considering tilt-up-style construction for a project. Tilt-Up’s April 27 bid was submitted on Nicas’ Form and included within its scope the requisites listed under item 1, entitled “Tilt-Up Contract.”

*141 Tilt-Up’s April 27, 1993, bid conveyed Tilt-Up’s lump-sum price of $1,172,000.11 for the stated scope of work. The bid included the requisites listed under the “Tilt-Up Contract” portion, item 1 of Nicas’ Form. It also included the underslab fill sand, two elevator pits, and structural engineering for the INS Project. It did not include any accommodations for winter conditions, since Star City was anticipating an award of the INS Project in the first week of September and planned to have the tilt-up building shell completely erected by mid-November.

On approximately June 8, 1993, Nicas provided Miers with the information necessary to revise Tilt-Up’s price to add a loading dock. On June 15, Miers gave Nicas Tilt-Up’s revised price of $1,308,000. Nicas and Gendler each understood the $1,308,000 price to include the work described under item 1 of Nicas’ Form. Thereafter, Nicas and Gendler requested Miers to revise the price again to reflect an increase in the load-bearing capacity of the second floor of the building to 150 pounds. On June 29, Miers gave Nicas the revised Tilt-Up price of $1,352,800. Miers confirmed this price in writing on June 30. Nicas understood that the scope of work included in Tilt-Up’s $1,352,800 lump-sum price was everything included in the $1,308,000 price, plus an adjustment for the increase in the load-bearing capacity of the second floor.

In approximately October 1993, Star City submitted its best and final offer for the INS Project to the GSA. On November 23, the GSA formally awarded the INS Project to Star City. Within a day of the award, Nicas advised Miers that Tilt-Up should plan on constructing the project through the winter months. To accommodate winter construction conditions, Gendler agreed to pay a portion of the cost of the special fabrication of insulating blankets. Gendler also asked Miers to have the site work done and to have 6 to 8 inches of rock backfill placed on the site to alleviate potential moisture problems. Such work was considered by both Miers and Gendler to be extra work that was not included in Tilt-Up’s $1,352,800 price. Gendler later agreed to pay Tilt-Up’s cost plus 10 percent for the site work and cost plus 5 percent for the rock backfill work.

On December 15, 1993, Miers hand delivered to Gendler a letter setting forth Miers’ understanding of the changes that had *142 been made to the project since June and the extra work Gendler authorized and anticipated. In the letter, Miers confirmed and delineated the scope of his $1,352,800 price; proposed a unit price for the additional quantities of footings resulting from the changes in footing design ordered by Nel Hymans, Star City’s project engineer; and set forth the terms upon which Tilt-Up would perform other work items or extras that had been authorized and which were not within the scope of Tilt-Up’s $1,352,800 price. Upon receipt of Miers’ December 15 letter, Gendler did not express any disagreement with the pricing of the original scope of work, the pricing of the extras, or the delineation of the original scope and the extra work.

The next day, December 16, 1993, Miers discussed the project with Gendler and asked whether Tilt-Up should delay commencement of the footing work, which was a part of Tilt-Up’s normal scope of work, until after the December 18 groundbreaking ceremony. Gendler told Miers to get started and requested that Miers have on site for the groundbreaking some dirt-moving equipment for photographs.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Artisan Pools, Inc. v. Siemer
Nebraska Court of Appeals, 2026
Freedom Specialty Contracting v. Nichol Flats
28 Neb. Ct. App. 797 (Nebraska Court of Appeals, 2020)
Danford v. Lowe's Companies Inc
W.D. North Carolina, 2020
Travelers Indem. Co. v. Gonzalez Constr.
Nebraska Court of Appeals, 2019
Duke Builders, Inc. v. John K. Massey
Court of Appeals of Georgia, 2019
Duke Builders, Inc. v. Massey
831 S.E.2d 172 (Court of Appeals of Georgia, 2019)
Becher v. Hunt Irrigation
Nebraska Court of Appeals, 2019
Weyh v. Gottsch
303 Neb. 280 (Nebraska Supreme Court, 2019)
Waldinger Corp. v. WorldCom, Inc. (In Re WorldCom, Inc.)
466 F. App'x 28 (Second Circuit, 2012)
Fru-Con Construction Corp. v. Controlled Air, Inc.
574 F.3d 527 (Eighth Circuit, 2009)
Taylor v. Taylor
764 N.W.2d 101 (Nebraska Supreme Court, 2009)
In Re Worldcom, Inc.
382 B.R. 610 (S.D. New York, 2008)
Preston Refrigeration v. Omaha Cold Storage
742 N.W.2d 782 (Nebraska Court of Appeals, 2007)
Zepsa Construction, Inc. v. Randazzo
591 S.E.2d 29 (Court of Appeals of South Carolina, 2004)
Tilt-Up Concrete, Inc. v. Star City/Federal, Inc.
621 N.W.2d 502 (Nebraska Supreme Court, 2001)
Lincoln Lumber Co. v. Lancaster
618 N.W.2d 676 (Nebraska Supreme Court, 2000)
Sorenson v. Dager
601 N.W.2d 564 (Nebraska Court of Appeals, 1999)
Putnam v. Fortenberry
589 N.W.2d 838 (Nebraska Supreme Court, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
582 N.W.2d 604, 255 Neb. 138, 1998 Neb. LEXIS 190, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tilt-up-concrete-inc-v-star-cityfederal-inc-neb-1998.