South Builders, Inc. v. Brown

449 S.W.2d 542, 1969 Tex. App. LEXIS 2254
CourtCourt of Appeals of Texas
DecidedNovember 28, 1969
DocketNo. 4348
StatusPublished
Cited by4 cases

This text of 449 S.W.2d 542 (South Builders, Inc. v. Brown) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
South Builders, Inc. v. Brown, 449 S.W.2d 542, 1969 Tex. App. LEXIS 2254 (Tex. Ct. App. 1969).

Opinion

COLLINGS, Justice.

Edwin L. Brown, Lonnie E. Williams and W. A. Peavy, doing business on a State highway project, as subcontractors under the firm name of Brown, Peavy and Williams Company, filed suit against South Builders, Inc., the prime contractor on the job, alleging breach of their written contract. The plaintiffs sought to recover the full contract price for all work performed on the Haskell County contract, lost profits and the reasonable rental value of certain equipment which was allegedly idle while plaintiffs waited for defendant to furnish necessary crushed rock before plaintiffs could perform their part of the resurfacing project. Plaintiffs also sought to recover from defendant for blad-ing, grading and removing old concrete on a project in Jones County under a special contract with defendant. South Builders had previously filed a plea of privilege to be sued in Dallas County which was overruled in the trial court and on appeal. South Builders filed a cross action for claims of third parties against plaintiffs which it had paid, and for the excess cost over the contract price of completing plaintiffs’ portion of the subcontract after plaintiffs, at defendant’s direction, left the job.

The case was tried before a jury and based upon the verdict, judgment was rendered for plaintiffs for lost profits equaling the total amount anticipated for the whole Haskell County job; for idle equipment caused by appellant’s delay in furnishing material as agreed; for the amount due on another contract in Jones County, for sums due for extra work, plus the full contract price for all work performed by plaintiffs on the Haskell County job prior to their discharge by defendant on September 25, 1967, and for attorney’s fees. South Builders has appealed.

The Record shows that appellant, South Builders, entered into a contract with the State of Texas for resurfacing approximately ten miles of a highway in Haskell County, and thereafter entered into a contract with appellees to do dirt excavation work and preparation of the subgrade in final form prior to the laying of the surface materials thereon by appellant. The written contract between the parties provided that South Builders was to make payment of appellees’ payrolls and various other costs as same were incurred by ap-pellees, and that payments by South Builders of appellees’ expenses were to be deducted from credits otherwise accruing to appellees as they performed the work; that the State of Texas allows credit and makes payment as the work is performed and such payments were credited to ap-pellees as paid by the State. South Builders accounted to appellees in monthly estimates showing the work paid for by the State which was done by appellees and also showed the amount of expenses paid by South Builders on behalf of appellees. Under the written contract appellees were [544]*544to prepare the subgrade to State specifications to receive the first layer of roadway material; that preparation of the subgrade involved cutting down or filling up to a required level set by the State. Appellees also had the duty under the contract to achieve the proper density in the subgrade which involved processing the dirt and obtaining a proper mixture with water until it passed the State’s density requirement. When this had been accomplished, it became South Builders responsibility under its contract with the State to follow with a surface material. In the ten miles of highway in the rural section of the Haskell County job the surface material required to be put down by South Builders consisted of a flexible base crushed rock. South Builders had difficulty in furnishing the required flexible base material which would meet the specifications of the State. It is undisputed that the State engineers would not permit appellees to begin excavation in that portion of the City section where flexible base was to go on the sub-grade until August 14th. There was evidence to the effect that such flexible base material was not available on the rural portion of the contract until September 26, 1967. Appellees had continued working when possible on the job in the rural section and in the city section until September 25, 1967, at which time they were informed by a letter from South Builders that their work was not proceeding satisfactorily and, pursuant to an option provided in the contract, South Builders was taking over and would complete appellees’ portion of the job, whereupon appellees removed all of their equipment and filed this suit.

The computation of the amount of the judgment for appellees was arrived at as follows:

Items and amounts claimed by appellees:
For work done under Haskell County contract. $14,021.90
For total anticipated profit (on Haskell County Contract) . 11,932.94
Cost to appellees for idle equipment. 13,547.32
Extra work (not questioned) . 12,805.00
Attorney’s fees. 5,000.00
TOTAL. $57,307.16
Less Credits to South Builders:
For payments, including pay-rolls, insurance, equipment rental and 3rd party accounts paid by appellant . $36,287,29
Balance due appellees on Haskell job. 20,819.87
Balance due appellees from computation of charges and payments on Jones County job. 3,104.69
Total amount of judgment. $23,924.56

In answer to special issue No. 18 the jury found that the reasonable profit which Brown, Peavy and Williams would have realized from the Haskell County job, except for interference by South Builders, was $11,932.94. As above indicated, this was one of the items included in the judgment for appellees. In its first 9 points appellant complains of the lack of pleadings, evidence and of the insufficiency of the evidence to support submission of issue number 18, or the answer of the jury thereto; that it was, therefore, error to enter judgment based thereon; that it was error to submit issue number 18 because it was based upon improper measure of damages in a suit on a partially completed contract; that the finding of $11,932.94 constituted all of plaintiffs’ anticipated profit for the Haskell County job, which [545]*545was improper in this suit on a partially-completed contract; that it was error to award plaintiffs their full estimated profits on the entire Haskell County contract and in addition to allow plaintiffs the full contract price for all work done on the job by plaintiffs in the amount of $14,021.90 until the date plaintiffs left the job, because this allows plaintiffs a double recovery of profits; and that the court erred in granting plaintiffs judgment for lost profits in the amount of $11,932.94, because stipulations of the parties and the answers to other special issues conclusively show that South Builders expended more in reasonable and necessary costs in completing plaintiffs’ contract than the total contract price.

We sustain appellant’s point contending that the evidence, considered as a whole, is insufficient to support the finding of the jury in answer to special issue 18, concerning the loss of anticipated profits, and that such finding is against the great weight and preponderance of the evidence. Appellees did testify they would have realized profits in the amount of $11,932.94 from the Haskell County job but for interference by South Builders.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
449 S.W.2d 542, 1969 Tex. App. LEXIS 2254, Counsel Stack Legal Research, https://law.counselstack.com/opinion/south-builders-inc-v-brown-texapp-1969.