Texas Bank & Trust Co. v. Campbell Brothers, Inc.

569 S.W.2d 35, 1978 Tex. App. LEXIS 3355
CourtCourt of Appeals of Texas
DecidedMay 31, 1978
Docket19489
StatusPublished
Cited by4 cases

This text of 569 S.W.2d 35 (Texas Bank & Trust Co. v. Campbell Brothers, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Texas Bank & Trust Co. v. Campbell Brothers, Inc., 569 S.W.2d 35, 1978 Tex. App. LEXIS 3355 (Tex. Ct. App. 1978).

Opinion

GUITTARD, Chief Justice.

This suit arose out of a contract for construction of an apartment project. The contractor, Campbell Brothers, Inc., stopped the work because of failure of the owner, San Mateo Properties, Inc., to make a progress payment pursuant to an application for payment presented by the contractor. The contractor sued the owner for the amount alleged to be due and also for damages for breach of contract, and joined as a defendant Texas Bank & Trust Company, alleging that the contractor had a lien superior to the deed of trust securing the bank’s construction loan. The owner and the bank counterclaimed against the contractor and the surety on the contractor’s performance bond, alleging breach by the contractor in failing to complete the contract and damages consisting of the excess of the cost of completion over the contract price. The jury’s answers to special issues were favorable to the contractor and the surety. From a judgment on this verdict, only the bank has appealed.

We hold that recovery by the owner and the bank was properly denied because the evidence supports the jury’s finding that the owner had failed to make payments as required by the contract when the contractor left the job, and the bank, as a co-obli-gee on the contractor’s performance bond, has no independent right to demand performance without payment of the amount due. We hold also that the trial court properly determined the contractor’s statutory lien to be superior because the evidence supports the jury finding that the contractor had commenced visible construction of the project before the bank recorded its deed of trust. In response to the contractor’s cross-point, we hold that the trial court properly declined to include in the amount secured by the contractor’s lien the contractor’s lost profit on work not performed. Accordingly, we affirm the judgment of the trial court in all respects.

1. Owner’s Claim for Breach of Contract

Although the owner has not appealed, we consider first the owner’s claim for breach of contract, since the bank’s position depends on the owner’s claim in some respects. For this purpose, we temporarily defer the bank’s claim that it has established grounds of recovery not available to the owner.

*37 The contract sued on provides for reimbursement of the contractor’s costs plus a fixed fee, with an overall limit of $2,636,-738. The owner is required to reimburse the contractor for costs as the work progresses on applications for payment submitted by the contractor. The contractor stopped the work on December 2, 1974, after the owner failed to pay the amount the contractor claimed to be due on application number 29, presented on November 1,1974.

In asserting a breach by the contractor, the bank attacks the jury’s answer to special issue number 15, by which the jury found that at the time the contractor terminated the work, the owner had failed to pay for work done or materials furnished under the contract contained in application for payment number 29. The bank contends that this finding has no support in the evidence, and, in the alternative, that it is contrary to the great weight and preponderance of the evidence, in that the evidence shows that no money was due from the owner because the contractor had earlier charged to the job more than $53,000 of work that was not within the scope of the contract.

Application number 29 states the amount of work “completed and stored to date” to be $2,091,746, and since the contractor admitted receiving payments aggregating $2,038,238, the indicated balance due would be $53,508. The bank argues that nothing was due to the contractor when it left the job because the work “completed and stored to date” was overstated by more than the amount of this balance. According to the bank, the following items are shown by the undisputed evidence to have been improperly included:

(1) $17,774 for work done on the site before the contract work began;
(2) $17,680 for a bond premium not included in the contract amount;
(3) $2,205 for a building permit not included in the contract amount;
(4) $36,067 for work done on the residence of George Jones, sole stockholder of the corporate owner, San Mateo Properties, Inc.

The aggregate amount of these claimed reductions is $73,726. The bank says that none of these items actually appeared in application number 29, but that the amounts were concealed within this application under the amounts stated for other items of work shown to have been done under the contract.

The contractor responds that there was no fraud or deception because all of the items in question were known and understood by the owner and all were sums legitimately due. The contractor insists that it had actually paid out the amounts in question for site work, bond premium, and building permit, and that all were properly charged against the owner. The contractor further asserts that it had actually done work on the Jones residence to the extent of $36,067, and that payments in this amount, as well as payments for the other items in question, had previously been credited to the owner and had been included in the total payments of $2,038,238, which the contractor had received. Thus, the contractor argues that it was entitled to apply the previous payments received to those disputed items rather than to amounts due strictly within the terms of the contract and that it was entitled to stop the work until payment of the balance was received. Moreover, the contractor asserts, there was no dispute concerning the work actually done in the period for which application number 29 was submitted. Consequently, it argues that neither the owner nor the bank could properly withhold payment for this work on the ground that previous payments, which had been credited by the contractor to other legitimate claims, were not applied to the amounts due under the contract in question.

With respect to the work done on the Jones residence, there is at least a dispute in the evidence as to whether any proceeds of the bank’s loan were used for that purpose. Jones testified that he paid approximately $79,000 of his own funds to the contractor in September, October and November of 1974. Thus, it would have been reasonable for the jury to conclude that although various applications for payment *38 included work on the residence as well as on the apartment project, the bank was not prejudiced because the amount of the residence work so chárged was more than offset by payment from Jones’ personal funds.

The owner’s obligation to make progress payments and the contractor’s right to stop the work if such payments are not made depend on the provisions of the contract documents. Article 14 of the contract provides:

The Contractor shall, at least ten days before each progress payment falls due, deliver to the Architect a statement, sworn to if required, showing in complete detail all moneys paid out or costs incurred by him on account of the Cost of the Work during the previous month for which he is to be reimbursed under Article 6 and the amount of the Contractor’s fee due as provided in Article 7, together with payrolls for all labor and all receipted bills for which payment has been received.

Article 15.1 provides further:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tilt-Up Concrete, Inc. v. Star City/Federal, Inc.
582 N.W.2d 604 (Nebraska Supreme Court, 1998)
Argee Corp. v. Solis
932 S.W.2d 39 (Court of Appeals of Texas, 1995)
In Re Moussa
93 B.R. 96 (N.D. Texas, 1988)
A. P. Ross Enterprises, Inc. v. Hynds Plumbing & Heating Co.
639 P.2d 526 (Nevada Supreme Court, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
569 S.W.2d 35, 1978 Tex. App. LEXIS 3355, Counsel Stack Legal Research, https://law.counselstack.com/opinion/texas-bank-trust-co-v-campbell-brothers-inc-texapp-1978.